Challenges In Deploying Temporary Polar Seismic Equipment Challenges In Deploying Temporary Polar Seismic Equipment

Challenges In Deploying Temporary Polar Seismic Equipment - PowerPoint Presentation

mitsue-stanley
mitsue-stanley . @mitsue-stanley
Follow
374 views
Uploaded On 2017-10-12

Challenges In Deploying Temporary Polar Seismic Equipment - PPT Presentation

Paul Carpenter IRIS PASSCAL 6112013 Outline Current Systems amp Design P hilosophy Schedule Logistics Challenges from Field Conditions Design philosophy Current Systems amp Design Philosophy ID: 595312

field amp philosophy design amp field design philosophy logistics current systems install shipping arctic antarctic life work ice schedule

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Challenges In Deploying Temporary Polar ..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Challenges In Deploying Temporary Polar Seismic Equipment

Paul Carpenter

IRIS / PASSCAL

6/11/2013Slide2

OutlineCurrent Systems & Design PhilosophyScheduleLogisticsChallenges from Field ConditionsDesign philosophySlide3

Current Systems & Design PhilosophyCurrent systems well built and designedHigh data returnFurther refinementEasy to install or serviceSlide4

January

February

March

April

May

June

July

August

September

October

November

December

Schedule

Antarctic Prep

Antarctic Shipping

Antarctic Field Work

Arctic Field Work

Arctic Shipping

Arctic PrepSlide5

Logistics to the IceLong shipping lead timesDocumentation & paperworkHold upsWeatherEnvironmentalMechanicalSlide6

Logistics on the IceStaging AreaPaperwork & coordinationEquipment handlingStorageEquipment MovementPre Site visit prepWeather has a large roleSlide7

Field lifeBig or small campSeveral to no support staffSubjected to weatherCamping life styleDiet changesRemoved from society24 Hour SunlightSlide8

WeatherDynamic weatherLow temperaturesWindDry or WetWarm!?Clothing managementRemember to review body conditionSlide9

Climate & TerrainSnow & IceCrevasseBlue IceAnimalsAccumulationAltitude0’ to >10,000’Slide10

Field Crew at SitePhysical stateLong hoursFatigue, exhaustionMental stateStressDistractedSlide11

Design PhilosophyEasy to install or servicePre-assembled Ready and runningMinimal construction neededModularQuick swap componentsEasy to read and understand lights or screensSlide12

Design Philosophy cont.One Opportunity to Install or ServiceFocusSensor placementData recording