DEFINITION 2 Contract Monitoring noun verb kon trakt mon i tering Contract monitoring is a regular process of evaluating contractor performance based on measurable service deliverables and verifying compliance with the standards terms and conditions in the contract ID: 911625
Download Presentation The PPT/PDF document "Monitoring ProTech Service Contracts" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Monitoring
ProTech Service Contracts
Slide2DEFINITION
2
Contract Monitoring
[ noun, verb,
kon
-trakt
mon
-
i
-
ter-ing
]
Contract monitoring is a regular process of evaluating contractor performance based on measurable service deliverables, and verifying compliance with the standards, terms and conditions in the contract.
Slide3BASIC OBJECTIVES
3
1. To get what the government needs
2. When it needs it
3. At a fair and reasonable price
Slide4PURPOSES OF MONITORING PROTECH ORDERS
4
Improve
ProTech
program performance
Identify potential problems
Evaluate agency performance controls
Assure that financial documentation is adequate and accurate
Identify program and/or financial problems as early as possible
Slide5EXAMPLES OF FAIR OPPORTUNITY EXCEPTIONS
5
Three major goals –
To achieve clear and mutual understanding of the contractual requirements
To understand what the contractor is planning to do
To answer contractor questions and resolve potential problems
Slide6COR
PROTECH CONTRACTING OFFICER’S REPRESENTATIVE ROLE
6
Know the contract requirements
Determine monitoring techniques to be used
Develop a work plan
Monitor performance
Keep the Contracting Officer (CO) advised
Slide7ETHICS & STANDARDS OF CONDUCT
7
• Treat contractors impartially (FAR 3.101-1)
• Do not accept gratuities
• Do not discuss employment opportunities with contractors
• Avoid conflicts of interest
• Safeguard source selection or proprietary information.
Slide8THE COR WORK PLAN
8
A baseline for project management and scheduling
A simple tool for tracking contract progress
An aid for the post award orientation conference
Slide9ELEMENTS OF A COR WORK PLAN
9
Administrative items (e.g., contract number, dollar amount, type of contract)
Historical factors
Monitoring techniques
Documentation of the contractor’s performance
Areas of concern or conflict
Slide10EXAMPLE COR WORK PLAN OUTLINE
10
Contract
Number and Title:
Criticality Designator:
Contract Amount: $ (base year); total of $ for all 5 years
Contract Type:
Date of Award:
Responsibilities under Contract (as detailed in designation letter)
Determining the adequacy of contractor performance
Representing the government in directing work
Ensuring compliance of work with requirements
Advising the CO.
Slide11EXAMPLE COR WORK PLAN OUTLINE
11
Government Points of Contact
Contract Administrator:
Responsible for:
Day-to-day inspection and monitoring
Documenting inspections
Following through on deficiencies.
Contractor:
Location of Files
–
Contractor’s Scope of Work
To provide all management, supervision, labor, materials, supplies, and equipment (except as specified)
To plan, schedule, coordinate, and ensure effective performance of:
Slide12EXAMPLE COR WORK PLAN OUTLINE
12
Place of Performance:
Contractor Reporting Requirements
Annual Daily/Periodic Schedule submitted five workdays prior to start date and then annually
Daily Work Report (GSA Form 64 or equivalent), submitted daily to the COR
Quality Control Program, submitted five workdays prior to start date
Resumes of initial and replacement supervisors.
Contractor Milestones
Previous Contracts
(This is a first-time contractor. There is no information on file for this contractor.)
Slide13EXAMPLE COR WORK PLAN OUTLINE
13
Potential Problem Areas
All supplies, materials, and equipment used by the contractor must conform to specifications and must, on request, be identified; possible problems could be avoided by requesting a listing prior to the start date and prior to any substitutions.
Space for locker rooms for contractor personnel, for storage of equipment and supplies, and for use as the contractor’s onsite office is to be government-furnished; this space should be identified and inspected prior to the start date.
Contract does not specify which official will determine when the contractor’s personnel will be diverted for snow removal or emergency conditions; when given, these instructions should be in writing to avoid disputes over deductions.
The contractor is to have the opportunity to re-perform deficient services and ensure future services before deductions are taken; however, no time limit for remedial action is specified.
