Fresca 2 cryostat update Fresca 2 cryostat update

Fresca 2 cryostat update - PowerPoint Presentation

amelia
amelia . @amelia
Follow
66 views
Uploaded On 2023-07-12

Fresca 2 cryostat update - PPT Presentation

A Vande Craen on behalf of the FRESCA 2 test facility team 10022021 B163 Upgrade Meeting 1 10022021 B163 Upgrade Meeting 2 Milestones OVV Received on 04022021 in SMI2 ready for acceptance test dimensional control ID: 1008154

feb jun assembly mar jun feb mar assembly 2015 test 2021b163 upgrade 21na15 vessel jan 20nana15 vacuum apr thermal

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Fresca 2 cryostat update" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

1. Fresca 2 cryostat updateA Vande Craen on behalf of the FRESCA 2 test facility team10/02/2021B163 Upgrade Meeting1

2. 10/02/2021B163 Upgrade Meeting2MilestonesOVV : Received on 04/02/2021, in SMI2 ready for acceptance test (dimensional control)OTS and ITS : FinishedIHV and OHV : Machining and welding of big components startedDelivery still expected for beginning of Q4-2021Preliminary DesignDetailed Design (3D)Verifications/Structural checks/PrototypeManufacturing Drawings (2D)IT/DO readyContract PlacementInternal Manufacturing endDelivery at CERNCompleted (accepted/tested)1Outer Vacuum Vessel Assembly - OVV AssyDone31-Jan-2015-Feb-2029-Feb-208-May-201-Jul-20NA4-Feb-2131-Jan-212Outer Helium Vessel Assembly - OHV AssyDone15-Feb-2015-Apr-2015-Jun-20NANA30-Jan-21NA15-Mar-213Outer Thermal Screen - OTS AssyDone29-Feb-20NA15-Mar-20NANA30-Jan-21NA15-Mar-214Inner Vacuum Vessel Assembly - IVV AssyDone15-Jun-2015-Jun-2030-Jun-20NANA15-Feb-21NA15-Mar-215Inner Helium Vessel Assembly - IHV AssyDone30-Apr-2015-Jun-2030-Jun-20NANA15-Feb-21NA15-Mar-216Inner Thermal Screen - ITS AssyDone30-Apr-20NA30-Jun-20NANA15-Feb-21NA15-Mar-217MLIDoneNANA30-Jun-2025-Aug-2015-Oct-20NA28-Feb-2115-Mar-218Magnet AssemblyDone15-Jun-2015-Jun-2030-Jun-20NANA15-Feb-21NA15-Mar-21Was 31/12/2020Was 31/12/2020

3. Status10/02/2021B163 Upgrade Meeting3Magnet in 156, finished thermal shields and top parts of IHV in backgroundOVV in SMI2Magnet supports being pre-assembled

4. UpdatesKolsterizingAll parts send for treatmentCharacterized within MME (S Sgobba) and validated at coldMagnet in 156Stripping discussed and agreed with MSCBlank assembly being prepared to be ready to give it back to MSC on 25/03Handling and transportTooling in productionTest on 163 crane to validate load and movement  OK, crane run smoothly and precisely enough for assembly operationPressure test procedureDiscussed and agreed with HSEDocument under preparationHeat load budgetDocument prepared summarizing all heat loadsTo be shared with CRGDiscussion on-going with CRG to clarify operation, instrumentation and wiring10/02/2021B163 Upgrade Meeting4

5. Lambda plate sealTest of Indium seal on-goingFirst test showedLoss of leak tightness at coldHeat load too high to be measured (cannot reach steady conditions)  Probably due to loss of pre-compression at coldNew test on-going with Belleville washer to simulate magnet weight Very good leak tightness at warmCool-down planned for end of this week or next weekIf test is not conclusive : integrated both solutions (vacuum grease and indium) on the flanges to release manufacturing of flange and lambda plate10/02/2021B163 Upgrade Meeting5

6. 10/02/2021B163 Upgrade Meeting6ConclusionsFabrication is going full speed, within schedule and budgetNext step is blank assembly into the magnetTest of lambda sealing solution is still on-going results expected soon