24 FEBRUARY 2015 PORTFOLIO COMMITTEE ON BASIC EDUCATION CONTENTS BACKGROUND AND OVERALL ASIDI PROGRESS FOR 201415 FINANCIAL YEAR Financial and NonFinancial DETAILED NONFINANCIAL PROGRESS ID: 514188

batch projects implemented schools projects batch schools implemented progress idms construction water sanitation due practical completion idt number 2014

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "PROGRESS AND STATUS OF THE ACCELERATED S..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

PROGRESS AND STATUS OF THE ACCELERATED SCHOOL INFRASTRUCTURE DEVELOPMENT INITIATIVE (ASIDI)

24 FEBRUARY 2015

PORTFOLIO COMMITTEE ON BASIC EDUCATIONSlide2

CONTENTSBACKGROUND AND OVERALL ASIDI PROGRESS FOR 2014/15 FINANCIAL YEAR (Financial and Non-Financial);DETAILED NON-FINANCIAL PROGRESSDETAILED FINANCIAL PROGRESS

SOCIAL FACILITATION STATUS

2Slide3

CONTENTSBACKGROUND AND OVERALL ASIDI PROGRESS FOR 2014/15 FINANCIAL YEAR (Financial and Non-Financial);DETAILED NON-FINANCIAL PROGRESSDETAILED FINANCIAL PROGRESS

SOCIAL FACILITATION STATUS

3Slide4

Background and Overall ASIDI ProgressSlide5

SCHEDULE 7: SCHOOL INFRASTRUCTURE BACKLOGS GRANTThe purpose of the grant is for the eradication of entire inappropriate schools;provision of basic level of water, sanitation and electricity to schools. The grant is also referred to as the ASIDI (Accelerated Schools Infrastructure Delivery Initiative)5Slide6

ASIDI SCOPE OF WORKS (objectives and intentions)On all four sub-programs the services provided adhere to GUIDELINES RELATING TO PLANNING FOR PUBLIC SCHOOL INFRASTRUCTURE Inappropriate structures (entire mud schools, plankie schools, corrugated sheeting structures and prefab schools which are no longer fit-for-purpose) Learning and teaching spaces, water, sanitation, electricity and furniture

Water Supply (schools that never had water)Municipal connection where reticulation exists.Ground water exploration and boreholes where the yield and water quality is of acceptable standard.

Rain water harvesting and Elevated water tanks for storage of potable water for immediate or future use.

Sanitation provision

(schools that never had sanitation)

Waterborne sewerage systems where sufficient water is available,

Enviro-

loos

as well as

Ventilated Improved Pit (VIP) Latrines.

Electrification

(school that never had electricity)

As far as is possible Schools are connected to the electrical grid through ESKOM.

In those instances where Grid Electricity is not available Solar Electricity is provided.

 

6Slide7

ASIDI SCOPE OF WORKS 

Inappropriate

Electricity

Sanitation

Water

Provinces

Baseline

Actual to date

Baseline

Actual to date

Baseline

Actual to date

Baseline

Actual to date

Eastern Cape

442

458

317

221

344270619538Free State303014387684610164Gauteng2022281400KwaZulu Natal3311615614050230255Limpopo3314257778121102Mpumalanga55148538211719North West2241429211615Northern Cape11002617129Western Cape222577212144Total51052791653574153811201006

7Slide8

ASIDI PROGRAMME BUDGET ALLOCATIONFinancial Year (ending 31 March)

Budget Amount (‘000)

Division of Revenue Act 2014

Division of Revenue Act 2013

Division of

Revenue Act 2012

Division of

Revenue Act 2011

FY11/12**

R700 000

R700 000

R700 000

R700 000

FY12/13**

R2 065 000

R2 065 000

R2 065 000

R2 315 000

FY13/14**

R2 489 000R2 489 000R5 189 000R5 189 000FY14/15R2 938 500R3 170 000R5 500 340-FY15/16***R2 433 310R2 912 000--FY16/17***R2 610 660---TOTALR13 236 470R11 336 000R13 454 340R8 204 0008Slide9

ASIDI TARGETS AND PROJECTIONS FOR INAPPROPRIATE SCHOOLS  

Baseline

Actual to date

2011/12

2012/13

2013/14

2014/15

2015/16

2016/17

2017/18

Total

APP targets (Projected number of schools which will go into implementation)

510

527

-

49

140

150171--510Actual/ projected No of schools rolled out for implementation  4915199228---527Actual/Projected number of schools built/to be built   173662**107150155527**To date, 39 schools have been completed for 2014/159Slide10

ASIDI PROGRESS – INAPPROPRIATE SCHOOLS Sub Programme

Inappropriate schools

Fin Year

 Target 

2011/12

2012/13

2013/14

2014/15

2015/16

APP

targets

510

-

49

140

150

171

No of schools and the year of roll out

49

15199 Year of Completion  173639Appointed IAs are DBSA, IDT, CDC, Adopt A Schools, ECDPW, NDPW, FSED and WCED.299 schools have been allocated to IAs. The balance of the projects are in EC.Since inception 92 schools have been completed as follows:In Eastern Cape 78 schools have been completedIn WC 9 schools have been completedIn Mpumalanga 3 schools have been completedIn Free State 2 schools have been completed 10Slide11

ASIDI PROGRESS - WATERSub Programme

Water

Fin Year

Target  

2011/12

2012/13

2013/14

2014/15

App

Targets

1120

188

932

-

-

Completed

342

 

156

49137Implementing Agents are KZNED, WCED, NWED, GED, FS ED, CSIR, Mvula Trust, IDT, CDC and Mhlathuze Water. All projects are in implementation.Since inception 342 schools have been completed as follows:In Eastern Cape - 131In FS - 30In Gauteng – n/aIn KZN - 74In Limpopo - 91In Mpumalanga - 10In NW - 3In NC - nilIn WC - 311Slide12

ASIDI PROGRESS - SANITATIONSub Programme

Sanitation

Fin Year

Target  

2011/12

2012/13

2013/14

2014/15

APP targets

741

354

387

-

-

Completed

351

 

