/
Crab Cavity Cryostat Fabrication and Challenges Crab Cavity Cryostat Fabrication and Challenges

Crab Cavity Cryostat Fabrication and Challenges - PowerPoint Presentation

quinn
quinn . @quinn
Follow
344 views
Uploaded On 2022-05-18

Crab Cavity Cryostat Fabrication and Challenges - PPT Presentation

Tom Peterson FNAL FNALLHC Crab Cavity Engineering Meeting 14 Dec 2012 LHC Crab Cavity Cryostat 14 Dec 2012 Crab cavity cryostat discussion Fabrication of the different types of cryostat and their advantage and disadvantages should be reviewed ID: 911891

cryostat cavity pressure crab cavity cryostat crab pressure dec lhc vacuum bar design vessel helium 2012 heat thermal pipe

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Crab Cavity Cryostat Fabrication and Cha..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Crab Cavity Cryostat Fabrication and Challenges

Tom Peterson (FNAL)

FNAL-LHC Crab Cavity Engineering Meeting

14 Dec 2012

Slide2

LHC Crab Cavity Cryostat, 14 Dec 2012Crab cavity cryostat discussion

Fabrication of the different types of cryostat and their advantage and disadvantages should be reviewed.

Challenges in the design choice, fabrication steps, integration along with feasibility of a two cavity cryostat within the specified scheduled should be reviewed and mitigation should be discussed.

2

Slide3

LHC Crab Cavity Cryostat, 14 Dec 2012Final crab cavity system requirements

Definition of requirements is still in progress

Elements of these requirements include:

Interfaces to the LHC accelerator system, cryogenic system, and tunnel infrastructure

Thermal conditions, cavity temperature, intercept temperatures, heat loads

Cavity arrangement, supporting structure and possibility for alignment, beam-beam spacing and allowance for two beams, how many cavities per cryostat?

2

Constraints from vertical and horizontal crabbing schemes RF coupler and HOM/LOM configurations and constraints Tuner configurations and constraints Instrumentation requirements Cryostat, piping, and helium vessel safety, code compliance requirements from final design.

3

Slide4

LHC Crab Cavity Cryostat, 14 Dec 2012Given the final system requirements above, how may the prototype differ from the final design?

Cavity support structure, same as final design?

YES

Arrangement of multiple cavities. Same total number of cavities?

NO

Provisions in the prototype for one beam only?

PERHAPS

Cryostat vacuum vessel differences

SIGNIFICANTRF couplers and HOM/LOM configuration and orientation through the cryostat SIMILAR to final design Special instrumentation not in the final cryostat Cryogenic connections, interfaces to infrastructure may differ YES, but not yet defined

4

Slide5

LHC Crab Cavity Cryostat, 14 Dec 2012Peak warm pressure

Compressor suction set pressure

1.2 bar (to avoid subatmospheric excursions)

Control margin

+/- 0.2 bar

Relief set pressure margin

+ 0.3 bar above control excursions (a judgment here, would like 0.5 bar)

Suction relief set pressure

1.7 bar (from 1.2 + 0.2 + 0.3 bar above)Pressure drop from far helium vessel to relief + 0.1 bar (needs to be determined for specific system, but probably low for the low flow in the warm situations) Peak warm pressure 1.8 bar (note that 0.5 bar set pressure margin, which would be better ==> 2.0 bar peak warm pressure)

Conclusion: 2.0 bar warm MAWP is a practical lower limit

ILC presentation – Tom Peterson

5

Slide6

LHC Crab Cavity Cryostat, 14 Dec 2012Cold peak pressures - 1

Loss of vacuum to air

Safety Aspects for the LHe Cryostats and LHe Containers,

” by W. Lehman and G. Zahn, ICEC7, London, 1978 “

3.8 W/sq.cm. for an uninsulated tank of a bath cryostat

0.6 W/sq.cm. for the superinsulated tank of a bath cryostat”“Loss of cavity vacuum experiment at CEBAF,” by M. Wiseman, et. al., 1993 CEC, Advances Vol. 39A, pg 997. Maximum sustained heat flux of 2.0 W/sq.cm. LEP tests and others have given comparable (2.0 to 3.8 W/sq.cm.) or lower heat fluxes Film boiling of helium with 60 K surface is about 2.5 W/sq.cm.

ILC presentation – Tom Peterson

6

Slide7

LHC Crab Cavity Cryostat, 14 Dec 2012Cold peak pressures - 2

Input parameters

Heat flux as limited by

Rate of air inleak

Surface heat transfer Total surface area involved

Can be limited by vacuum breaks, fast valves

Initial conditions

Note that 4.5 K just after filling (as opposed to 2 K when the large, low pressure volume acts as a buffer) is the worst case!

