/
SST Source & Front  End Overview for IRR SST Source & Front  End Overview for IRR

SST Source & Front End Overview for IRR - PowerPoint Presentation

olivia-moreira
olivia-moreira . @olivia-moreira
Follow
350 views
Uploaded On 2018-09-26

SST Source & Front End Overview for IRR - PPT Presentation

Gregory Fries NSLSII Accelerator Division Project Engineer SST ID amp FE IRR November 8 2017 Outline Scope Machine Status amp Operating Schedule Source amp Straight Layout ID Refurbishment ID: 680409

front amp commissioning safety amp front safety commissioning beam sst shutters photon radiation device nsls straight installed complete shutter u42 installation shutdown

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "SST Source & Front End Overview for..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

SST Source & Front End Overview for IRR

Gregory Fries, NSLS-II Accelerator Division Project EngineerSST ID & FE IRRNovember 8, 2017Slide2

Outline

ScopeMachine Status & Operating ScheduleSource & Straight LayoutID RefurbishmentSource & Straight Installation & ReadinessFront End (FE) LayoutFront End

Development,

Installation & Readiness

Radiation Safety

Source & FE Commissioning Plan

ConclusionSlide3

Scope

SST

(7-ID) Source

One U42 undulator (refurbished)

One EPU60 (refurbished

)

Straight Section

EPU vacuum chamber

Canting Magnets (permanent magnet)

RF BPMs

SST

Front End

One canted insertion device (ID) front

end

X-BPMs were removed from the scope due to cost

The photon & safety shutters will remain locked out during commissioning and do not yet require wiring into PPS & EPSSlide4

Machine Status & Shutdown Schedule

Installation, testing & commissioning

dependent upon operating schedule

NSLS-Il beamline operations in process

Three machine shutdowns per year (4-5 weeks each)

Dec/Jan

April/May

August

Typically a

two-day

maintenance period every

third

week

& a studies period every week during

operations

Minor

installation & testing during maintenance days

Installation completed

during

Aug ‘17

shutdown

Commissioning scheduled for

Nov

‘17Slide5

Operating Schedule

Shifts for

SST ID & FE

CommissioningSlide6

SST ID & Straight Layout

Courtesy of B. Kosciuk

Beam

U42 Undulator

EPU60

Canting Magnet (3x)

RF BPMs

EPU chamberSlide7

U42 Undulator Refurbishment

Previously used device from ESRF

Specifications

1.6m long, 42mm period

0.79T nom.

p

eak field, 2.9kW nom.

m

ax power

A new control system

required

to meet NSLS-II

standards

New motor, drivers, gearbox, encoders & limit switchesNew manufactured parts for mechanismKill switches & home switches added

Correction coils addedE-stops & beacons addedMagnetic measurements performedSlide8

EPU60 Refurbishment

Previously used device

from SRC Wisconsin

Specifications

0.89m

long,

60mm

period

N

om

. peak

field – V: ~0.79T, H: ~0.45T

Nom. max

power – LH: 1.4kW, LV: 0.51kW, C: 0.74kWA new control system required to meet NSLS-II standardsA new plinth required

to bring EPU to the proper beam heightNew limits switchesKill switches

addedNew motorE-stops & beacons addedMagnetic measurements performedSlide9

Straight Section

EPU vacuum chamber procured from FMB

Berlin

Received in Nov. ’16

Leak checked & pre-surveyed prior to installation

S

tandard RF

BPM

buttons, SiO2 cables, & electronics

Canting

magnets

procured

from

VacuumschmelzePermanent magnets; no power supplies or water coolingMeasured & shimmed by ID groupSlide10

ID & Straight Section Installation

Dec/Jan ‘16 Shutdown

Installed

EPU vacuum chamber & RF BPMs

Baked

& surveyed straight

section

April/May

17 Shutdown

Installed U42 into SR tunnel

Installed U42 electronics rack & cables

Locked

o

ut

U42

(full open gap) until IRR

approval

Aug ‘17

Shutdown

Installed

EPU60

into SR tunnelInstalled EPU60 electronics rack & cablesInstalled canting magnets (adjusted lattice upon machine startup)Final survey of SST straight, IDs, & canting magnetsTesting controls In-situ

Locked U42 & EPU60 (full open gap) until IRR approvalSlide11

SST ID Straight

Actions

Specifications defined.

Design complete.

Design reviews completed and all actions resolved.

Devices under configuration management.

Magnetic fields measured.

Mechanical travel tested.

Water flow measured.

N/A

EPS tested.

Travelers developed and approved.

Travelers completed.

Note that there is no cooling water to

IDsSlide12

Safety Features of NSLS-II Insertion Devices

Various safety features have been implemented for all IDs:Brakes in motorsBrakes are on when there is no powerSelf-locking gearsGap will not close by attractive force onlyPilot lamp during gap/phase motionWarns people in the vicinity of the device that it is in motionLexan cover for magnetic gaps and external pinch points

Covers from both inner and outer side of a device.