188

64

99Implementing Agents are KZNED, WCED, NWED, GED, FS ED, CSIR, Mvula Trust, IDT, CDC and Mhlathuze Water. All projects are in implementation.Since inception 351 schools have been completed as follows:In Eastern Cape - 139In FS - 13In Gauteng – 14In KZN - 72In Limpopo - 73In Mpumalanga - 9In NW - 9In NC - 3In WC - 1912Slide13

ASIDI PROGRESS - ELECTRIFICATIONSub Programme

Electrification

Fin Year

Target 

2011/12

2012/13

2013/14

2014/15

APP Targets

914

 

231

 

683

 

 

Completed

288

 

1447767Implementing Agents are WCED, GED, FS ED, and ESKOM. All projects are in implementation.Since inception 288 schools have been completed as follows:In Eastern Cape - 166In FS - 23In Gauteng – 2In KZN – 43In Limpopo - 5In Mpumalanga - 39In NW - 2In NC - n/aIn WC - 813Slide14

DETAILED NON-FINANCIAL PROGRESS Slide15

IA Baseline ASIDI IPMP No of projects Allocated as per Appointment letterNo of projects Cancelled due to sufficient infrastructure

No of Projects Cancelled due to closures No of Projects added as change of scope

Total No of Projects to be implemented

The

Mvula

Trust (Batch I) Water

84

84

2

0

0

82

The

Mvula

Trust (Batch I) Sanitation

60

60

1

0

059The Mvula Trust (Batch II) Water121121870106The Mvula Trust (Batch II) Sanitation575727113049IDT (Batch I) Water13413460 0128IDT (Batch I) Sanitation797980071IDT (Batch II) Water969620094IDT (Batch II) Sanitation5959130046CSIR (Batch I) Water152 1650390126CSIR (Batch I) Sanitation63 5007043Total905905676430804EASTERN CAPE PROVINCEWATER AND SANITATION - Scope of WorksTotal Water projects to be implemented is 536Total Sanitation projects to be implemented is 26815Slide16

IATotal No of Projects to be implemented No of projects at Planning (IDMS)No of projects at detailed design (IDMS)

Tender/ProcurementNo of Projects in execution (IDMS)

No of Projects at close out (IDMS)

The

Mvula

Trust Batch 1

141

0

0

0

0

141

The

Mvula

Trust

Batch 2

154

0

0

051103IDT Batch 119900012277IDT Batch 21400014000CSIR Batch 116900431260Total804183299322EASTERN CAPE PROVINCEWATER AND SANITATION -Progress16Slide17

 No of Projects in executionPer IA

No of Projects to be implementedNo of projects with construction at 25%

No of projects with construction at 50%

No of projects with construction at 75%

No of projects at PC

The

Mvula

Trust (Batch I) Water

82

0

0

0

82

The

Mvula

Trust (Batch I) Sanitation

59

0

0

059The Mvula Trust (Batch II) Water106004660The Mvula Trust (Batch II) Sanitation4900544IDT (Batch I) Water12817364925IDT (Batch I) Sanitation710111952IDT (Batch II) Water940000IDT (Batch II) Sanitation460000CSIR (Batch I) Water 1261553580CSIR (Batch I) Sanitation 430000TOTAL80432100177322EASTERN CAPE PROVINCEWATER AND SANITATION – Progress (cont.)Total Water projects at PC are 167Total Sanitation projects at PC are 15517Slide18

No of projects that achieved/ or are to achieve PC Per IACumulative at Q3

Jan-15

Feb

-15

Mar

- 15

The

Mvula

Trust (Batch I) Water

82

0

0

0

The

Mvula

Trust (Batch I) Sanitation

59

0

0

0The Mvula Trust (Batch II) Water4701515The Mvula Trust (Batch II) Sanitation46050IDT (Batch I) Water001014IDT (Batch I) Sanitation33086IDT (Batch II) Water0000IDT (Batch II) Sanitation0000CSIR (Batch I) Water 001515CSIR (Batch I) Sanitation0 000Total26705350EASTERN CAPE PROVINCEWATER AND SANITATION – Practical Completions18Slide19

IA Baseline ASIDI IPMP No of projects Allocated as per Appointment letterNo of projects Cancelled due to sufficient infrastructure

No of Projects Cancelled due to closures No of Projects added as change of scope

Total No of Projects to be implemented

DBSA (Batch I)

50

50

1

 

0

 

0

49

DBSA (Batch II)

50

50

0

 

0

 

0 50IDT (Batch I)141420 0 12IDT (Batch II)3636 00 0 36CDC (Batch I)323280 125DPW (Batch I)16160 1116NDPW (Batch I)36360 0 0 36TOTAL2342341112224EASTERN CAPE PROVINCEINAPPROPRIATE STRUCTURES – TARGETS19Slide20

IATotal No of Projects to be implemented No of projects at Planning (IDMS)No of projects at detailed design (IDMS)

No of projects at tender/procurement

No of Projects in execution (IDMS)

No of Projects at close out (IDMS)

DBSA (Batch I)

49

0

0

0

0

49

DBSA (Batch II)

50

0

0

0

50

0

IDT (Batch I)

1200039IDT (Batch II)36003600CDC (Batch I)25310516DPW (Batch I)1600394NDPW (Batch I)36360000Total224391396778EASTERN CAPE PROVINCEINAPPROPRIATE STRUCTURES – PROGRESS20Slide21

 No of Projects in executionPer IA

No of Projects with work commenced No of projects with progress less than 25 %

No of projects with construction at 25%

No of projects with construction at 50%

No of projects with construction at 75%

No of projects at PC

DBSA (Batch I)

49

0

0

0

0

49

DBSA (Batch II)

50

11

20

12

7

0IDT (Batch I)1210029IDT (Batch II)3600000CDC (Batch I)25010416DPW (Batch I)1603244NDPW (Batch I)3600000Total2241224141778EASTERN CAPE PROVINCEINAPPROPRIATE STRUCTURES – PROGRESS (cont.)21Slide22

EASTERN CAPE PROVINCE Inappropriate Structures - Actual PC and Projected PC No of projects that achieved/ or are to achieve PC

Per IA

Cumulative at

Q3

Jan

- 15

Feb

- 15

Mar

-15

DBSA (Batch I)

49

0

0

0

DBSA (Batch II)

