Download Presentation The PPT/PDF document "Diagnostic Commissioning Plan & BCM ..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
1. Diagnostic Commissioning Plan & BCM for AthosAthos BPM Status and Plans, on behalf of Boris KeilGian Luca Orlandi:: Electron Beam Instrumentation :: Paul Scherrer InstitutAthos Commissioning Workshop March 4, 2020
2. Bunch Compression Monitor System Expert: F. FreiPage 2Status March 2020: in design.Rough time plan:5 March 2020 Decide on BCM or CDR implementation (F. Löhl, R. Ganter, S. Reiche, R. Ischebeck, F. Frei)Q1/Q2 2020 3D + drawings (Goran Kotrle)Q3 2020 ProcurementSpring 2021 Installation and commissioning
3. Screen Monitors System Expert: R. Ischebeck3DevicesBasicRequirementsShifts 2020WhenStatusSoftware—done✅Study of linearity / saturation: ongoing- High charge, known optics1Did one shift, but require smaller beam sizeATHOS-DSCR…Calibration of individual monitors—done✅HERO screensinstrumentation for overlap of laser and electron beamsHERO laser and commissioning plan1On progressDevicesFuture StudiesRequirementsShiftsWhenATHOS-DSCR (DLAC)Improvement of resolution: magnifying opticsTesting new scintillators- Low-emittance beam2Summer 2020Objective arrived, measurements in 2020Comparison to DLAC wire scanners- Known optics1done✅
4. DBLM/DLLM/DICT/DDRM in ATHOS and 2-bunch operationSystem Expert: G. L. OrlandiPage 4DevicesBasicCommentsShifts 2020Status March 2020DBLM Installation and commissioning on-going according to the ATHOS installation plan2 more DBLMs to be installedpresently installed DBLMs commissioned2In operation/installation on progressDLLMInstallation and commissioning on-going according to the ATHOS installation plan1 DLLM (z=430517m) to be installedpresently installed DLLMs commissioned1In operation/installation on progressDDRMDDRM installation on-going in parallel with installation of ATHOS undulators- 4 DDRMs presently installed- remaining DDRMs to be installed together with undulatorsPIn operation/installation on progressDICTSATBD02-DICT020 installed and configured Nov2019- open issues on DICT: intervention plan to be defined (meeting March,13)PIn operationDWSC3/3 ATHOS WS installed and commissioned- ARAMIS WS: Commissioning 2-bunch operations done (04.02.2020-07.02.2020) - ATHOS WS: basic commissioning done (07.02.2020)1In operationSINBC02-DSRM3102-bunch fast gated camera- Camera installed and under configuration (Controls)PCommissioning on progress
5. Athos BPM Status and PlansBoris Keil :: GFA/AEK :: Paul Scherrer InstitutAthos Commissioning Workshop, March 4, 2020
6. SwissFEL BPM OverviewPage 6BPM pickup (mechanics) types:Low-Q BPMs (3.3 GHz):For linac & transfer linesCan measure two bunches (short ringing signal)Two types (16mm & 38mm aperture)High-Q BPMs (4.9 GHz):Can only measure single bunches (long ringing signal)Mainly used for undulators (higher resolution that low-Q)Two types (Aramis: 8mm, Athos branch: 5mm aperture)BPM electronics types:"Old" type ("MBU" = Modular BPM unit), based on E-XFELPresently installed in Aramis & Athos, for all BPM types"New" type (DBPM3), based on new SLS2 BPM platformOnly for high-Q (4.9 GHz high-resolution) BPMs~3x cheaper than "Old" MBU electronicsExpect comparable performance (ADCs 3x faster)
7. Athos BPM Status & PlansPage 7So far, only MBU BPMs are used in SwissFEL, including AthosNot all BPMs needed yet -> only BPMs required for commissioning were equipped with electronics, using Aramis sparesIn April 2020, the first DBPM3 electronics should become operational in Athos (pre-series, successfully tested in lab)In summer 2020, all Athos undulator BPMs should be equipped with new DBPM3 series version electronicsLater, also Aramis undulators will use DBPM3 (probably Q1/2021), replacing old high-Q MBU electronics to be used as (low-Q) long-term spares ( >80% of low-Q/high-Q electronics are identical)Old and new electronics have same EPICS channels used by operations (position, charge, ...) -> should be transparent for operation.Only expert EPICS channels different, but we will try to make this transparent, too (save/restore, loading defaults, ...)
8. Athos BPM Status & Plans (Cont'd)Page 8All priority 1 Athos BPMs were ready 11/2019 for 1st lasingFirst DBPM3 BPM electronics April 2020Remaining DBPM3 electronics to be installed in summer 2020