Day 3 – Session 6 “General cryogenic maintenance policy and recent update for CERN - PPT Presentation

Frédéric Ferrand CERN Geneva Switzerland On behalf of CERN Cryogenics Group OUTLOOK Introduction Definition of maintenance strategy for critical Assets Maintenance Policy for cryogenic equipment at CERN ID: 1032862

cern maintenance lhc amp maintenance cern amp lhc 000 check cold running test machine operation boxes valves compressor weeks

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Day 3 – Session 6 “General cryogen..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

1. Day 3 – Session 6“General cryogenic maintenance policy and recent update for CERN assets”Frédéric FerrandCERN, Geneva, SwitzerlandOn behalf of CERN Cryogenics Group

2. OUTLOOKIntroduction Definition of maintenance strategy for critical Assets Maintenance Policy for cryogenic equipment at CERN Work Organization an implementation of the strategy for Long Shut Down 2Conclusion

3. LHC Machine Cryogenics ArchitectureSURFACECompressor Stations 4.5K Cold Boxes Liquid & Gas storagesUNDERGOUND4.5K & 1.8K Cold Boxes Distribution Valve Boxes Distribution System@CERN @CERN @CERN @CERN @CERN @CERN Compressor station4.5 K refrigerator1.8 K pumping unit (cold compressor)Interconnection boxP1P2P3P4P6P7P8P5P18BBAABBAAA – upgraded ex-LEP cryo plantB – new LHC cryogenic plantLHC CryogenicsLHC cryogenics:8 x 18 kW @ 4.5 K24 km & 20 kW @ 1.8 K130 tons of helium inventory circumference  ~ 27 km, constructed at ~ 100 m underground, the accelerator ring inclination is 1.4 %

4. LHC Machine Cryogenics Maintenance WindowsLONG SHUTDOWN50 Weeks per cryoplantYEAR END TECHNICAL SHUTDOWN2 Weeks per cryoplantEXTENDED YEAR END TECHNICAL SHUTDOWN4 Weeks per cryoplantYETSYETSYETSYETSCRYO ASSETS RUNNING HOURS ~40’000MAINTENANCE WINDOWS =CRYO ASSETS RUNNING HOURS ~32’000

5. Cryogenic Test and Experimental Facilities 18 cryoplants in addition to LHC Machine Serving more than 20 key users Tailor made Operation & Maintenance plan@CERN – CMS Detector

6. Cryogenic Test and Experimental Facilities@CERN – CMS DetectorOperation & Maintenance Operation planning is a combination between LHC general planning and each experiment specific requirementsUsually 2 to 4 weeks maintenance window is allocated on standard yearTailor made planning for each installation according to user requirementsUsually 1 to 4 weeks maintenance per year External Contractor Result oriented contract CERN& support contract

7. Basic Functional Analysis of LHC cryogenicsMAIN CRITICAL EQUIPMENTSExpanding TurbinesCompressors Cold Compressors

8. Compressor station & Oil Removal System @CERNCourtesy of Serge Claudet Superconductivity and Cryogenics, 2011

9. Compressor station & Oil Removal System @CERNMAINTENANCE STRATEGYMaintenance strategy includes major overhauling during Long Shutdownvibration analysis to anticipate complete breakdown for compressors and motorsOil Analysis for large capacity oil separator设备维修策略

10. @CERN – North Area Compressor 1979 Other compressors in Operation@CERNCritical spare parts LHC 4.5K: 8 spares for 52 compressors in operation for LHC machine 16% of the financial RAVCritical spare parts LHC 1.8K: 2 spares for 16 compressors in operation for LHC machine 12.5% of the financial RAVSame approach applied to Motors not presented hereCompressor station & Oil Removal System4.5K_____1.8K

11. Compressor station & Oil Removal System Courtesy of TE-CRG Mechanical SectionPREDICTIVE Maintenance program – Condition Based Monitoring Checked CriteriaVibration analysis Monthly Multiple : spectrum analysisOil analysis program Yearly Multiple : oxidation, particulesElectrical cabinets thermography Yearly Over heating temperatureCritical instrumentation checks 4-Yr Deviating valuePREVENTIVE Maintenance programOil pumps Revision 8’000(minor) & 24’000(major) running hours Activated charcoal load replacement 24’000 running hoursCoalescing filters replacement None or 24’000 running hoursScrew compressor Major Overhauling 40’000 running hoursHigh Voltage Motors 30’000(bearings) & 40’000(sleeve bearings) running hoursVacuum pumps revisions 8’000 to 40’000 running hoursSafety chain check YearlySafety valves test bench test 2-Yr, 4Yr, 5-YrWater Heat Exchangers chemical cleaning 4-YrCritical instrumentation & valves check 4-Yr

