2010 and beyond Plans amp Milestones 2010 A Year of Transition Phase 1 ends Phase 2 begins This is our last meeting in Phase 1 Seamless transition No major restructuring etc Adiabatic shift in emphasis needed ID: 1033241

baseline amp beam demonstration amp baseline demonstration beam design phase system tests components prototype accelerator planning work studies adi

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Nick Walker Marc Ross Akira Yamamoto" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

1. Nick WalkerMarc RossAkira Yamamoto2010 (and beyond)Plans & Milestones

2. 2010 – A Year of TransitionPhase 1 ends – Phase 2 beginsThis is our last meeting in Phase 1Seamless transitionNo major re-structuring etc.Adiabatic “shift in emphasis” neededBeginning plan for producing TDR (end 2012)Consolidation (results) of risk mitigating R&DCollider design work → updated cost estimateDocumentation!A good opportunity to take stock and review where we are

3. TD Phase Goals – A ReminderTDR deliverables:Results from Risk Mitigating R&DUpdated Reference DesignUpdated VALUE estimateProject Implementation PlanGeneral GoalsRisk Mitigating R&DMain Linac SCRF [gradient, cavity yield, mass-production and industrialisation]Beam Test Facilities [ATF/ATF2, CESRTA, TTF/FLASH, DAPHNE…]Sources…Accelerator Design & IntegrationIntegrated, robust and simplified designCost containment

4. Where do we stand?Published milestones in R&D PlanPay attention!Part of Workshop Charge: Review these milestones & goalsExpect status report as part of WG summariesPM are planning major update for Release 5Due June 2010Your input will be required

5. Collider Design Work (ADI)✔✔Impact of re-baseline delay requires schedule review

6. Collider Design Work (ADI)✔✔CC processImpact of re-baseline delay requires schedule review

7. Collider Design Work (ADI)✔✔CC processImpact of re-baseline delay requires schedule review

8. R&D: SCRF✔?CC processRequired: strategy and plans for producing an updated cryomodule cost (early 2012?)

9. R&D: SCRF HLRFMilestones for RDR Alternatives:Marx modulator development / demonstration 2010Demonstration of circulator-less distribution 2010system (with VTO)Klystron Cluster System (KCS)Initial high-power tests of WG components 2010EM modelling of components (VTO etc) 2010FMEA / operations study 2010Full-power tests of WG components 2012Distributed RF System (DRFS)Prototype of 700kW Mod. Anode Klystron 2010Prototype of Mod. Anode Modulator 2010Design for manufacture (cost!) 2012MAK/MAM lifetime demonstration 2012

10. R&D: SCRF HLRFMilestones for RDR Alternatives:Marx modulator development / demonstration 2010Demonstration of circulator-less distribution 2010system (with VTO)Klystron Cluster System (KCS)Initial high-power tests of WG components 2010EM modelling of components (VTO etc) 2010FMEA / operations study 2010Full-power tests of WG components 2012Distributed RF System (DRFS)Prototype of 700kW Mod. Anode Klystron 2010Prototype of Mod. Anode Modulator 2010Design for manufacture (cost!) 2012MAK/MAM lifetime demonstration 2012→ CC (re-baseline)

11. R&D: SCRF HLRFMilestones for RDR Alternatives:Marx modulator development / demonstration 2010Demonstration of circulator-less distribution 2010system (with VTO)Klystron Cluster System (KCS)Initial high-power tests of WG components 2010EM modelling of components (VTO etc) 2010FMEA / operations study 2010Full-power tests of WG components 2012Distributed RF System (DRFS)Prototype of 700kW Mod. Anode Klystron 2010Prototype of Mod. Anode Modulator 2010Design for manufacture (cost!) 2012MAK/MAM lifetime demonstration 2012→ CC (re-baseline)?

12. Accelerator Systems R&DElectron Source:Proof of principle system 2008 (?)Reliable 200 kV load-locked gun prototype 2009 (?)Prototype laser system 2010Generation of beam with ILC spec. 2010Reliable 350 kV load-locked gun prototype 2011 Required: plans for polarised cathode fundamental R&D

13. Accelerator Systems R&DPositron Source:SC Helical undulator prototype 2009 ✔Feasibility studies and design of a high-field 2009 (2010)flux concentrator Feasibility study and design of a lithium lens 2010 with possible beam tests Engineering design of rotating target system 2010with appropriate lifetime Feasibility studies and beam tests of 2010liquid Pb target Feasibility studies and beam tests of 2010a hybrid crystal target In addition: SB2009 parameters/specifications and associated ADI work → CC (re-baseline)

14. Accelerator Systems R&DDamping Ring – ATF:Demonstration of 2pm vertical emittance 2010Damping Ring - DAfNEFast kicker demonstrations 2010Damping Ring – CesrTA:Reconfiguration of machine 2008 ✔incl. instrumentation and test sections;First measurements of ecloud building up.Reduced emittance operation; 2009 ✔e-cloud build-up in wiggler chambersCharacterisation of e-cloud build-up and 2010instability thresholds as a function of lowvertical emittance (≤20 pm) Final recommendations on e+ DR configuration (including possible 3km ring) → CC (re-baseline)

15. Accelerator Systems R&DRTMLExperimental demonstration of the bunch 2011compressor RF phase stability, and beam- (FLASH)loading compensationResults of beam dynamics simulation, 2010?demonstrating the required emittancetuning techniquesFurther studies of single-stage compressor option for SB2009 (compression limits)

16. Accelerator Systems R&DBDS– ATF2:Demonstration of design beam size 2010Demonstration of the beam stability 2012Evaluation of performance of SC FD andpermanent magnet FD 2012BDSDemonstration of the required phase ?stability of the prototype crab cavity systemMany other ADI related studies listed in Appendix B

17. Accelerator Systems R&DSimulation:Answers to critical beam-dynamics questions arising during the TD Phase (engineering driven)Overall (simulated) demonstration of emittance preservation from the Damping Rings to the interaction pointModelling of halo generation, transport and collimationSoftware tools (simulation codes)Specific studies resulting from SB2009 studies to be defined → CC (re-baseline)

18. CFSFocus has been on ADI (SB2009) in 2009Schedule needs re-work for proposed CC (re-baseline)

19. Planning for the TDR201020112012Risk Mitigating R&DRe-Baseline (CC)AD&ISCRFCFSUpdate VALUE estimateDocument baselineWrite TDR report(s)More detail requiredDefinition of milestones & critical pathAD&I, SCRF and CFS are focus activities and need definition

20. TDR – what is it?Provides traceabilityReleased documentationAll relevant design documentation over next two years

21. Two Imminent ReportsTD Phase Interim ReportTo be published ~July 2010General status reportTerse!Upbeat publication (outreach)PhotosResults..TD Phase R&D Plan Release 5To be published in June 2010Resource tables update in May for FALC RGMore detailed planning for TD Phase 2Major update (re-write) expectedMain report body – PMsAppendix B sections – TAG leadersConsiderable amount of work which will require careful planning.

22. This WorkshopWhat’s expected from the WGReview of the R&D status (esp. R&D Plan milestones)How will R&D results factor into ILC baseline?And when?ADI activities – how mature are the current designsSpecial attention to SB2009 themesCatalogue outstanding decisionsWhat remains to be done for the TDR?Overall planning and milestone updatesR&D plan releaseWhat’s expected from the PMsBetter defined overall schedule and goals (2010+)Change control procedure (SB2009)Outline for Interim ReportSchedule/requirements for R&D Plan UpdateDetailed planning (action items) for next 6 months→ October GDE meeting (Geneva)Top-level planning towards TDR