Eric Prebys June 15 2015 F ermilab A ccelerator S cience and T echnology E Prebys ProtonsgtIOTA Update 2 61515 New name The FAST Facility Fermilab Accelerator Science and Technology Facility would encompass what is presently in the New ID: 616367
Download Presentation The PPT/PDF document "Proton->IOTA Update" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Proton->IOTA Update
Eric Prebys
June
15,
2015Slide2
Fermilab Accelerator Science and Technology
E. Prebys, Protons->IOTA Update
2
6/15/15
New
name:
The
FAST Facility (Fermilab Accelerator Science and Technology Facility) would encompass what is presently in the New
Muon
Lab Building and its recently constructed
extension. It
will have:
The
IOTA ring (an experimental storage ring for electrons and protons)
An
electron injector (a 300-MeV SRF-based photo injector)
A
proton injector (a 2.5-MeV conventional ion source followed by an RFQ)
All
associated conventional,
rf
and
cryo
infrastructure, presently housed at the New
Muon
Lab and its extension
.Slide3
Planned Milestones E. Prebys, Protons->IOTA Update3
6/15/15
FY15
20 MeV e- commissioned
HE beam line 40%
IOTA parts 60%
FY16
50 MeV e- commissioned
150 MeV
CM2 to dump
IOTA installed
60%
FY17
IOTA installed
IOTA
e-
commissioned
IOTA research starts with
e-
Proton RFQ move
30%
FY18
Proton RFQ move
100%
Proton RFQ commissioned
FY19
IOTA research starts with
p+Slide4
Issues: lots of entropy at HINSThe major pieces still exist, but everything’s been disconnected since HINS last ran ~5 years ago.6/15/15
E. Prebys, Protons->IOTA Update
4Slide5
Entropy: cont’d6/15/15
E. Prebys, Protons->IOTA Update
5Slide6
General PlanStabilize Arealocks on cavesigns on equipment, messages to other groups: “not parts bin”Get RFQ working in current location (HINS cave at MDB)FY15:
Get ion source under vacuum and activate filament
FY16:
Establish 50kV beam from ION sourceResurrect 325MHz klystron, reconnect it, and establish 2.5 MeV Beam in situ
Establish proton beam at IOTAFY17: Move ion source, RFQ and girder to IOTA
Use new 325 MHz klystron (in storage)Use charging supply, modulator and transformer that were intended for the third ASTA
cryomodule
(at FAST)
6/15/15
E. Prebys, Protons->IOTA Update
6