Building Builtup Area 13800 m 2 15 less material usage Benefits of using Steel Tubes 8 saving in total project cost Particulars PEB using Beams amp Plates PEB using APL Apollo Steel Tubes ID: 926492

steel cost case study cost steel study case quantity material tubes

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Case Study VI – G+14 Office" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Case Study

VI

G+14 Office

Building

Built-up Area 13800 m2

15% less material usage

Benefits of using Steel Tubes

8% saving in total project cost

ParticularsPEB – using Beams & PlatesPEB – using APL Apollo Steel Tubes Steel consumption (Ton)853739Raw Material (Rs/kg)6570Conversion Cost (Rs/kg)1010Transportation (Rs/kg)1.21.5Erection (Rs/kg)5.05.0Total cost (Rs/kg)81.286.5Project Cost (Rs Cr)6.926.39

Composite Design used, Concrete quantity are not included in Case study