Planning Commission Workshop March 22 2016 Jennifer Campos Senior Planner Evergreen Corridor Management Plan Roadway Maintenance P athway I mprovements Presentation Overview Evergreen Highway Corridor ID: 645207
Download Presentation The PPT/PDF document "Evergreen Highway Corridor Update" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Evergreen Highway
Corridor Update
Planning Commission Workshop
March
22,
2016
Jennifer Campos,
Senior PlannerSlide2
Evergreen Corridor Management Plan
Roadway Maintenance
P
athway
I
mprovements
Presentation Overview
Evergreen Highway Corridor
Update
-
2Slide3
Project context
Evergreen Highway Corridor
Update
- 3Slide4
Project purpose
Evergreen Highway Corridor Update
- 4
The purpose of the Evergreen Corridor Management Plan (CMP) is to provide
guidance, direction and documentation
for future decisions and actions
along
SE
Evergreen
HighwaySlide5
Scope
Evergreen Highway Corridor Update-
5
Traffic volumes
and speeds
Local and regional access
Roadway surface and maintenance
Pathway
design
Roadway
standards
Stormwater
requirements
Historic
and scenic significance
Street lighting and utilitiesSlide6
Process and inputs
Evergreen Highway Corridor
Update- 6
Evergreen Highway CMPSlide7
Concept-level designs
Recommended changes to city code and road design standards
F
unding and implementation strategies
Final plan
presented to City Council for adoption
Outcomes
Evergreen Highway Corridor
Update-
7Slide8
Project Timeline
Evergreen Highway Corridor Update-
8
MARCH
APRIL
MAY
JUNE
JULY
Develop draft plan
P
lan adoption
AUGUST
Open House
Internal draft review
Public draft review
Open House
Finalize planSlide9
Community Outreach
Evergreen Highway Corridor Update
- 9
Presentations at two neighborhood association meetings (100+ participants)
Online community survey (321 respondents)
Eight small group meetings (61 participants)
Ongoing email and website updates
Next step:
O
pen house on April 16Slide10
Community
Outreach Findings
Evergreen Highway Corridor Update- 10
Safety for all users (motorists, people walking, people cycling) is a top priority
Focus on a short-term solution for the roadway surface condition
Completion of the pathway is more important than extra amenities (such as lighting, historic markers, or undergrounding utilities)Slide11
Current Road Conditions and Status
The City has 1,810 lane miles of streets
185
total lane miles are “failed”
Rated as a Pavement Condition Index (PCI) from 0-100*
“Failed” is a PCI < 40 for
arterials
Average PCI of Evergreen Highway
Chelsea to SE 164
th
Ave. = 34
SE 164
th
Ave to City Limits =
46
*
PCI does not measure ride quality
Evergreen Highway Corridor Update-
11Slide12
Current Road Conditions and Status
Thin asphalt repairs
Pothole repairs
Milling of thin asphalt
Test treatment
Enhanced cape seal
Evergreen Highway Corridor Update-
12Slide13
2016 Pavement Work
Continued milling of asphalt
Asphalt repairs
Concrete grinding (new)
Enhanced cape seal
Re-striping and reflective markers
Evergreen Highway Corridor Update-
13Slide14
Treatment Options and Cost
Complete
Reconstruction
Current Regulations
$515 /SY
2017 Regulations
$355 /SY
Evergreen Highway Corridor Update-
14Slide15
Treatment Options and Cost
Reconstruction of Roadway
Estimated total cost: $27.0M - $39.5M
Includes entire corridor from Chelsea to City limits (192
nd
Ave)
Cost is for replacement with asphalt
Assumes that road width remains the same
Phased construction
Pathway built as a separate project
Evergreen Highway Corridor Update-
15Slide16
Treatment Options and Cost
Develop a detailed pavement rehabilitation plan for the corridor
Interim measures to improve ride quality
Continue enhanced cape seal along corridor
Areas of asphalt overlay
Concrete slab repairs
Evergreen Highway Corridor Update-
16Slide17
Update on pathway improvements
Evergreen Highway Corridor Update -
17Evergreen Highway
Pathway SegmentsSlide18
Update on pathway improvements
Evergreen Highway Corridor Update-
18Segment
Begins/EndsLength
Status
Funding Gap
A
Chelsea to Image
1.1
Design in
progress.
$1,275,000
B
Image to 100th
0.4
Design
75% complete
$900,000
C
100th to Ellsworth
0.4
Complete (2015)
--
D
Ellsworth to Columbia Springs
0.7
Complete (2001)
--
E
Columbia Springs to 164th
2.3
Community fundraising effort enabled preliminary design work
to be completed by
BergerABAM
To be determined
F
164th to City Limits
1.8
Conceptual design
complete as part of overall east segment study
$3,000,000+
Row height = relative length of segmentSlide19
Evergreen Highway Corridor
Update- 19
SE 100th Court to SE Ellsworth Road
Pervious ConcreteSlide20
Evergreen Highway Corridor
Update- 20
SE 100th Court to SE Ellsworth Road
Walls and Pervious ConcreteSlide21
Evergreen Highway Corridor
Update- 21
SE 100th Court to SE Ellsworth Road
Pervious PaversSlide22
Questions and Discussion
Jennifer Campos, Senior Planner, City of Vancouver
jennifer.campos@cityofvancouver.us
(360)
487-7728
www.cityofvancouver.us/
evergreenSlide23
Evergreen Highway Corridor
Update- 23
Evergreen Trail – 100th Ct. to Ellsworth