0

0

0

2IDT (Batch I)9010IDT (Batch II)0000CDC (Batch I)16044DPW (Batch I)4004NDPW (Batch I)0000Total78051022Slide23

WESTERN CAPE PROVINCEInappropriate SchoolsIADate of Appointment

No of projects Allocated as per Appointment

letter

No of projects Cancelled due to sufficient infrastructure

No of Projects Cancelled due to closures

No of Projects added as change

of

scope

Total No of Projects to be implemented

WCED

17-MAY-12

25 (14

+11)

0

0

0

25

Total

 

25251. Number of projects being implementedIATotal No of Projects to be implemented No of projects at Planning (IDMS)No of projects at detailed design (IDMS)No of Projects in execution (IDMS)No of Projects at close out (IDMS)WCED Batch 11400140WCED Batch 21100110Total252502. Progress in terms of number of projects being implemented23Slide24

WESTERN CAPE PROVINCEInappropriate Schools3. Number of Projects in ExecutionPer IA

No of Projects with work commenced

Construction at:

0 to 25 %

Construction at:

26 to 50 %

Construction at:

51

to

75 %

Construction at:

76

to

99 %

Projects

at

Practical Completion

WCED Batch 1

 

14 006(62% Average)6(91% Average)2WCED Batch 2 11 2 (23% average)6 (37% Average)0 3 (87% Average)0 Total2526692Note / Comments:West Coast Cluster (3 Schools) – Replacement Contractor (H&I) was appointed and sites was handed over to them in December ‘14. 24Slide25

WESTERN CAPE PROVINCEInappropriate Schools4. Practical Completion Projections for Western Cape:

Project Name:

Practical Completion and

Planned Practical

Completion

Dates:

Delta PS

Phase 1 - 06/05/2014

Phase 2 – 30/03/2015

De

Duine

PS

Phase 1 - 23/06/2014

Phase 2 – 27/02/2015

Sophumelela SS

Phase

1 -

16

/07/2014

Phase 2 – 12/12/2014Hawston PSPhase 1 - 17/07/2014Phase 2 – 15/05/2015Kensington SSPhase 1 - 17/04/2014Phase 2 – 16/01/2015Portia PSPhase 1 - 07/08/2014Phase 2 – 30/03/2015Heideveld PSPhase 1 - 27/08/2014Phase 2 – 30/03/2015Knysna SSS Phase 1 – 16/08/2013Phase 2 – 04/06/2014Phase 3 – 16/08/2014Phase 4 – 12/02/2015Kasselsvlei PSPhase 1 – 29/01/2015Phase 2 – 30/04/2015Sophakama PSPhase 1 - 30/04/2015Phase 2 – 30/07/2015Valhalla PSPhase 1 – 06/02/2015Phase 2 – 30/06/2015Parkview PSPhase 1 – 30/08/2015Phase 2 – 31/10/2015Wesfleur PSPhase 1 – 30/08/2015Phase 2 – 31/10/2015Willemsvallei PSPhase 1 – 30/08/2015Phase 2 – 31/10/20154.1. WCED Batch 2: 4.2 WCED Batch 1:Project Name:Planned Practical Completion Dates:Mount View SSPhase 1 - 14/11/2014Phase 2 – 02/07/2015Phase 3 – 29/09/2015Voorspoed PSPhase 1 - 15/05/2015Phase 2 – 11/08/2015Red River PSPhase 1 - 23/07/2015Silverstream PSPhase 1 - 17/02/2015Phase 2 – 19/10/2015Scottsdene SSPhase 1 – 23/10/2014Phase 2 - 08/05/2015Phase 3 – 08/05/2015Delft South PSPhase 1 - 04/06/2015Rosewood PSPhase 1 - 25/02/2015Phase 2 – 07/04/2015Tygersig PSPhase 1 - 26/02/2015Phase 2 – 07/05/2015Du Noon PSPhase 1 +2 - 12/06/2015Phase 3- 14/08/2015Vooruitsig PSPhase 1 - 01/06/2015Phase 2 – 18/09/2015Swartberg SSPhase1 - 12/12/2014Phase 2 – 30/03/2015.25Slide26

MPUMALANGA PROVINCEInappropriate SchoolsIADate of Appointment

No of projects Allocated as per Appointment

letter

No of projects Cancelled due to sufficient infrastructure

No of Projects Cancelled due to closures

No of Projects added as change

of

scope

Total No of Projects to be implemented

DBSA

27-NOVEMBER -12

5

0

3

3

5

Total

 

5

3351. Number of projects being implementedIATotal No of Projects to be implemented No of projects at Planning (IDMS)No of projects at detailed design (IDMS)No of Projects in execution (IDMS)No of Projects at close out (IDMS)DBSA50023Total500232. Progress in terms of number of projects being implemented26Slide27

MPUMALANGA PROVINCEInappropriate Schools3. Number of Projects in ExecutionPer IA

No of Projects with work commenced

Construction at:

0 to 25 %

Construction at:

26 to 50 %

Construction at:

51

to

75 %

Construction at:

76

to

99 %

Projects

at

Practical Completion

DBSA

5 001 Tiyimeleni @ 72%1Wesselton @ 78%3Loding @ 100%Goba @ 100 %Ngema @ 100%Total50011327Slide28

MPUMALANGA PROVINCEInappropriate Schools4. Practical Completion Projections for Mpumalanga:

Project Name:

Practical Completion and

Planned Practical

Completion

Dates:

Ngema PS (100%)

Practical

Completion

-

12/11/2014

Works Completion – 08/12/2014

Planned Final Completion – 28/02/2015

Wesselton

PS (78%)

Planned Practical

Completion

- 11/03/2015Planned Works Completion – 07/04/2015Planned Final Completion – 19/07/2015Tiyimeleni PS (72%)Practical Completion - 14/03/2015Works Completion – 02/04/2015Planned Final Completion – 30/06/2015Goba PS (100%)Practical Completion - 05/11/2014Works Completion – 22/01/2015Planned Final Completion – 24/04/2015Loding PS (100%)Practical Completion - 22/08/2014Works Completion – 10/11/2014Planned Final Completion – 16/02/2015 .28Slide29

MPUMALANGA PROVINCEWater and Sanitation1. Number of projects being implemented2. Progress in terms of number of projects being implemented

