Noravan 40022020 kV and related substation Terms and conditions of Provided Investment Facilities Based on the Memorandum of Mutual Understanding signed on May 17 2006 between the Republic of Armenia and the Islamic Republic of Iran a Contract ID: 556413
Download Presentation The PPT/PDF document "Loan Project of Construction of Iran-Ar..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1Slide2
Loan Project of Construction of Iran-Armenia 400kV third power transmission line (“
Noravan
’’ 400/220/20 kV
) and related substation Slide3
Terms and conditions of Provided Investment Facilities
Based on the Memorandum of Mutual Understanding signed on May 17, 2006 between the Republic of Armenia and the Islamic Republic of Iran a Contract
(N4777/85EPC)
was signed between SUNIR Company and Ministry of Energy and Natural Resources of RA “High Voltage Electric Networks’’ CJSC for “Design, Engineering, Procurement of Goods and Equipment, Supply and Construction of Iran-Armenia 400kV third power transmission line” (hereinafter Project). The Project cost
is 107,9 mln
. Euro. The financing of 77% of Contract total price will be carried out by the Export Development Bank of Iran (EDBI).
(Financial Agreement
N900/M/ARM/09, 26.07.2011
), and
23% (24,8 Euro) by Company «SUNIR International FZE» (Bond Contract N1390/1195/57175, 23.02.2012) Slide4
The length of OTL is 268 km, the number of towers are 706.
The construction works of Project were kicked-off on August 2012
but they had been suspended at the beginning of 2013.
On August 9, 2015 EDBI has recommenced financing and as a
recommencement date was defined 01.09.2015.
Signing of additional Contract of financing recommencement with
EDBISlide5
Project Objectives
The Project implementation will enable:
Enhancing the power flows from 350 MW up to about 1,000 MW between the Republic of Armenia and the Islamic Republic of Iran
Increasing the reliability and stability of parallel works of RA and IRI Energy systems
Increasing the Energy Security levelIncreasing the reliability and stability of Energy systems of RA by strengthening the North-South power connection of Republic
Using the entire volume gas pipeline capacity of Iran-Armenia in the framework of the program "Gas Towards Electricity“. Slide6
Expected Project Results
In the result of Project Implementation 400 kV double circuit OTL will enter into operation with the length of 268 km from “
Ddmashen” substation up to the southern border of RA (
Agarak) and after construction of Armenia-Georgia 400kV OTL Armenia will become a transit country of Energy power. Slide7
Project Implementation Deadlines
According to Performance schedule,
Loan Project of Construction of Iran-Armenia 400kV third power transmission line (“
Noravan
’’
400/220/20
kV) and related substation
should be completed in 2017. Slide8
The impact on Electricity tariff in the result of Project Implementation
Loan and Grant Project of
“Construction of Iran-Armenia
400kV
third power transmission line and substation
”
Mln
.
dram
4,044.1
11,535.2
19,518.8
10,112.2
9,667.7
9,223.3
4,444.9
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Impact on tariff
0.5944
1.6954
2.86871.48621.42091.35560.65330.00000.00000.00000.00000.00000.00000.0000
Project name
01.08.2016-01.08.2017
01.08.2017-01.08.2018
01.08.2018-01.08.2019
01.08.2019-01.08.2020
01.08.2020-01.08.2021
01.08.2021-01.08.2022
01.08.2022-01.08.2023
01.08.2023-01.08.2024
01.08.2024-01.08.2025
01.08.2025-01.08.2026
01.08.2026-01.08.2027
01.08.2027-01.08.2028
01.08.2028-01.08.2029
01.08.2029-01.08.2030Slide9
The impact on Electricity tariff in the result of Project Implementation