FCC Addendum Kick Off Meeting 07122017 Maria Durante on behalf of the ECC team CONTENT Initial Program Design options CEA block coil option status CEA block coil option ID: 913780
Download Presentation The PPT/PDF document "EuroCirCol WP5 Cea Activities" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
EuroCirCol
WP5
Cea
Activities
FCC
Addendum Kick Off Meeting
07/12/2017
Maria Durante
on behalf of the ECC team
Slide2CONTENT
Initial Program
Design optionsCEA block coil option: statusCEA block coil option: next stepsCDR contentCDR Road MapFCC Magnet System Cost ModelProject Team
| PAGE 2
CERN-CEA meeting 07/12/2017 – FCC Addendum kick off meeting
Slide33
/ 153
Dipole 16 T – Nb3Sn
High Field Magnet
WP5
Design study for FCC-HH June 2015 – Mai 2019
Focus on the key design questions
feasibility of a 100
TeV
FCC-HH
CDR by end 2018 in time for the next European Strategy Update
WP5 - Task
denominations and distribution of task leadership
Task
Denomination
Leader
Alternate
5.1CoordinationCERN (D. Tommasini)CIEMAT (F. Toral)5.2Design Options (16 T – Nb3Sn – 2D analysis) CIEMAT (F. Toral)CEA (C. Lorin)5.3Cost ModelCERN (D. Schoerling)CEA (M. Durante)5.4Magnet Conceptual DesignINFN (S. Farinon)CEA (M. Durante)5.5Conductor StudiesCERN (B. Bordini)UT (M. Dhallé)5.6Quench ProtectionTUT (A. Stenvall)INFN (M. Sorbi)5.7Magnet Engineering DesignCEA (M. Durante)CERN (D. Schoerling)
EuroCirCol
WP5 - Initial Program
CERN-CEA meeting 07/12/2017 – FCC Addendum kick off meeting
Slide4EuroCirCol
WP5 - design options
The three identified design options have been developed by the three institutes INFN, CEA and CIEMAT. INFN took charge of the cosine theta designCEA took inncharge the block coil designCIEMAT took in charge the common coil designLast summer, the cosine theta option has been officially chosen as the baseline option for the FCC (“design configuration in use in all superconducting colliders made so far”).However, the interest of the alternative options has been pointed out leading to the decision to continue to go on in parallel.The initial foreseen magnet engineering design deliverable (by CEA) is replaced for Europe by the detailed conceptual designs of the three options
and the signature of three contracts to build dipole models.
Slide5CEA block
coil
optionAfter a first 2D magnetic and mechanical design based on the first set of parameters (250 mm interbeam distance, 18% LL margin, 800 mm outer diameter)
[
v101]
Al
Iron
Ti
CuAl
Steel
Slide6Bp
ss
-Bpends = 0.4 TCEA block coil optionCEA produced a more compact design based on the new set of parameters defined following recommendations of the 1st WP5 EuroCirCol Review Reduction of the margin on the load line from 18% to 14%Reduction interbeam distance from 250 to 204 mm
[
v1ari204, FCC week 2017]
Yoke/pads
Coils
Ansys
+
Cast3m
//
study
Slide7CEA block
coil
optionCEA produced a more compact design based on the new set of parameters defined following recommendations of the 1st WP5 EuroCirCol Review and discussions of the 2017 FCC week Reduction of the margin on the load line from 18% to 14%Release of the constrain on stray field at the cryostat surface (1 m) from 0.1 T to 0.2 T Reduction of the cold mass size : cryostat max outer Ø = 1200-1250 mm colds mass max outer Ø = 750-800 mm including SS shellAt the same time reduction of the interbeam distance from 204 to 194 mm (LHC interbeam distance)
Slide8CEA block
coil
option2D magnetic and mechanical design finalized BUT for an interbeam distance of 194 mm
3D
m
agnetic
Design
3D
Mechanical
Design to
be
done
[
MT25]
Slide9CEA block
coil
option – next stepsReview of the 2D design with an interbeam distance of 204 mmIntegration of a SS shell outer the Al shellMagnetization losses studies
3D magnetic Design
3D
Mechanical
Design
As far as possible
until
June 2018
Slide10CDR content
(
courtesy of Davide tommasini)A "summary" volume including 5-6 pages on 16T dipolesan introduction (1 page) the baseline option (2-3 pages), the other options (1-2 pages). 1 page on quadrupoles.A "detailed" volume on the technological part,
describing all the options in as much details as produced by the deadline for the reduction.
Slide11CDR Road
Map
(courtesy of Davide tommasini)Dec 2017: First draft of summary FCC CDR book chapter on 16T.2 D designs of all design optionsApril 2018: FCC Week 2D EM and mech design finalized (with SS shell, 204 interbeam)conceptual 3D EM study (EM model + artistical picture)integration in the cryostat (by CERN)
Status of the 3D Mechanical study
report
for Task 5.3
Cost
model
report for Task
5.5 Conductor studies
r
eport for Task 5.6 Quench protectionJune 2018: first draft of detailed FCC CDR book chapter on 16T dipole Dec 2018: compilation of FCC CDR April 2019: final report for EU
Slide12FCC COST MODEL – WP5
Objective : FCC Magnet System Cost Model
Focused on the Dipole Magnets which dominate over other magnet costA study has been started to analytically estimate the costs of production of a 16 T FCC-hh magnet (cosine-theta baseline), separated into:Cost of parts (CIEMAT)Cost of the assembly process (CEA) for a required production rate of 20 magnets/week to complete the production in 5 years.
Slide13FCC COST MODEL –
Assembly
costAssembly process first analysis: technical manpower+ production engineers, foremen, controls and quality assurance engineers, administrative
Process
step
Shifts
Time needed (WEEKS)
Nb of
Operators
Work
Hours
Qualification
Operations/magnet
Tot hours/magnet
Coil
Winding122160
Mechanical/Winding
8
1280
Coil Heat treatment
3
2
0.1
24
Non skilled worker
8
192
Internal Splices (HF, if any) 2/coil
0
1
2
Mechanical
8
Transfert, Coil instrumentation, end splices
1
2
2
160
Mechanical/Electrical
8
1280
Coil Impregnation
1
1
2
80
Mechanical/chemist
8
640
Coil tests
1
1
1
40
Electrical/Mechanical
8
320
Coil pack Assembly
1
1
3
120
Mechanical
2
240
Structure
assembly
1
1
3
120
Mechanical
1
120
Cold mass assembly and finishing
2
4
2
640
Mechanical
1
640
14
weeks
1344
4712
3.5 months
Slide14FCC COST MODEL – NEXT STEPS
Establish a
production flow chart to be able to estimate the:tooling cost Edit a first furnace specification to evaluate feasability and cost of a large furnace (maximum number of coils)New Impregnation moulding techniques fitting with high rate productionlabour cost (manpower table to be consolidate)indirect cost (25% to direct costs according to the guideline for EU H2020 projects)
Slide15EuroCirCol
- Project Team –
until October 2017
Slide16EuroCirCol
- Project Team
Slide17| PAGE
17
CERN-CEA meeting 07/12/2017 – FCC Addendum kick off meeting