IA

Date of Appointment

No of projects Allocated as per Appointment letter

No of projects Cancelled due to sufficient infrastructure

No of Projects Cancelled due to closures

No of Projects added as change of scope

Total No of Projects to be implemented

TMT (BATCH1) WATER

May

2012

25

0

7

2

20

TMT

(BATCH 1 ) SANITATION

May 2012

10021220Total (TMT) BATCH 135091240IATotal No of Projects to be implemented No of projects at Planning (IDMS)No of projects at detailed design (IDMS)No of Projects in execution (IDMS)No of Projects at close out (IDMS)TMT(Batch 1) Water2000200TMT(Batch 1) Sanitation2000200Total (TMT) Batch 1400040029Slide30

MPUMALANGA PROVINCEWater and Sanitation3. Number of Projects in Execution

Per IA

No of Projects with work commenced

Construction at:

0 to 25 %

Construction at:

26 to 50 %

Construction at:

51

to

75 %

Construction at:

76

to

99 %

Projects

at

Practical Completion

TMT(Batch 1) Water

20011612TMT (Batch 1) Sanitation2001199Total (TMT) Batch 140022152130Slide31

FREE STATE PROVINCEInappropriate SchoolsIADate of Appointment

No of projects Allocated as per Appointment

letter

No of projects Cancelled due to sufficient infrastructure

No of Projects Cancelled due to closures

No of Projects added as change

of

scope

Total No of Projects to be implemented

IDT

21-Jun-12

10

0

0

0

10

DBSA

27-Nov-12

10

00111FS DoE14-May-13103029Total 30303301. Number of projects being implementedIATotal No of Projects to be implemented No of projects at Planning (IDMS)No of projects at detailed design (IDMS)No of Projects in execution (IDMS)No of Projects at close out (IDMS)IDT100190DBSA1101100FS DoE99000Total30921902. Progress in terms of number of projects being implementedIDT: - Sehlabeng - contractor still be to appointed. DBSA: - Construction on (Metsimatle) is delayed due to EIA study. EIA approved in Jan 2015FS DoE: - Number of projects reduced to due to zero progress achieved since May 201331Slide32

FREE STATE PROVINCEInappropriate Schools (Continued)3. Number of Projects in ExecutionPer IA

No of Projects in execution (IDMS)

Construction at:

0 to 25 %

Construction at:

26 to 50 %

Construction at:

51

to

75 %

Construction at:

76

to 100

%

Projects

at

Practical Completion

IDT

9

21321DBSA10 03331 FS DoE0 00000Total192465232Slide33

FREE STATE PROVINCEInappropriate Schools (Continued)4.1 Progress and Practical Completion Projections for IDTSchool Name

Contract Amount

Site Handover Date

Contract Practical Completion Date

Revised Practical Completion Date

Contract Period Elapsed (%)

Physical Progress to Date (%)

Caledon Park Primary School

R

32 998 207.90

17/07/2013

02/06/2014

18/12/2014

132%

84%

Diamanthoogte Intermediate School

Pending

TBC

TBCTerminated on 28 July 2014TBC27%Heide Primary SchoolR 40 993 926.0007/08/201313/09/201416/12/2014102%66%Itemoheng Primary SchoolR 39 490 634.2611/10/201308/09/201431/01/2015116%63%Luckhoff Combined SchoolR 55 774 398.0420/11/201304/12/201419/02/201596%62%Nampo Secondary SchoolR 41 297 045.1616/07/201322/08/201425/03/2015111%77%PT Sanders Intermediate SchoolR 41 893 366.6107/08/201313/09/201413/09/2014100%93%Boshof Intermediate SchoolPendingTBCTBCTerminated on 5 Feb 2014TBC16%Sehlabeng Secondary SchoolPendingTBCTBCTBCTBC0%Tweespruit Primary SchoolPendingTBCTBCTerminated on 15 April 2014TBC3% Note: Contract amounts exclude decanting works figures33Slide34

FREE STATE PROVINCEInappropriate Schools (Continued)4.2 Progress and Practical Completion Projections for DBSA Schools

Project Name:

Contract Amount

Contract Start

Date

Anticipated Practical

Completion

Contract Period Elapsed (%)

Actual Physical

Progress

(%)

Bethlehem C/S

53,354,164.86

16 April 2014

8 Apr 2015

69%

43%

Ntsu S/S

65,377,645.8716 April 201428 Feb 201573%46%Clarens P/S29,030,087.6129 Aug 201431 Mar 201541%26%Dorrington Matsepe I/S72,562,777.26 18 March 201417 Feb 201582%82%Phephetso S/S53,477,082.2018 March 201431 Jan 201590%84%Vredefort P/S40,205,392.3219 March 201419 Dec 2014100%100%Lehutsho P/S47,560,854.95 20 March 201415 Dec 201497%90%Metsimatle S/SDelayedDelayedDelayedDelayedEIA approvedPele-ya-Pele S/S29,835,380.7220 March 201415 Feb 201579%34%Qalabotjha S/S28,695,588.66 25 March 201427 Feb 201581%38%Tjhebelopele P/S45,463,919.26 26 March 201419 Jan 201590%75%34Slide35

FREE STATE PROVINCEInappropriate Schools (Continued)5. Independent Development trust (IDT)Practical Completion:PT Sanders has successfully reached Practical Completion on 9

th October 2014 and the new structures were handed over. Delay in removal of the 5 remaining decanting units by FS DoE impacted negatively on completion of sports field.

Penalties

Contractors

at Caledon

Park

I/S,

Itemoheng

P/S,

Heide

P/S

and

Nampo

S/S

): are on penaltiesNampo: Poor workmanship at Nampo S/S is being addressed. However, the contractor is on penalties.

Outstanding Appointments

Sehlabeng:

Contractor to be appointed.

35Slide36

FREE STATE PROVINCEInappropriate Schools (Continued)5. Independent Development trust (IDT) – continuedTerminations:Three(3) Contracts were terminated due to lack of progress.

(Boshoff I/S – 6 February 2014, Tweespruit P/S – 16 April 2014, and

Diamanthoogte

– 28 July 2014)

IDT forwarded

Boshoff I/S and Tweespruit P/S replacement Contractors’ request for concurrence to DBE.

