January 23 2017 Resettlement Threshold Background In November ERCOT staff detected a material increase in DAM MakeWhole payments subsequent to the implementation of NPRR 617 Energy Offer Flexibility on June 22 2016 ID: 653054

dam resettlement threshold ercot resettlement dam ercot threshold data issue statement rtm prices day errors total due review settlement market operating section

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Resettlement Threshold CSWG" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Resettlement Threshold

CSWG

January

23,

2017Slide2

Resettlement Threshold

Background

In November ERCOT staff detected a material increase in DAM Make-Whole payments subsequent to the implementation of NPRR 617, Energy Offer Flexibility, on June 22, 2016.It was determined that the increase resulted from a mismatch between Startup and Minimum Energy Costs used by the Day-Ahead Market clearing engine and those used for Day-Ahead Make-Whole payments.

2Slide3

Upon

discovering the issue, ERCOT analyzed all impacted Operating Days and determined that no days met the 2% threshold for Resettlement of the Day-Ahead Market per Protocol Section 9.2.5(2). A Market Notice was issued to this

effect and the issue was reviewed at the December 1, 2016 TAC.TAC requested review of appropriateness of the 2% threshold value by WMS and COPS.3

Resettlement ThresholdSlide4

Applicable Protocol language (DAM):

4

Resettlement Threshold

9.2.5 DAM Resettlement

Statement

ERCOT

shall issue DAM Resettlement Statements for a given DAM if the ERCOT Board finds that the DAM Locational Marginal Prices (LMPs), Market Clearing Prices for Capacity (MCPCs), or Settlement Point Prices are significantly affected by a software or data error under Section 4.5.3, Communicating DAM Results. ERCOT shall also produce DAM Resettlement Statements required by resolution of Settlement and Billing disputes.

ERCOT

shall issue a DAM Resettlement Statement for a given DAM due to error in data other than prices when the total of all errors in data other than prices results in an impact greater than

2% of the total payments due to ERCOT for the DAM, excluding bilateral transactions

. ERCOT shall issue DAM Resettlement Statements as soon as possible to correct the errors. ERCOT shall review this percentage on an annual basis. Upon the review, ERCOT may make a recommendation to revise this percentage under Section 21, Revision Request Process

.

ERCOT

shall issue a DAM Resettlement Statement for an Operating Day if an error in the DAM Settlement, which does not otherwise meet the Protocol requirements for resettlement as specified in paragraphs (1) and (2) above, will prevent ERCOT from achieving revenue neutrality

.

(

4) A

DAM Resettlement Statement must reflect differences to financial records generated on the previous Settlement Statement for the given DAM. Slide5

Applicable Protocol language (RTM):

5

Resettlement Threshold

9.5.6 RTM Resettlement

Statement

ERCOT

shall issue a RTM Resettlement Statement using corrected Settlement data due to resolution of disputes and correction of data errors. Any resettlement occurring after an RTM True-Up Statement has been issued must meet the same Interval Data Recorder (IDR) Meter Data Threshold requirements defined in Section 9.5.8, RTM True-Up Statement, and is subject to the same limitations for filing a dispute. Despite the preceding sentence, the ERCOT Board may, in its discretion, direct ERCOT to run a resettlement of any Operating Day, at any time, to address unusual circumstances

.

(

2) ERCOT

shall issue a RTM Resettlement Statement for a given Operating Day due to data error in data other than prices when the total of all errors in data other than prices results in an impact greater than

2% of the total payments due to ERCOT for the RTM for the Operating Day, excluding bilateral transactions.

ERCOT shall issue RTM Resettlement Statements as soon as possible to correct the errors. ERCOT shall review this percentage on an annual basis. Upon the review, ERCOT may make a recommendation to revise this percentage under Section 21, Revision Request Process.Slide6

DAM total charges and threshold values

6

Resettlement ThresholdSlide7

Size of 2016 DAM Make-Whole issue relative to DAM charges

Issue was in the system for 146 days, of which 57 had a data error.

Total overpayments were ~.20% of DAM charges.7Resettlement ThresholdSlide8

Please note that ERCOT staff have drafted an NPRR that removes the “data error” classification;

ie

errors would be categorized as either due to prices or all other errors. All other things equal, the resettlement frequency for RTM may be expected to be less than DAM because of Final and True-Up settlements.ERCOT believes that a DAM threshold based on aggregate market activity is appropriate. 8