Slide14EXAMPLE COR WORK PLAN OUTLINE
14
Monitoring
Contractor technical and schedule techniques to be used:
Making onsite visits and personal observations
Contacting the quality assurance specialist
Reviewing progress or status reports.
Documentation
The contractor’s performance will be documented in the contract file using:
Monitoring Report.
Action Requirements
Attend post award preliminary briefing on (Date) with CO to discuss roles and responsibilities for post award conference with contractor, scheduled for (Date).
Slide15STEPS IN MONITORING CONTRACTS
15
Slide16DETERMINE WHAT NEEDS TO BE MONITORED
16
Contractor technical and schedule compliance
Costs (in cost-type contracts)
The financial condition of a contractor
The contractor’s statutory compliance
Slide17SELECT THE TECHNIQUES USED FOR MONITORING
17
Monitoring techniques include:
Conducting meetings
Making onsite visits and other personal observations
Reviewing contractor reports
Reviewing tracking and management systems
Slide18DETERMINE HOW TO DOCUMENT MONITORING ACTIONS
18
Meeting Minutes
Correspondence
Letter
Email
Surveillance reports
Technical Analysis
Slide19DOCUMENTING PERFORMANCE ISSUES
19
A description of the performance problems
Discussion of mitigating or extenuating circumstances, if any
Indexed file or related documents documenting performance problems
An analysis of the impact that the contractor’s performance problems have had on:
Overall cost
Delays in obtaining needed services
Mission accomplishment.
Slide20GFP
GOVERNMENT-FURNISHED PROPERTY
20
Supervise the initial transfer of government property
Monitor the contractor’s use of government property
Monitor the disposition of government property
Slide21TRANSFER OF GOVERNMENT PROPERTY
21
Establish an inventory list of the property being delivered
Set up management requirements
Inspect government-provided equipment
Document transfer
Slide22USE OF GOVERNMENT PROPERTY
22
Ensure the contractor maintains an adequate property management system
Perform periodic property audits
Record any notification from the contractor that the government-furnished equipment is in need of repair
Report of any shortages, losses, damage, destruction, or misuse of GFP to the CO
Slide23DISPOSITION OF GOVERNMENT PROPERTY
23
When the contract is completed, the government may:
Request that the contractor deliver government property back to the government
Request that the contractor deliver government property to another government contract site
Dispose of the property.
Slide24DISPOSITION OF GOVERNMENT PROPERTY
24
When disposing of property, the government may choose one of the following options (listed in preferred priority order):
Allow the contractor to purchase or retain the government property at cost
Return the property to the suppliers
Use the property within the government
Donate the property to eligible entities (e.g., schools, charitable organizations)
Sell the property
Donate the property to other public agencies (e.g., state and local
governments)
Abandon the property.
Slide25DOCUMENTING DELAYED PERFORMANCE
25
Identify the existence of a delay
Substantiate the evidence of the delay
Substantiate the costs associated with the delay
Determine if the delay was excusable (i.e., beyond the contractors control and without its fault or negligence)
Potential alternatives and resolution recommendations
Pros and cons of each listed alternative or resolution
Notify the Contracting Officer
Slide26DECISION TABLE FOR SELECTING A CONTRACT REMEDY
1
26
PROBLEM
OPTIONS
COMMENT
Late delivery
(The
CO has determined that
the deliverable has been
or will be delivered late
and that the delay is
non-excusable.)
Reschedule the delivery date
in exchange for consideration (i.e., something of value in return from the contractor).
Appropriate when (1) no liquidated damages clause was included in
the original contract, (2) there is a
reasonable probability of delivery
by the new delivery date, and (3)
the requiring activity can accept the new date.
Reduce or suspend progress
payments under FAR 52.232-
16(c)(2). For advance payments, see FAR 52.232.12(k).
Appropriate when (1) progress
payments are being made and (2)
performance of the contract is
endangered by the contractor’s failure to make progress.
1
The COR/COTR Answer Book,
Third Edition
Bob Boyd, CFCM
Slide27DECISION TABLE FOR SELECTING A CONTRACT REMEDY
27
Late delivery
(cont.)
Accept late delivery and
impose liquidated damages.