However, IDT is uncertain

on how the difference in original tender amounts for terminated Contractors and proposed new Contractors would be paid. DBE has requested IDT to clarify how the variance will be dealt

with. IDT response remains outstanding

General - IDT

Slow rate of progress on various IDT’s sites remains a concern

Notice of default and intention to terminate IA

MoA

was issued to IDT by DBE on 29 July 2014, and IDT responded on 14 August 2014.

36Slide37

FREE STATE PROVINCEInappropriate Schools (Continued)Development Bank of SA (DBSA)DBSA have appointed Contractors for 11 schools and handed over 10 out of the 11 sites.DelaysPele Ya Pele School: The contractor experienced delays due to clashing with undetected water and electrical services running beneath the construction site.  

Qalabotjha S/S: Ground water issues were resolved. A notice for Extension of Time has been received but not yet approved. Recovery plan still outstanding.Delay in Tranche payments is causing late payment to Contractors. This

could

have negative impact on the programme 

37Slide38

6. Development Bank of SA (DBSA) - continuedDelaysTjhebelopele P/S: The Contractor was delayed by the steel strike.   The EoT claim is currently being reviewed.  Metsimatle

Secondary School: A delay in the approval of an Environmental Impact Assessment by the Department of Economic Development, Tourism and Environmental Affairs (DETEA) resulted with delay in commencement of this project. The EIA was approved in Jan 2015. DBSA will commence with procurement process.

FREE STATE PROVINCE

Inappropriate Schools (Continued)

38Slide39

7. General Comments: FS DoE The FS DoE was appointed to implement replacement of inappropriate schools on 14 May 2013 and to date conceptualisation and design for these schools has not started.The FS DoE was issued with a Final Notice letter dated 25 August 2014 re: Final Notice and Intention to Terminate On 05 February 2015 the

DBE has taken a decision to reduce the scope of work of the FS DoE on the ASIDI programme to only be limited to the basic services projectsThe 9 inappropriate schools project will no longer form part of the projects being implemented by the

FS DoE

FREE STATE PROVINCE

Inappropriate Schools (Continued)

39Slide40

FREE STATE PROVINCEWater and SanitationIADate of AppointmentNo of projects Allocated as per Appointment letter

No of projects Cancelled due to sufficient infrastructure

No of Projects Cancelled due to closures

No of Projects added as change of scope

Total No of Projects to be implemented

FS DoE Water

14-Dec-12

37

0

8*

0

29

FS DoE Sanitation

14-Dec-12

36

0

0

0

36

FS DoE Electricity14-Dec-1264012*12**64Total 137020121291. Number of projects being implementedIATotal No of Projects to be implemented No of projects at Planning (IDMS)No of projects at detailed design (IDMS)No of Projects in execution (IDMS)No of Projects at close out (IDMS)FS DoE Water2900290FS DoE Sanitation3603600FS DoE Electricity64054100Total129090390* FS DoE have identified 8 water schools and 12 electrical schools where teaching activity has ceased since Jan 2014.**FS DoE have indicated the addition of 12 electrical projects.2. Progress in terms of number of projects being implemented40Slide41

FREE STATE PROVINCEWater and Sanitation (Continued)3. Number of Projects in ExecutionPer IA

No of Projects with work commenced Construction

0% to

25%

Construction at

26% to 50%

Construction at

51% to 75%

Construction at

76% to

100%

No of projects at PC

FS DoE Water

29

34

0

0

0

0FS DoE Sanitation000000FS DoE Electricity1000090Total390343490 4. Free State Department of Education (FSDoE)4.1 Water: FS DoE Water Contractors appointments were approved by DBE and FS DoE had aligned the SDPs and BOQ. Variation Orders were submitted to DBE/PSU, however additional information was requested by DBE PSU from FS DoE and remains outstanding;41Slide42

FREE STATE PROVINCEWater and Sanitation (Continued)4.2 Sanitation: No SDPs approved to date. No appointments of contractors made to date.

Request for concurrence for appointment of contractors was forwarded to DBE. Concurrence was declined due to non-compliance with PFMA & PPPFA.

4.3

Electricity:

No appointments of contractors for installation made to date

and tender validity period has expired.

Request for concurrence for appointment of contractors was forwarded to DBE. Concurrence was declined due to non-compliance with PFMA.

4.4

General

FSDoE

have indicated their intention to re-tender sanitation and electricity projects

FSDoE

to submit formal request to DBE for re-tendering of the sanitation and electrical projects.

42Slide43

GAUTENG PROVINCEWater and Sanitation1. Number of projects:IA

Date of Appointment

No of projects Allocated as per Appointment

letter

No of projects Cancelled due to sufficient infrastructure

No of Projects Cancelled due to closures

No of Projects added as change

of

scope

Total No of Projects to be implemented

Electricity:

2011/2012

04-May-12

2

0

0

0

2

Water:2013/201404-May-120001010Sanitation:2011/201204-May-12770772013/201404-May-121414+40117Total 232502826No of Projects allocated as per DBE Appointment letter (reference 003), signed and dated 14th December 2012.Total No of Projects added as per scope change approved by DBE on 23rd July 2013, for work to be complete under the following Categories - Category (i) Conversion of pit latrines to water borne systems, (7 No.) - Category (ii) Replace septic tanks with conservancy tanks (11 No.). - Category (iii) Water quality and water pressure (10 No.)A further 4 schools from Category ii removed as per DBE scope change Letter 007, signed and dated 27th June 201443Slide44

GAUTENG PROVINCEWater and SanitationIATotal No of Projects

to be implemented

No of projects at Planning (IDMS)

No of projects at detailed

design

(IDMS)

No of Projects in execution (IDMS)

No of Projects at

close

out (IDMS)

Electricity:

2

0

0

0

2

2011/2012

Water:2013/20141001000Sanitation:2011/2012700072013/20147070Total26017092. Progress in terms of number of projects being implemented44Slide45

GAUTENG PROVINCEWater and Sanitation (Continued)3. Gauteng Department of Education (GDE)2013/2014 List of schools:C

ategory (ii) – Replacement of Septic Tanks with Conservancy Tanks at 11 schools still to be done. Category (iii) – Improvement of water quality and pressure at 10 schools still to be done.