Pipe diameters out to the helium vent Overall distances and pipe lengths out to the helium vent A finer degree of segmentation can reduce pipe diameter requirements ILC presentation – Tom Peterson

7

Slide8

LHC Crab Cavity Cryostat, 14 Dec 2012Cold peak pressures - 3Relief pressure will be suction relief set pressure (for example, 1.7 bar)

Heat flux of 10

s of KW to liquid helium

Mass flows of many kg/sec Pressure drops to vent may result in peak pressures of 2.5 bar to 4 bar locally Maintaining a low peak pressure (e.g., 2.5 bar) requires larger piping and/or shorter vent path lengths

ILC presentation – Tom Peterson

8

Slide9

LHC Crab Cavity Cryostat, 14 Dec 2012Conclusion for MAWP

Maximum Allowable Working Pressure

(MAWP) The pressure which we declare on our engineering notes will be the maximum the vessel will see Relief valves and vent piping are sized to prevent pressure exceeding this value

2 bar differential pressure warm (minimum!)

Helium space to cavity vacuum

Helium space to insulating vacuum

2.5 bar to 4 bar differential pressure cold Helium space to cavity vacuum Helium space to insulating vacuum Higher (closer to 4 bar) is better in allowing smaller diameter and longer pipes to vent valves ILC presentation – Tom Peterson

9

Slide10

LHC Crab Cavity Cryostat, 14 Dec 2012Safety/compliance issue

In the U.S., Europe, and Japan, these helium containers and part or all of the RF cavity fall under the scope of the local and national pressure vessel rules.

Thus, while used for its superconducting properties, niobium ends up also being treated as a material for pressure vessels.

For various reasons, it is not possible to completely follow all the rules of the pressure vessel codes for most of these SRF helium vessel designs

Presentation to DOE, 21 Sep 2011

10

Slide11

LHC Crab Cavity Cryostat, 14 Dec 2012Issues for code compliance

Cavity design that satisfies level of safety equivalent to that of a consensus pressure vessel code is affected by

use of the non-code material (niobium),

complex forming and joining processes,

a shape that is determined entirely by cavity RF performance,

a thickness driven by the cost and availability of niobium sheet,

and a possibly complex series of chemical and thermal treatments.

Difficulties emerge pressure vessel code compliance in various areas Material not approved by the pressure vessel code Loadings other than pressure Thermal contraction Tuning

Geometries not covered by rules

Weld configurations difficult to inspect

Presentation to DOE, 21 Sep 2011

11

Slide12

LHC Crab Cavity Cryostat, 14 Dec 2012General solution

In applying ASME code procedures, key elements demonstrating the required level of design safety are

the establishment of a maximum allowable stress

And for external pressure design, an accurate approximation to the true stress strain curve

Apply the ASME Boiler and Pressure Vessel Code as completely as practical

Exceptions to the code may remain

We have to show the risk is minimal

Satisfy the requirement for a level of safety greater than or equal to that afforded by ASME code.

Fermilab, Brookhaven, Jefferson Lab, Argonne Lab, and others in the U.S. have taken a similar approachPresentation to DOE, 21 Sep 201112

Slide13

LHC Crab Cavity Cryostat, 14 Dec 2012Conclusions

Niobium, niobium-titanium, electron beam welding, and other features required for the proper function of superconducting RF cavities create problems with respect to pressure vessel codes in all regions of the world

With significant effort, laboratories have found various ways to provide levels of safety equivalent to the applicable code rules

These methods involve

taking some very conservatively low values for niobium yield strength due to heat treatments and uncertainty, and doing analysis and quality assurance inspections in accordance with code rules as much as possible

Treating the vacuum vessel as the primary containment volume or excluding the niobium material from the pressure boundary definition may be feasible in some cases

Presentation to DOE, 21 Sep 2011

13

Slide14

LHC Crab Cavity Cryostat, 14 Dec 2012Cryomodule requirements -- major components

D

ressed

RF cavities

RF

power input couplers

One intermediate temperature thermal shield

Cryogenic valves

2.0 K liquid level control valve Cool-down/warm-up valve 5 K thermal intercept flow control valve

Pipe and cavity support structure

Instrumentation -- RF, pressure, temperature, etc.

Heat exchanger for 4.5 K to 2.2 K precooling of the liquid supply flow

14

Slide15

LHC Crab Cavity Cryostat, 14 Dec 2012Cryomodule requirements -- major interfaces

Bayonet

(or other style) connections

for helium supply and return

Vacuum vessel support structure

Beam tube connections at the

cryomodule

ends

Double vacuum valves

Guard vacuum pumping

Thermal intercepts

Allowance for thermal contraction

RF waveguide to input couplers

Instrumentation connectors on the vacuum shell

Alignment

fiducials

on the vacuum shell with reference to cavity positions.

