Adopting a Raccoon Project Management for RIMI Adopting a Raccoon Project Management for RIMI

Adopting a Raccoon Project Management for RIMI - PowerPoint Presentation

greyergy
greyergy . @greyergy
Follow
343 views
Uploaded On 2020-08-05

Adopting a Raccoon Project Management for RIMI - PPT Presentation

Agenda Project Management Stages Branding TeamResources Steps in RIMI Project Summary Project conception and initiation Project definition and planning Project launch or execution Project performance and control ID: 799189

rim days project estimate days rim estimate project step pilot daysit plan based external training daysexternal day vendor governance

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "Adopting a Raccoon Project Management fo..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Adopting a Raccoon

Project Management for RIMI

Slide2

Agenda

Project Management Stages

Branding

Team/Resources

Steps in RIMI Project

Summary

Slide3

Project conception and initiation

Project definition and planning

Project launch or execution

Project performance and control

Project close

Project Management Stages

Slide4

Branding

Slide5

Email

Face to Face

Newsletter

Departmental Meetings

Posters

Communication

Slide6

Keep it Small

Keep it Simple

Keep it Fun

Change is HARD

Slide7

RIM

CRM

EDRMS

Reserve

IT

PM ECM

BA DEV ReserveExternal Services Consultants EDRMS

Software Development

ECM

*Expected Hard Limit of 220 Days/Year/Person

Project Team / Resources

Slide8

Step 1 - Project Governance

Step 2 - Corporate Policies

Step 3 - Enterprise Adoption Plan

Step 4 - Plan/Strategy

Step 5 - Records Foundation

Step 6 - RIM Administration

Step 7 - Business Procedures Step 8 - Repository Governance Step 9 - Declaration

Step 10 - Validation

Step 11 - End User Training

Step 12 - Pilot

Steps in RIMI Project

Slide9

Project Phases

Project Governance

Weekly Team Meetings (estimate 40-60 days depending upon length of project)

RIM – XX Days

IT – XX DaysCorporate PoliciesMake Decisions, Draft Policy, Get it Approved (estimate based upon how quickly your organization processes)

RIM – XX DaysIT – XX Days

Educate on/Disseminate the Policy (estimate 7-10 days)RIM – X DaysIT – X Days

Slide10

Enterprise Adoption Plan

Execute Enterprise Adoption Plan (plan for no less than 14 days)

RIM – XX Days

IT – XX Days

Plan and StrategyProject Functional Specs (Bi-Weekly) (estimate based upon length of project)RIM – XX DaysIT – XX Days

External – X DayProject Planning + GANTT update (work with your PM to get these estimates)

RIM – XX DaysIT – XX DaysExternal – XX Day

Slide11

Records Foundation

Make File Plan EDRM Ready (Estimate based upon condition of existing plan)

RIM – XX Days

External – SS Day

File Server Legacy Migration (Estimate 2-5 days)RIM – XX Days

IT – XX DaysBuild Cost Schedule Index (Estimate total of 10-20 days based upon organizational comfort)RIM – XX Days

IT – XX DaysExternal – XX DaysPhysical Records Configuration (if these are included)RIM – XX DaysExternal – X Day

Slide12

RIM Administration

Vendor Product Training (Estimate 3-5 days depending upon vendor)

RIM – XX Days

IT – XX Days

External – XX Days

3rd Party RIM Admin Training (Estimate 3-5 days depending upon vendor)RIM – XX Days

IT – XX DaysExternal – XX DaysRIM Admin Self-Training (estimate 7-10 days)RIM – XX DaysExternal – XX DayTrain Back-up RIM Admin (estimate 5-10 days)

RIM – XX Days

Slide13

Business Procedures

Define/Conduct SOP’s (Estimate 5-15 days depending upon level of existing documentation)

RIM – XX Days

IT – XX Days

External – XX Days

Repository Governance

Metadata Mapping (Pilot Group) (Pilot size will impact estimates 2-5 days)RIM – XX DaysIT – XX DayConfigure SharePoint (Pilot Group)RIM – XX DaysIT – XX Day

Repository Governance Plan Oversight Committee Meetings (estimate dependent upon frequency and productivity of committee meetings)

RIM – XX Days

IT XX Days

Slide14

Declaration

Build, Test, Deliver RBR Rules (Pilot) (Estimate based upon vendor)

RIM –XX Days

Install and Configure Email Integration (Pilot) (Estimate based upon vendor)

RIM –XX DaysIT – XX DayValidationConfirm System Performance Validations (36) (Estimate based upon number of SPV’s and efficiency of IT 7-15 days)

RIM – XX DaysIT – XX Days

External – XX Days

Slide15

End User Training (All estimates should be based upon available training resources –

WaterOne

has a dedicated education specialist in HR)

Develop Course Content (10-15 days)

RIM – XX DaysIT – XX DaysExternal – XX DaysCourse Materials

Configure Training Facility and System (10-15 Days)RIM – XX DaysIT – XX Days

External – 10 DaysInstall and Configure Email Integration (Pilot) (3-5 Days)IT – XX Days

Slide16

Pilot

Conduct 30-day Pilot (Estimate is dependent upon size of pilot)

RIM – X Days

IT – XX Days

External – XX Days

Slide17

Current Projected

RIM – 212 days

CRM – 69 Days

EDRM – 143 Days

IT – 228 days

PM – 75 DaysECM – 110 Days

BA – 33 Days

Dev – 10 Days

External – 91 days

Users for Pilot – 16 days

Summary