Following the DBE’s decline for concurrence for appointment of preferred contractor by Rand Water Foundation, GDE terminated their agreement with Rand Water Foundation.

DBE is intending to takeover the management of the implementation of 2013/14 projects

45Slide46

Progress: Adopt-A-SchoolKWAZULU NATAL PROVINCEInappropriate Schools

Project Name:

DBE Estimates

AAS Contract Amount incl.

Approved VO’s

Contract

Start

Date

Planned Practical

Completion

Lembe

Primary

R

28,076,202.03

R 17,001,612.00

1 April

2014

30 Sept

2015Enhlanhleni Primary R 25,792,789.18R 21,208,284.001 April 201430 Sept 2015Ingweni PhaphamaR 26,239,357.28R 18,920,024.001 July 201431 Dec 2015Project Name:Contract Amount incl. approved VO’sContract Start DatePlanned Practical CompletionContract Period Elapsed (%)Actual Physical Progress (%)Lembe Primary R 17,001,612.00 1 Apr 201430 Sept 201553%56%Enhlanhleni R 21,208,284.001 Apr 201430 Sept 201553%43%Ingweni Phaphama* R 18,920,024.001 Nov 201431 Dec 201516%31%46Slide47

KWAZULU NATAL PROVINCEWater and Sanitation1. Number of projects being implemented

IA

Date of Appointment

No of projects Allocated as per Appointment letter

No of projects Cancelled due to sufficient infrastructure

No of Projects Cancelled due to closures

No of Projects added as change of scope

Total No of Projects to be implemented

MW WATER

07-Dec-12

79

7

1

0

71

MW SANITATION

07-Dec-12

10

3

007Total (MW) 89101078CDC WATER07-Dec-127042064CDC SANITATION07-Dec-122022016Total (CDC) 9064080IDT WATER07-Dec-126921773IDT SANITATION07-Dec-1220211027Total (IDT) 894*2*1710047Slide48

KWAZULU NATAL PROVINCEWater and Sanitation (Continued)2. Progress in terms of number of projects being implemented

IA

Total No of Projects to be implemented

No of projects at Planning (IDMS)

No of projects at detailed design (IDMS)

No of Projects in execution (IDMS)

No of Projects at close out (IDMS)

MW WATER

71

0

0

 

55

 

16

MW SANITATION

7

0

0

16Total (MW)78005622CDC WATER65074414CDC SANITATION1503102Total (CDC)800105416IDT WATER73004429IDT SANITATION27001413Total (IDT)10000584248Slide49

KWAZULU NATAL PROVINCEWater and Sanitation (Continued)3. Number of Projects in Execution

Per IA

No of Projects with work commenced

Construction at 25%

Construction at 50%

Construction at 75%

No of projects at PC

MW WATER

 

71

0

0

45

26

MW SANITATION

7

0

0

1

6Total (MW)78004632CDC WATER57003225CDC SANITATION130094Total (CDC)70004129IDT WATER73014527IDT SANITATION2703618Total (IDT)100045145Total KZN2480413810649Slide50

Development Bank of Southern AfricaDate of appointment : 27 November 2012Number of schools allocated : 3The contractor at Sedibeng Special School – expected to reach PC by 14 Jan 2015

The contractor at Molepo Primary School – expected to reach PC by 28 Feb 2015

The

contractor at

Honoko

Primary

School)

has managed to make significant progress following the delays experienced from the rock. There contractor is experiencing some difficulty in getting material delivered onto the site but has made suitable interventions to deal with the situation

. The contractor is expected to reach PC by 5 Mar 2015.

LIMPOPO PROVINCE

Inappropriate Schools

Project Name:

Contract Amount

Contract

Start

Date

Planned Practical

Completion

Contract Period Elapsed (%)Planned Physical ProgressActual Physical Progress (%)Molepo Primary SchoolR26,540,123.40 20 March 201428 Jan 2015100%70%98%Sedibeng Special SchoolR 7,502,547.48 19 March 201420 Dec 2014100%70%98%Honoko PrimarySchoolR 4,249,285.6618 April 20145 Mar 201580%40%60%50Slide51

LIMPOPO PROVINCEWater and SanitationIADate of Appointment

No of projects Allocated as per Appointment

letter

No of projects Cancelled due to sufficient infrastructure

No of Projects Cancelled due to closures

No of Projects added as change

of

scope

Total No of Projects to be implemented

Water

10-May-2012

83

12

5

0

64

Sanitation

10-May-2012

37

20035Total10-May-12115  14* 50991. Number of projects being implemented*Mvula Trust submitted a list of 19 schools which were not implemented as they had proper infrastructure or closed** 1 No. water school not found, not even on NEIMS. Mvula Trust to submit scope change to remove these schools from ASIDI Master ListThe Limpopo Provincial Department of Education has been requested to confirm the latter findings, where-after an application will be lodged to have these projects been removed from the list of projects to be implemented.2. Number of Projects in ExecutionPer IANo of Projects with work commenced Construction at 26% to 50%Construction at 50 51% to 74%Construction at 75% to 100%No of projects at PCWater6400857Sanitation3500034Total990089151Slide52

LIMPOPO PROVINCEWater and SanitationNo. of projects that achieved / or are to achieve PC

Per

IA

(

Mvula

Trust)

No. of Projects to be implemented

Cumulative at

Q2

Oct 2014

Nov 2014

Dec 2014

2015

Water

64

57

0

0

0

7Sanitation35340001Total9991000852Slide53

Development Bank of Southern AfricaDate of appointment : 27 November 2012Number of schools allocated : 2DBSA have appointed inappropriate school contracts and sites handed over as follows:

The

contractor at

Motaung

Primary

School is

22days behind time - delays due to steel strikes

The

contractor at

Toevlug

Primary

School

submitted a VO for an

EoT

for 11days due to the construction of retaining walls

NORTH WEST PROVINCE

Inappropriate Schools

Project Name:

Contract Amount

Contract Start DateRevised Practical CompletionContract Period Elapsed (%)Planned Physical ProgressPhysical Progress to Date (%)Motaung Primary SchoolR 44,846,815.19 18 Mar 201412 Feb 2015100%100%90%Toevlug Primary SchoolR 34,464,798.06 18 Mar201419 Feb 2015100%100%93%53Slide54

