/
Facilities  Development Process Facilities  Development Process

Facilities Development Process - PowerPoint Presentation

eatfuzzy
eatfuzzy . @eatfuzzy
Follow
343 views
Uploaded On 2020-07-03

Facilities Development Process - PPT Presentation

FDM Chapter 3 Fall 2016 Cheryl Simon NC Region Program Controls Design Engineer cherylsimondotwigov 7153655728 John VonRuden SW Region Program Controls Design Engineer johnvonrudendotwigov ID: 794401

project phase process design phase project design process plan schedule fdm chapter amp preliminary life management move deliverables cycle

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "Facilities Development Process" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Facilities Development Process(FDM Chapter 3)

Fall 2016

Slide2

Cheryl Simon, NC Region Program Controls Design Engineercheryl.simon@dot.wi.gov(715)-365-5728

John

VonRuden, SW Region Program Controls Design Engineer john.vonruden@dot.wi.gov(608) 789-5952

Presenters

2

Slide3

Hold all questions until the end.

Questions

3

Slide4

Facilities Development Process (FDM Chapter 3) has been rewritten to include uniform statewide definitions for the following:

Phases

Life Cycles MilestonesDeliverables

WHAT

4

Slide5

5

WHY

The need became evident as a result of work by two teams which included:

Slide6

Consistent application of the process statewide. Time needed to mobilize resources.

Scope changes.

Projects started on time.

Identified Problems

6

Slide7

Planning/Programming performance measures.PMP 2.5 application upgrade.

Guidance in FDM Chapter 3 outdated.

Other Considerations

7

Slide8

Revise process outline.

Provide a clear blue print of how we progress though the process.

Solution

8

First Step Update FDM Chapter 3

Slide9

9

Prototype - Concept

Slide10

10

Refined

- Process

Slide11

Phase Elements11

Phase Name

Correlates to work being done.

Slide12

Phase Elements12

Life Cycle

FIIPS accounting Life Cycle for the construction LET project.

Tracks the refinement of the construction estimate and schedule date.

Slide13

Phase Elements13

Milestone

Significant points identifying the start or end of a phase or event.

Slide14

Phase Elements14

Timeline

Chart lists some general timeline information

Slide15

Phase Elements15

Deliverables

Required to be completed prior to advancing to the next phase.

Scope, Schedule, Budget and Other Phase Deliverables

Slide16

Phase Elements16

Phase Activities

Task that may be occur during a phase.

FDM Chapter 3 attachment 1.2.

Slide17

Phase Elements17

Phase Activities

FDM Chapter 3 attachment 1.2.

Slide18

Phase Elements18

Change Management

Follow Regional Change Management Process.

Slide19

Phase Elements19

Performance Measures

FDM Chapter 3 attachment 1.1 page 2.

Lists Performance Measures that directly correlate to the Facilities Development Process.

Slide20

20

Slide21

21

Slide22

Program Development Phase22

Phase at the beginning of the process

Life Cycle: LC00

Scope: Program Level

Schedule: Program Let

Schedule

Budget

: Program Level Construction

Estimate

Slide23

Program Development Phase23

Other Phase Deliverables include:

Design ID Authorization

Highway Improvement TypeSigned State Municipal Financial Agreement (SMFA) for the design of projects on connecting highways

Slide24

Program Development Phase24

End of Phase

Move to LC10

Move to Project Management Plan Phase

Slide25

Project Management Plan Phase25

Life Cycle: LC10

Milestones: Project Start and Project Management Plan Approved

Scope: Project LevelSchedule: Control and Detail; Let Schedule

Budget: Construction Estimate and Design Delivery Budget

Slide26

Project Management Plan Phase26

Other Phase Deliverables include:

Purpose and Need

Scoping Intersection Control Evaluation (ICE)Safety Screening Analysis (SSA)

Risk Assessment

Slide27

Project Management Plan Phase27

The

Project Management Plan is approved once all required business areas concur.

The approved Project Management Plan sets baseline for performance measures and change management

.

End of Phase

Move to LC 11

Move to Project Resourcing Phase.

Slide28

Project Resourcing Phase28

Phase provides time in the delivery schedule to mobilize resources either in-house or consultant.

Life Cycle: LC 11

Milestones: Project Management Plan Approved and Begin Design

Scope, Schedule and Budget unchanged.

Slide29

Project Resourcing Phase29

Other Phase Deliverables include

:Assignments for resources

Executed consultant contracts (if required)

Risk Assessment

Slide30

Project Resourcing Phase30

End of Phase

Life cycle remains at LC11

Move to Preliminary Impact Review Phase

Slide31

Preliminary Impact Review Phase31

Life Cycle: LC11

Milestones: Begin Design and Preliminary Impact Review Complete

Scope, Control and Detail Schedule, and Let Schedule reviewed and verified

Schedule: Non-Let schedules

Budget: Construction Estimate and Non-Let Estimates

Slide32

Preliminary Impact Review Phase32

Other Phase Deliverables include:

Alternative Selection Intersection Control Evaluation (ICE)

Draft Preliminary Plan

Preliminary Structure Plan

Environmental, Utility, R/W Impacts

Railroad Project Submittal Package

Signed State Municipal Financial and Maintenance Agreements

Risk Assessment

Slide33

Preliminary Impact Review Phase33

End of Phase:

Move to LC12

Move to Design Study Phase.

Slide34

Design Study Phase34

Life Cycle: LC12

Milestones: Preliminary Impact Review Complete and Design Study Report Approved

Scope, Schedule and Budget verified.

Slide35

Design Study Phase35

Other Phase Deliverables include:

Preliminary Plan

Preliminary Structure Plan

Signed Environmental document

Signed Design Study Report

Preliminary Plat

Risk Assessment

Slide36

Design Study Phase36

End of Phase

Move to LC 15

Move to PS&E Phase

Slide37

PS&E Phase37

Life Cycle: LC15

Milestones: Design Study Report Approved and PS&E Complete

Scope, Schedule and Budget should typically remain unchanged.

Slide38

PS&E Phase38

Other Phase Deliverables include:

PS&E package

PS&E exceptionsPermits

Risk Assessment

Slide39

PS&E Phase39

End of Phase:

Move to LC 20

Move to Design Project Closeout Phase

Slide40

Design Project Closeout Phase40

Life Cycle: LC20

Milestones: PS&E Complete, Project Let and Project Award

Slide41

Design Project Closeout Phase41

Other Phase Deliverables include:

PS&E exceptions

Plan check revisions

Advertisement for bid

Addenda

Risk Assessment

Review bids

Slide42

Projects started on timeTime needed to mobilize resources

Scope changes

Consistent application of the process statewide

Direct Benefits

42

Slide43

A clear understanding of the expectations with flexibility for regional differences.Less stress on resources.Improved relations with internal and external partners.Overall improvement of performance measures not

directly correlated

to the Facilities Development Process. Indirect Benefits43

Slide44

FDM Chapter 3 updates Update conflicting guidanceRegional guidance to supplement the updated process

What's Next?

44

Slide45

Link to Facilities Development Process documents @http://wisconsindot.gov/Pages/doing-bus/eng-consultant/cnslt-rsrces/rdwy/training-fdm3.aspx

FDM

Chapter 3 Section 1 Process Overview (narrative) FDM Chapter 3 Attach 1.1 (deliverables & performance measures)FDM Chapter 3 Attach 1.2 (phase activities) FDM Chapter 3 Fall 2016 training webinar & slide show presentation

Resources

45

Slide46

Q&A46