Download Presentation The PPT/PDF document "Wastewater treatment Petrit tare" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Wastewater treatment
Petrit tareGeneral director of UKKO JSc
conforming to EU Wastewater treatment Directive
case study of Korca City, AlbaniaSlide2
Status of WWTP in Albania
Wastewater treatment in all parts of Albania has improved during the last 10
years.
The percentage of the population connected to wastewater treatment in Albania has increased over the last ten years. Latest
values of population connected to wastewater treatment in Albania is still relatively low compared to Eastern, Central and Northern Europe. 10 %Danube Water ConferenceSlide3
WWTP in Albania
Danube Water ConferenceSlide4
Who we are?
Status: Regional Operation Joint Stock CompanyEmployees
: 93Operations Locations: 1 City and 7 Communes in the rural areas
Services: Drinking water distribution and 24 hrs services of water supplyWaste water Collection and treatmentInfrastructure
: Water Network - 127 kmSewer Network - 92 km1 Centralized Wastewater Treatment PlantSolar panel system
Danube
Water
ConferenceSlide5
History
Water supply investments
24’000’000 EUR
Sewer Investments
25’000’000 EUR
Waste Water Treatment Plant investment
8’300’000 EUR
Danube Water ConferenceSlide6
Water improvements
Reduction of health risks
- Development of
Turani Wellfield- Sealing first Aquifer of Well against Surface Water intrusion
Hygienically safe water- Distribution Network Replacement and Rehabilitation- New House Connection- New Transmission Mains
24
hours water supply
- Replacement
of
Turani
Pumping
Station
Provision
of Adequate Storage Volume
Sustainability
of
Project
-
Central Billing Office
- New Tariff Structure
-
Implementation of an EDP based Billing System
- Public Awareness Campaigns
Danube Water ConferenceSlide7
New Institutional Framework
High electricity Consumption
Low services tariffs
No finances from Government
High electricity tariffs
Low treatment efficiency
High ware of the equipment
More stringent effluent standards
Danube Water ConferenceSlide8
"Sewerage and Storm Water Disposal Korca III & IV"
Objective of the project: Rehabilitation of the existing sewer infrastructureResults of the project:
Waste Water Treatment Plant for a perspective year 2030
Protection of public health Environmental ProtectionComply with 271/91/EECSlide9
Scope of the works (1)
Primary Treatment: New Structure (pumping station)
Fine ScreensSand Separator
Secondary Treatment:
2 stages of aerated ponds (30+18 surface aerators)1 stage polishing pondProcess Control:
Complete automation
New SCADA System
Automated sampling system
Danube Water ConferenceSlide10
Overview of the WWTP of Korca City
Danube Water Conference
Advantages of the selected project:
Secondary Treatment of all discharges from agglomerations of > 2000
p.e. for a not sensitive area (WWTP of the City of Korca designed for 85.000 PE);
Easy
for management in terms of effluent quality and
operation;
Successfully
applied in high density population
areas
(Municipality Area);
Low cost of maintenance
Fully automatedSlide11
Where we are now?
Treatment capacity: 500 l/sEnergy Consumed (av, year 2015): 125.450 Kw/m Energy Recovery from the Solar panel: 116.397 Kw/m Efficiency: 92.7 %
Danube Water ConferenceSlide12
Performance of the plant
Danube Water ConferenceSlide13
What is left?
Abandonment of open wastewater discharge in the rural areas Construction of new small Waste Water Treatment Plants for the rural areas
Improvement of rainwater treatment (e.g. infiltration of rainwater as far as possible to close natural water cycle)
Implement Directive 91/271/EEC improving the sludge management and disposalDanube Water ConferenceSlide14
Conclusions:
Channeling the investments properlyRigid implementation standardsForecasted data standards
Operation challenge
Guaranteed success / self sustainabilityDanube Water ConferenceSlide15
Water is life
but
Wastewater is DIGNITY!
Danube Water Conference