NORTH WEST PROVINCEWater and Sanitation1. Number of projects being implemented

IA

Date of Appointment

No of projects Allocated as per Appointment letter

No of projects Cancelled due to sufficient infrastructure

No of Projects Cancelled due to closures

No of Projects added as change of scope

Total No of Projects to be implemented

Batch

1:

 

 

 

 

 

 

DoE NW

5 Dec

2011

 28130015** IDT Water 30003** IDT San 1200012Batch 2:      DoE NW Water12-Sep-13121*0011DoE NW San12-Sep-1391*008Total 49150034*DoE NW Batch 2: 1 x Water project (Setshabha) and 1 x sanitation project Pemelo Motsheg are removed from list of schools in Batch 2. Schools handed over to Department of Social Development. Scope change approved by DBE 31st July 2014. 54Slide55

NORTH WEST PROVINCEWater and Sanitation (Continued)2. Progress in terms of number of projects being implemented

IA

Total No of Projects to be implemented

No of projects at Planning (IDMS)

No of projects at detailed design (IDMS)

No of Projects in execution (IDMS)

No of Projects at close out (IDMS)

Batch 1:

 

 

 

 

 

IDT Water

3

0

0

3

0

IDT San1202*100Batch 2:     DoE NW Water1111000DoE NW San88000Total34192130*Contractors put on hold. DBE and NWPED agreed to include Sione and Rakoto into Batch 2.No progress made on all Batch 2 projects due to internal SCM challenges within NW PED. In Jan 2015, NW PED surrendered all Batch 2 projects to DBE.55Slide56

* Tirelo Farm School

NORTH WEST PROVINCE

Water and Sanitation (Continued)

3.

Number of Projects in Execution

Per IA

No of Projects with work commenced

Construction at 25%

Construction at 50%

Construction at 75%

No of projects at PC

Batch 1:

 

IDT Water

3

0

 

0

 

03IDT San100 0 1*9Batch 2:00000Total13001124. Practical Completion Projections for North WestPer IATotal No of Projects to be implemented Cumulative since start to end Oct 2014Dec-142015Batch 1:IDT Water3300IDT San12903Batch 2:Water110011San800856Slide57

Development Bank of Southern AfricaDate of appointment : 27 November 2012Number of schools allocated : 1Scope changes : JG Jansen School substituted by SternhamDBSA have appointed Ruwacon (Pty) Ltd; site was handed over on 26th March 2014 and the anticipated Completion is schedule for January 2015

NORTHERN CAPE PROVINCE

Inappropriate Schools

Project Name:

Contract Amount

Contract Start

Date

Planned Practical

Completion

Contract Period Elapsed (%)

Physical Progress to Date (%)

Sternheim

School

R 26,040,840.58

26 Mar 2014

11 Feb 2015

91%

85%

Contractual

Start Date:Planned Practical CompletionPlanned Works CompletionPlanned Final CompletionSternham I/S Phase 1 (65%)26 March 201322 Sept 201412 Nov 201425 Mar 2015Sternham I/S Phase 2 (35%)11 August 201427 Jan 201511 Feb 201557Slide58

NORTHERN CAPE PROVINCEWater and SanitationIA

Date of Appointment

No of projects Allocated as per Appointment letter

No of projects Cancelled due to sufficient infrastructure

No of Projects Cancelled due to closures

No of Projects added as change of scope

Total No of Projects to be implemented

PED WATER

14-Dec-12

5

4

0

0

1

PED SANITATION

14-Dec-12

21

1

2

on hold020Total 2652 on hold021       Split on above per PED appointed IA: FOUR SANITATION SCOPE CHANGED TO WATERPED water 94005PED sanitation 10001IDT San 711 On Hold 06Public Works San 901 On Hold 09Total 2652 On Hold 0211. Number of projects being implemented58Slide59

NORTHERN CAPE PROVINCEWater and Sanitation (Continued)2. Progress in terms of number of projects being implemented

IA

Total No of Projects to be implemented

No of projects at Planning (IDMS)

No of projects at detailed design (IDMS)

No of Projects in execution (IDMS)

No of Projects at close out (IDMS)

PED water

5

0

5

0

0

PED sanitation

1

0

1

0

0

IDT sanitation61 On Hold050Public Works San91 On Hold260Total212 on Hold811059Slide60

NORTHERN CAPE PROVINCEWater and Sanitation (Continued)3.

Number of Projects in Execution

Per

IA

No of Projects with work commenced

Construction at:

0 to 25 %

Construction at:

26 to 50 %

Construction at:

51

to

75 %

Construction at:

76

to

99 %

Projects

at

Practical CompletionPED water300300PED sanitation200110IDT sanitation500023Public Works San600114Total16005444. Practical Completion Projections for Northern CapePer IATotal No of Projects to be implemented Cumulative since start to end Oct 2014Nov-2014Dec-14 to Jan-152015PED Water70670IDT Sanitation63121Public Works San8102260Slide61

Tadcaster – has reached Practical Completion. Challenge with septic tank due to high ground water level. Currently connected to an existing septic tank but there remains questions about the capacity of the tank. Installation of prefab septic tank currently on hold because the building has been vandalised already. PED plan to address situation with principal.Gazes - slow progress, no progress for last 4 months because of community unrest in JT District. NC DoE terminated the contract & intending to appoint a replacement contractorGlenred - No progress for past 4 months due to Community unrest in JT District. NC DoE terminated the contract & intending to appoint a replacement contractorDitshipeng -

Practically Completed and was handed over to school during January. There is a problem with water supply to the tank and the Ablution is not functional. PED is intending drilling a borehole using EIG funds.Kegomoditswe -

Practically Completed. Handed over to the school during April and is in use.

Public Works progress very slow

NORTHERN CAPE PROVINCE

Water and Sanitation (Continued)

5

.

