Relocation and shielding activities Relocation and shielding activities

Relocation and shielding activities - PowerPoint Presentation

numeroenergy
numeroenergy . @numeroenergy
Follow
342 views
Uploaded On 2020-08-07

Relocation and shielding activities - PPT Presentation

2011 TS and Xmas break 20112012 R2E project meeting 21 rst July 2011 A L Perrot Activities performedforeseen during the 2011 TS Already done Survey scans in Point 5 bypass Pt1UL146 ID: 801507

point installation activities relocation installation point relocation activities 2011 consideration bypass points rack pipes break cables shielding discussion civil

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "Relocation and shielding activities" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Relocation and shielding activities

2011 TS and Xmas break 2011-2012

R2E project meeting

,

21

rst

July

2011

A. L. Perrot

Slide2

Activities performed/foreseen during the 2011 TS

Already done

Survey: scans in Point 5 bypass, Pt1(UL14/6)Point 8: EL cabling activities, empty racks installation for IT,

preparatory work for the remote reset rack relocation (EL and IT)ForeseenSurvey: Scans of

Pt 7 (TZ76), Pt 8 (UJ84/UL84/US85/UL86/UJ86) Pt 4 (UJ44/UL44/US45/UL46/UJ46)

Point 1

cable displacement in view of RB shielding installation

reinforce the floor in the RB (civil engineering team)

Points 5/7

CE visits with firm to prepare future activities (wall dismantling in TZ76, drilling activities in UJ56, bypass)

Point 8

pipes installation in view of fibers installation

ventilation control cabinet relocation from UJ87 to UA87? to be discussed with CV

functionality

test of new cables for QURCB by

cryo

team (under progress)

Slide3

Activities foreseen for the Christmas break 2011-2012

Point 1

fire detection relocation to ULs shielding installation in RBs/UJs

preparatory work by EL (cable trays in the ULs- except those for water cooled cables)Point 5 fire detection displacement of the pipes in the by-pass, start pipes installation between RR and UJ -> under consideration; discussion with GS/ASE and integration in September

GGPSO installation in bypass Civil engineering: drilling the 5 or 7 holes in the separating wall (‘mur

tympan

’)

Point 8

Cryogenics:

- QURCB relocation: under consideration (decision at the end of the new cables tests)

- QURA relocation: under consideration (seems feasible; to be confirmed during Xmas break)

- EYQ01 rack relocation (24VDC distribution rack)

All points

Floor reference points to be installed -> under consideration; discussion with integration and survey in September