Appropriate when (1) the contract
provides for liquidated damages and (2) there is a reasonable probability of delivery by a date the requiring activity can accept.
Send a cure notice (ten days
or more prior to the contract’s
delivery date) or a show cause
notice (immediately upon expiration of the delivery period).
Appropriate when there is little
probability of delivery by a date that the requiring activity can accept, or the contractor has not offered adequate consideration.
Slide28DECISION TABLE FOR SELECTING A CONTRACT REMEDY
28
The deliverable has not been accepted and does not conform to the contract’s requirements
. (The
CO has determined that the deliverable has not been implicitly or explicitly accepted and does not conform to the contract’s requirements.)
Accept the deliverable without
consideration.
Appropriate when the nonconformance is minor and obtaining consideration is not in the government’s interests (see FAR 46.407(f)).
Accept the deliverable in
exchange for consideration.
Appropriate when the requiring
activity can tolerate non-conformance (see FAR 46
407(c))
Slide29DECISION TABLE FOR SELECTING A CONTRACT REMEDY
29
The deliverable has not been accepted and does not conform to the contract’s requirements
(cont.)
Accept the deliverable and
invoke a warranty to have the
deliverable improved to meet
specifications after acceptance.
Appropriate when there is an express or implied warranty and immediate acceptance will benefit the requiring activity.
Reject the deliverable and
obtain correction or replacement at no cost to the government. Tell the payment office to withhold payment until an acceptable deliverable has been furnished.
Appropriate when there is a reasonable expectation that a satisfactory replacement will be provided by the delivery date in the contract, or for consideration, within a reasonable time thereafter.
Slide30DECISION TABLE FOR SELECTING A CONTRACT REMEDY
30
The deliverable has
not
been accepted and does not conform to the contract’s requirements
. (cont.)
Reject the deliverable and send a cure or show cause notice.
Appropriate when there is little
expectation of receiving an acceptable product within a reasonable time.
The deliverable
has
been accepted but does not conform to the contract’s requirements
(The CO has determined that the
government has a reasonably strong case for revoking acceptance
based on the terms and conditions of the contract.)
Invoke an express warranty.
Appropriate if an express warranty
applies.
Invoke an implied warranty
Appropriate if an implied warranty
applies.
Demand that the deliverable be replaced or corrected or that the price be adjusted downward.
Appropriate if there is a latent defect in the deliverable or if acceptance was based on fraud or gross mistake
Slide31DECISION TABLE FOR SELECTING A CONTRACT REMEDY
31
Other breaches
(The CO has exhausted all efforts at informal resolution of the problem.)
Invoke whatever remedy (if any) is established in the applicable clause
Possible solutions for contractor
breaches:
• Liquidated damages (per FAR
52.219-16) for failing to comply
with the subcontracting plan
• Liquidated damages and withholding for unpaid wages (under FAR 52.222-4, “Contracting
Work Hours and Safety Standards
Act Overtime Compensation”)
• Cancellation, suspension, or
termination of the contract (under FAR 52.222-26, “Equal
Opportunity”)
Suspend or reduce progress
payments under FAR 52.232-16(c)(2). For advance payments, see FAR 52.232.12(k).
Slide32DECISION TABLE FOR SELECTING A CONTRACT REMEDY
32
Other breaches. (The CO has exhausted all efforts at informal resolution of the problem.)
(cont.)
• Withholding of payments and
contract termination (under FAR
52.222-41, “Service Contract Act
of 1965, As Amended”)
• Suspension of contract payments,
termination for default, and
suspension or debasement (under FAR 52.223-6, “Drug-Free
Workplace”).
Send a cure notice 10 days or more prior to the contract’s delivery date.
Appropriate when the breach is of
sufficient magnitude to warrant termination for default.
Slide33PAYMENT
33
Partial payment - based on acceptance of a particular part of contract performance
Prompt payment - the government pays the contractor prior to the invoice payment date
Prompt payment discount - an invoice payment reduction voluntarily offered to the government by the contractor for prompt payment that is made prior to the due date stated on the invoice
Slide34PERFORMANCE EVALUATION REPORTING
34
Reporting Requirements - Contractor Performance Assessment Reporting System (CPARS)
Report Content
Reporting Procedures:
Slide35For additional questions contact