General

61Slide62

ELECTRIFICATION PROGRESS Slide63

ContentsPROGRESS SUMMARY – ElectrificationNo Progress on Batch 1 schools (117/118)Batch 2 schools, 1 school completed for the month of November and December 2014 - (93/169 and 47/122)Actual expenditure reported for November 2014 = R 444,628 in VATActual expenditure reported for

December 2014 = R 1,616,102 in VAT

63Slide64

Progress per Province - Dec64Slide65

DETAILED FINANCIAL PROGRESS Slide66

COMMITMENTS / EXPENDITURE - 2014/15 Fin Year (1)66Slide67

COMMITMENTS / EXPENDITURE - 2014/15 Fin Year (2)67Slide68

CASH FLOW COMPARISON AGAINST NT ALLOCATION(1)68Slide69

CASH FLOW COMPARISON AGAINST NT ALLOCATION(2)69Slide70

CASH FLOW COMPARISON AGAINST IA SUBMISSIONS(1)70Slide71

CASH FLOW COMPARISON AGAINST IA SUBMISSIONS(2)71Slide72

  DoRA ALLOCATION versus ACTUAL EXPENDITURE April - Dec (9 Months) Projected Cash Flow According to DoRA Allocation

R

1 753 846 140

Actual expenditure through BAS

R 1

417 446 439

Balance Treasury Allocation / BAS Expenditure

R

334 399 701

Claims in Process & Accruals

R

840 456 903

Shortfall Treasury Allocation / BAS & In Process

R

-506 057 202

DoRA - CASH FLOW/EXPENDITURE

CASH OUTLAY - DBE

April – Dec (9 Months)

Balance on Tranche Payments

(Un-spend portion) R 591 216 280Actual Expenditure through BAS R 1 417 446 439 Other Opex through BAS R 32 491 385 Total Expenditure according to DBE R 2 041 154 104DoRA Allocation 9 Months R 1 753 846 140Shortfall according to DBE R 287 307 96472Slide73

Graphs73Slide74

74COMPARISON (Dec 2014)Slide75

CLAIMS IN PROCESS & ACCRUALS 31-12-2014 (1)75Slide76

CLAIMS IN PROCESS & ACCRUALS 31-12-2014 (2)76Slide77

BALANCE OF TRANCHE PMT’s AT 2014-12-31 77Slide78

UPDATED TRANCHE BALANCE TO DATE78Slide79

DEVELOPMENT FACILITATION STATUSSlide80

Development Facilitation reporting points per IAASIDI TargetsPSP Jobs createdPSP intern Jobs createdLabour createdLocal Economic Development

Skills developmentGeneral comments

80Slide81

Target Creation of 30 000 work opportunities by the end of the programme

35% of beneficiaries to be women, 30% youth and 2% people with disabilitiesProgress as at end of December 2014

22 245 Job Opportunities

have been created since inception of the programme, till December 2014, with 1644 & 80 new recruits in November and December respectively.

Labour count 9497

for month of December 2014

In most sites labour desks have been established

Employment Targets

81Slide82

Employment –New Monthly Recruits Per IA 2014IA

2012/13

Jan

‘14

Feb ‘14

Mar ‘14

Apr ‘14

May ‘14

Jun ‘14

Jul

‘14

Aug

‘14

Sept

‘14

Oct ‘14

Nov ‘14

Dec’ 14

IA Totals

EC DBSA 356600000463099872001584807411EC CDC 10880000000000001088EC IDT 8570082000000000939EC IDT w/s28015522617300005578451001526EC PW222

101

98

19

38

0

0

0

0

0

0

0

0

478

EC Mvula

741

0

1306

0

150

0

0

0

66

0

27

0

0

2290

CSIR

0

0

0

0

0

0

0

0

160

96

0

0

0

256

Kzn IDT

0

0

0

316

338

0

0

0

0

0

0

0

0

654

Kzn

Mhlz

0

0

0

0

0

0

0

352

0

0

0

0

0

352

Kzn CDC

0

0

0

0

442

0

0

0

0

220

0

0

0

662

Kzn Adopt

0

0

0

0

0

0

0

0

67

0

113

0

0

180

WC PW

759

0

0

0

0

0

0

0

0

0

0

9

0

768

82Slide83

Employment –New Monthly Recruits Per IA 2014IA

2012/13

Jan

‘14

Feb ‘14

Mar ‘14

Apr ‘14

May ‘14

Jun ‘14

Jul

‘14

Aug

‘14

Sept

‘14

Oct ‘14

Nov ‘14

Dec ‘14

IA Totals

NW IDT0410013800000000179NW DBSA00021162051010420270403MP DBSA0164017000000000181MP Mvula000000374000000374LP DBSA

0

0

12

0

0

38

55

73

0

0

0

23

0

201

LP Mvula

1573

0

0

0

0

0

0

0

0

0

0

0

0

1573

FS IDT

164

0

258

80

20

0

288

0

64

0

0

0

0

874

FS DBSA

0

0

0

0

0

0

306

547

274

59

346

0

0

1532

FS

PeD

ws

0

0

0

0

0

0

0

24

0

7

0

0

0

31

NC

PeD

0

0

113

0

0

79

0

0

0

0

0

0

0

192

NC DBSA

0

0

0

0

0

39

16

8

33

4

0

1

0

101

Totals/

mth

9250

461

2013

898

1188

156

1553

1004

2229

1364

537

1644

80

22 245

83Slide84

Job Opportunities 2012-1484Slide85

Job Opportunities Per Province85Slide86

Labour Count / IA 86Slide87

Equity Employment 2013/1487Slide88

Equity Employment 2013/14IMPLEMENTING AGENT 2013-December 2014 

YOUTH

WOMEN

DISABILITY

EC CDC

522

97

3

EC DBSA

2348

720

12

EC DPW

375

48

 

EC IDT

524

62

1EC MVULA 131325223EC IDT ws670362 NW IDT 8214 NW DBSA28432 WC DPW588331MP DBSA 9919 MP MVULA18647 FS IDT 524853FS DBSA938542FS DoE31  LP MVULA 417146 LP DBSA4911 NC PeD7914 KZN Adopt113  KZN IDT ws33178 KZN CDC ws22932 NC DBSA512     TOTAL975321084588Slide89

Education and Skills Development TargetTarget 1 learnership per site on learnership programme10% of the workforce to be recognised for prior learning

Achieved to date124 learnership on ASIDI project sites

89Slide90

Internships created per IA 2013IMPLEMENTING AGENTINTERNS

EC CDC49

EC IDT w/s

9

EC Public Works

30

WC Public Works

29

FS IDT

6

FS DoE w/s

1

Total

124

90Slide91