EPS Switch

M

echanical

switch on the

ID

independent from control system for “gap open” status is integrated into EPS

LOTO

procedures during maintenance

Written procedure for each type of the device for lock-out and tag-outSlide13

SST Front End Layout

Slow Gate Valve

Fixed Mask

Collimator 1

X-Y Slits

Collimator 2

Fast Gate

V

alve

Ratchet Wall Collimator

X-BPMs (on hold)

Safety Shutters

BM Photon Shutter

Beam

Courtesy of C. Amundsen

Flag

Photon ShutterSlide14

Front End Development

Most components are identical to previous ID front ends

First canted beamline with two

undulators

Synchrotron fans overlap each other at fixed mask

Original fixed mask has a center web between the two apertures

Required new fixed mask design

FDR for new fixed mask occurred in Oct. ’16

New design is more adaptable, generic, & easier to manufacture

A prototype was produced to validate the machining process

ANSYS analysis & weld testing

were performed

Minor upgrade to slit blade design

Better thermal transfer & easier assembly

Front end ray tracing approved & releasedSlide15

Radiation Safety & Top-Off

Radiation safety components:

Exit absorber

Fixed mask

Burn thru flanges #1 & #2

Collimators #1 & #2

Safety shutters #1 & #2

Ratchet wall collimator

Top-Off components:

Exit Absorber

Fixed mask

Collimator #2

Credited controls include all shielding & PPS components

Removal

or modification of any device under configuration control r

equires an approved PS safety system work permit Slide16

Front End Installation

Dec/Jan ‘16 Shutdown

Installed ratchet wall collimator & safety shutters

Installed front end stand assemblies

Pulled cables

April/May ‘17 Shutdown

Installed exit pipe & bending magnet photon shutter

Installed remaining front end components

Terminated

cables

Plumbed

DI water & compressed

air

Aug ’17 Shutdown

Tied-in front ends into EPS & PPSBaked & final surveyed front endFinal

integrated testing & labelingLocked out shutters until IRR approvalSlide17

SST Front End

Actions

Ray

tracings complete.

Design

drawings complete

.

Vacuum system complete.

Final survey

complete

.

Devices under configuration management.

Integrated testing complete.

Water flow measured.

Travelers complete.

Top-off analysis complete.

EPS verification.

PPS verification.Slide18

Commissioning Plan

Commissioning scheduled for

Nov

. ‘17

Commissioning

studies time

has been reserved

Commissioning effort will include staff from Operations, Physics, Insertion Device, Front End, and Diag. groups

Software controls & tools already developed and verified during NSLS-II beamline commissioning

Procedures released for ID & FE commissioning sequence and radiation survey plan

FE

similar

design at NSLS-II Project, ABBIX, &

NEXTIDs similar to other EPUs at NSLS-IISlide19

Insertion Device Commissioning

Beam current

below 2 mA

Verify orbit and characterize/correct lattice

Reduce ID

gap of one device

Generate orbit correction feed-forward (lookup) table

Inject with ID gap closed, improve injection

efficiency

General radiation

survey

Repeat for second ID (with first ID gap open)

Authorization

 proceed to FE commissioningSlide20

Front End Commissioning

Photon shutter & safety shutters remain locked out

Beam current

below 2 mA

Verify orbit and characterize/correct

lattice

Verify active interlock functionality

General radiation surveys

Align the photon beam using flag

Record slit positions with respect to beam center

Condition vacuum

Radiation

survey (fault study

)Hold point – before increasing currentSlide21

Beam Current Increase Plan

Obtain authorization to increase current to 120 mA Photon shutter & safety shutters remain locked outEvaluate and record current machine stateGradually increase current

Verify

active interlock system

being engaged

Monitor and verify orbit, tunes, lattice, vacuum, temperature

Hold Point – Radiation

survey

Phase 1 (slits open

)

Phase 2 (slits closed)

Phase 3 (fault studies)Beam conditioningRepeat to

allowable currentSlide22

Conclusion

Refurbished IDs have been brought up to NSLS-II standards

SST insertion devices & front

end installed & tested

Radiation components under configuration control

Assembly drawings, ray tracings, procedures, & travelers are available

Photon shutter & safety shutters are locked in the down

position

U42 & EPU60 IDs are locked out with the gaps fully open

SST IDs & front

end

are

ready for commissioningNo self-identified pre-starts

Commissioning experience & prepared commissioning procedures from previous IDs & front endsSlide23

Back-up SlidesSlide24

Front End Details

A front end delivers the photon beam to the beamline while controlling the sizes of both the synchrotron and bremsstrahlung radiation fans.

The

fixed mask shadows the vacuum chambers of downstream

collimators

and safety shutters for beam deviations controlled by active

interlock.

Lead

collimators trim

the Bremsstrahlung fan exiting to beamlines.

Photon shutter is used to stop the photon beam in order to protect the uncooled safety shutters.

The safety shutters block the bremsstrahlung radiation from exiting through the

ratchet wall collimator

chamber opening.The photon shutter & safety shutters are locked out. (Centrally controlled LOTO)SST is similar

design to NSLS-II Project, ABBIX, & NEXT front ends