Case Study Utility sector Remediation Waste Martin E Sánchez NJDEP Background As a result of upgrading substation utility company generated waste excavated soils The excavated soils were accumulated in piles and then sampled for determination ID: 773264

hazardous waste soils excavated waste hazardous excavated soils soil piles rcra part substation d008 linear construction guidance lead issued

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Case Study Utility sector Remediation Wa..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Case StudyUtility sector Remediation Waste Martin E. Sánchez NJDEP

Background As a result of upgrading substation, utility company generated waste excavated soils. The excavated soils were accumulated in piles and then sampled for determination. The soil piles were found to be above regulatory levels (TCLP) for lead. The substation generated Large Quantity Generator amounts of D008 hazardous (>2,200 lbs./month). As per RCRA, generators of hazardous can accumulate hazardous waste for less than 90 days without applying for Part A/Part B RCRA permit. Generators can only accumulate in containers, tanks, containment buildings and drip pads.

LSRP / Utility Co. Response Excavated soil was handled in accordance with the linear construction guidance document which allows soil to be stockpiled and contained while being tested for disposal.     These sites are undergoing remediation and RCRA requirements are not applicable. Linear Construction Technical Guidancehttp://www.nj.gov/dep/srp/guidance/srra/lc_guidance.pdf

Inspection Findings Excavated soils from the substation are not subject to the Linear Construction Technical Guidance but are a traditional LSRP case which would link to the linear construction project. Contamination found must be reported to the DEP Hotline. Since excavated soils were found to be above regulatory levels (TCLP) for lead, the substation is a hazardous waste generator and all applicable RCRA requirements apply.Notice of Violation was issued

Notice of Violation Issued Failed to determine the waste excavated soils were D008 hazardous waste prior accumulation in waste piles. Failed to place Waste lead contaminated soil (D008 hazardous waste) in containers instead of waste piles.Constructed and accumulated Waste lead contaminated soil (D008 hazardous waste) in waste piles without obtaining or submitting a Part A or Part B permit application. Settlement was reached with Company after the violations corrected.