12. Cold Boxes@CERN@CERNProcess cycle & T-S diagram of LHC 18 kW @ 4.5 K cryoplantLHCB P18 (AL)Courtesy of

13. Cold Boxes@CERN@CERNMAINTENANCE STRATEGYTurbine automation protection in the processService contract to reduce MTTR below 4 weeks and avoid buying spare for turbines above 80KCritical spare parts LHC Machine: 27 different types of turbines21 spares for 64 turbines in operation for LHC machine 32% of the RAV设备维修策略

14. Cold Boxes@CERN@CERNMAINTENANCE STRATEGYPower Supply and electronic design change to improve reliabilityPredictive maintenance with mechanical clearance and bearings check to validate service intervention on timeCritical spare parts LHC Machine: 7 different types of Cold Compressors7 spares for 28 units in operation for LHC25% of the financial RAV设备维修策略

15. Cold Boxes@CERN@CERNPREDICTIVE Maintenance program – Condition Based Monitoring Checked CriteriaElectrical cabinets thermography Yearly Over heating temperature Critical instrumentation checks 4-Yr Deviating valueCold Compressors 4-Yr Mechanical cleareanceHeat exchangers 4-Yr Tightness testTurbine filters Yearly Delta PPREVENTIVE Maintenance programSafety valves test bench or local test 2-Yr, 4Yr, 5-Yr Safety chain check YearlyWater Heat Exchangers chemical cleaning 4-YrVacuum pumps revisions 8’000 to 24’000 running hoursCritical valves & instrumentation check 4-YrTurbine filters 4-Yr (when vacuum break required) RUN to FAILTurbines

16. Storage, Distribution & Cryostat@CERN@CERNPREDICTIVE Maintenance program – Condition Based Monitoring Checked CriteriaLine integrity test during warm-up 4-Yr Pressure and vacuum testsCritical instrumentation checks 4-Yr Deviating valueCritical valves check 4-Yr Leak tighnessCapacity legal pressure check 10-Yr Pressure test according to EU PREVENTIVE Maintenance programSafety valves 2-Yr, 4Yr, 5-Yr Safety chain check YearlyVacuum pumps revisions 8’000 to 24’000 running hoursCritical valves check 4-YrCritical instrumentation check 1 to 4-Yr@CERN – LHC Point 2 Distribution Valve Box @CERN – LHC Nitrogen tank during LHC pre cooling

17. CERN Cryogenics group involvement in MaintenanceIndustrial PartnershipWork Organization and LS2 implementation Maintenance support TeamCoordinationPlanning CMMSSpare partsMechanical Maintenance TeamField Mechanical TeamField E&I TeamOperation support or fully delegated

18. Work Organization and LS2 implementation Computerized Maintenance Management SystemAll Maintenance Plans are review by: Maintenance experts by fieldMethod & Logistic support section Contractor Maintenance Support teamReference matrix is updated and shared with the teamUpdate of the of the CMMS is done by the contractor Work Preparation and planning will follow in the coming months according to CERN requirement

19. Work Organization and LS2 implementation Computerized Maintenance Management SystemTechnical Stop 3-4d 30-80woYETS 2-3wk 1’000-1’200woLong Shutdown 1yr 3’000-4’000wo Workflow is in place and each WO is check and validated by CERN technical expert in the field and quality controller

20. Work Organization and LS2 implementation Work Instructions and Field FormsAll mechanical documents technical contents have been updated in the past yearWe are testing electronic checklists and integrated calibration device

21. Conclusion@CERN – BA6 Mobile Cold BoxConclusionMaintenance Strategy definition is very important and shall integrate :Identification of the Failure ModesEvolution of the expected patternCriticality assessment of the AssetEvaluate technical and financial capabilityEnsure quality of the executed workCMMS is also mandatory in order to TRACK and RECORD precisely maintenance events and analyze things correctly the situation 设备维修策略when facing the unexpected.

22.

23. she bei wei hu ce lue \ \ / \ \ \Maintenance Strategy设备维修策略