M anufacturing p lanning 27 FEVRIER 2013 ESAC Revue Maria Durante 26 février 2013 OUTLINE 26 février 2013 PAGE 2 CEA 27022013 Procurements FOR M1 34 coils Procurements FOR ID: 920401
Download Presentation The PPT/PDF document "E u CARD 7.3 FRESCA 2 DIPOLE" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
EuCARD 7.3 FRESCA 2 DIPOLEManufacturing planning
27 FEVRIER 2013
ESAC Revue | Maria Durante
26 février 2013
Slide2OUTLINE26 février 2013| PAGE 2
CEA | 27/02/2013
Procurements FOR M1: 3-4 coils
Procurements FOR
M1: 1-2 coils
Schedule
of one coil
manufacturing
First magnet schedule
Second
magnet schedule
Slide3Procurements FOR M1: 3-4 coils26 février 2013| PAGE 3
CEA | 27/02/2013
3-4
COIL
TOOLS
Winding
tooling
:
DELIVERED, WINDING SPOOLS
UNDER
MODIFICATION
Reaction tooling :
DELIVERED
Instrumentation and splice
tooling : AVAILABLE AT CERNImpregnation tooling : FORESEEN FOR END OF MARCHFIRST COPPER COIL COMPONENTS - CC3401Insulated Copper cable : 270 m UNIT LENGTH AVAILABLE AT CEACoil components: DELIVERED, WITH Al2O3 COATINGInterlayer insulation : UNDER REALIZATION (BINDER APPLICATION) AT CERN Copper CC3401 coil winding is foreseen for end of March/beginning of April 2013.Nb3Sn COILS : CR3401 and CR3402RRP Nb3Sn strand: AVAILABLE AT CERNCoil components : DELIVERED, TO BE ALUMINA COATEDInterlayer insulation : TO BE PROVIDED First Nb3Sn 3-4 type coil is foreseen after 1-2 copper coil, for September 2013.
Slide4Procurements FOR M1: 1-2 coils26 février 2013| PAGE 4
CEA | 27/02/2013
1-2 COIL
TOOLS
Winding tooling :
UNDER REALIZATION,
WINDING TABLE FORESEEN FOR END OF APRIL 2013
Reaction
tooling :
CALL FOR TENDER STARTED
Instrumentation and splice tooling :
AVAILABLE AT CERN
Impregnation
tooling :
CAO DETAILED DESIGN UNGOINGSECOND COPPER COIL COMPONENTS – CC1201Coil components: FORESEEN FOR MID MAY 2013ALUMINA COATING 5 WEEKS LATERInsulated Copper cable : BARE CABLE AVAILABE AT CERN, TO BE INSULATED Copper CC1201 coil winding is foreseen for end of June.Nb3Sn COILS : CR1201 and CR1202RRP Nb3Sn strand: AVAILABLE AT CERNCoil components for CR1201: FORESEEN FOR MID MAY 2013, ALUMINA COATING 5 WEEKS LATERCoil components for CR1202 : CALL FOR TENDER TO BE LAUNCHED First 1-2 Nb3Sn coil winding is foreseen after 3-4 Nb3Sn coil, for November 2013;
Slide5schedule of one coil manufacturingFebruary 26, 2013| PAGE 5
CEA | 27/02/2013
Schedule of one coil manufacturing : first copper coil
Nom de la tâche
Durée
Début
Fin
Copper 3-4 type coil manufacturing - CC3401
Lun 25/03/13
Lun 24/06/13
Coil winding - Copper coil CC3401
3 sm
Lun 25/03/13
Ven 12/04/13
Reaction mold assembly - Copper coil CC3401
1 sm
Lun 15/04/13
Ven 19/04/13
Expédition au Transfer from CEA to CERN - Copper coil CC3401
1 sm
Lun 22/04/13
Ven 26/04/13
Heat treatment preparation - Copper coil CC3401
1 sm
Lun 29/04/13
Ven 03/05/13
Coil heat treatment - Copper coil CC3401
10 joursécVen 03/05/13Lun 13/05/13 Reaction mold opening - Copper coil CC34011 smMar 14/05/13Lun 20/05/13 Coil Splices - Copper coil CC34011 smMar 21/05/13Lun 27/05/13 Coil Instrumentation - Copper coil CC34011 smMar 28/05/13Lun 03/06/13 Transfer into impregnation mold - Copper coil CC34011 smMar 04/06/13Lun 10/06/13 Coil Impregnation - Copper coil CC34012 smMar 11/06/13Lun 24/06/13 Transfer from CERN to CEA - 3-4 winding and reaction tooling1 smMar 11/06/13Lun 17/06/13
Slide6First magnet schedule26 février 2013| PAGE 6
CEA | 27/02/2013
Slide7Second magnet schedule26 février 2013| PAGE
7CEA | 27/02/2013
Slide8DSM IRFUSACMCommissariat à l’énergie atomique et aux énergies alternativesCentre de Saclay |
91191 Gif-sur-Yvette CedexT. +33 (0)1 69 08 71 27 | F. +33 (0)1 69 08 69 49
Etablissement public à caractère industriel et commercial | RCS Paris B 775 685 019
26 février 2013
| PAGE
8
CEA | 10 AVRIL 2012
THANKS FOR YOUR ATTENTION