Vacuum system for pumping insulating vacuum

15

Slide16

LHC Crab Cavity Cryostat, 14 Dec 2012Design considerations

Cooling arrangement for integration into

cryo

system

Pipe sizes for steady-state and emergency venting

Pressure stability factors

Liquid volume, vapor volume, liquid-vapor surface area as buffers for pressure change

Evaporation or condensation rates with pressure change

Updated heat load estimatesOptions for handling 4.5 K (or perhaps 5 K - 8 K) thermal intercept flow Alignment and support stability Thermal contraction and fixed points with closed ends

16

Slide17

LHC Crab Cavity Cryostat, 14 Dec 2012Cryomodule Pipe Sizing Criteria

Heat transport from cavity to 2-phase pipe

1 - 1.4 Watt/

sq.cm

. is a conservative rule for a vertical pipe (less heat flux with non-vertical connection to helium

vessel, analysis for tight spaces)

Two phase pipe size

5 meters/sec vapor

“speed limit” over liquid

Not smaller than nozzle from helium vessel

Gas return pipe (also serves as the support pipe in TESLA-style CM)

Pressure drop < 10% of total pressure in normal operation

Support structure considerations

Loss of vacuum venting P < cold MAWP at cavity

Heat flux as much as 4 W/cm

2

on low-T bare metal surfaces

Path

includes nozzle from helium vessel, 2-phase pipe, may include gas return pipe, and any external vent lines

17

Slide18

Cryostat design options Use existing designs to the extent possible Two cavities, R&D nature of test Provide relatively easy access to cavities, tuner, input coupler, HOM couplers Several examples of such cryostats exist

1 – capture cavity

2 – horizontal test cryostats

3 – various top-loading designs

LHC Crab Cavity Cryostat, 14 Dec 2012

18

Slide19

Cryostat design option examples – 1 Capture Cavity Single cavity in a cryostat Tension rod support Flanged vacuum shell heads

Short cryostat allows attachment of tension rods to vacuum shell and transfer of load to the rods after insertion of cavity on simple tooling

Similar to what we saw from

Niowave

LHC Crab Cavity Cryostat, 14 Dec 2012

19

Slide20

Saclay/Fermilab Capture Cavity

LHC Crab Cavity Cryostat, 14 Dec 2012

20

Slide21

Cryostat design option examples – 2 Horizontal test cryostat (similar to “Chechia” at DESY) Single cavity in a cryostat Support post and frame beneath cavity

Cavity rolls into position for ease of frequent changes

Flanged and hinged vacuum shell heads

LHC Crab Cavity Cryostat, 14 Dec 2012

21

Slide22

Horizontal Test Cryostat

LHC Crab Cavity Cryostat, 14 Dec 2012

22

Slide23

Horizontal test cryostat

LHC Crab Cavity Cryostat, 14 Dec 2012

23

Slide24

Cryostat design option examples – 3 Top-loading cryostat Argonne, Triumf, Daresbury

, and others

Rectangular sides

Structures hung from top plate

This design has some attractive features given the physical constraints of the SPS tunnel location and the R&D nature of these first tests

LHC Crab Cavity Cryostat, 14 Dec 2012

24

Slide25

LHC Crab Cavity Cryostat, 14 Dec 2012

25

Slide26

Design Approach – Cryomodule Schematic

Shrikant Pattalwar Hi-

Lumi

Crab Cavity Engineering Meeting Dec 13-14, 2012 Fermi Lab

TWO PHASE LINE

60 K RETURN

40 K FORWARD

4K (LHe) SUPPLY

2K (

GHe

) RETURN

4K GHe RETURN

THERMAL SHIELD 40K TO 60K

5K THERMAL INTERCEPTS

4K PRE-COOL

2K HEX and a valve box could be a part of the module ??

Magnetic shield

Outer Vacuum Chamber

Shrikant

Pattalwar

LHC Crab Cavity Cryostat, 14 Dec 2012

26

Slide27

Design Approach – Conceptual Model

Shrikant Pattalwar Hi-

Lumi

Crab Cavity Engineering Meeting Dec 13-14, 2012 Fermi Lab

1000mm

2160mm

1000mm

Triple tube cavity support system

High order mode coupler

Low order mode coupler

RF input coupler

SPS by-pass line

413mm

420mm

194 mm

Shrikant

Pattalwar

LHC Crab Cavity Cryostat, 14 Dec 2012

27

Slide28

ScheduleDesign process for new cryostat or cryogenic box is typically 2 to 3 years After a complete definition of requirements, details of associated components (e.g., tuner, input coupler) are known, conceptual design (first year or more) . . . ~1

yr

engineering and design/drafting

~1

yr procurement and fabrication

LHC Crab Cavity Cryostat, 14 Dec 2012

28

Slide29

Schedule

Cavities to be installed in SPS in December 2015

Cryostat fully tested Q3-2015

Cryostat fully dressed Q2-015

Couplers available for cryostat Q1-2015

Couplers RF processed 50 kW SW

cw

all phases Q4-2014

Couplers assembled in clean room Q2-2014 onto test boxSpecial processes FPC + Test Box (Cleaning, Brazing, EB welding, Gold plating, Ti coating) completed Q1-2014All couplers + Test Box parts machined Q4-2013All raw material delivered Q2-2013

All raw material ordered Q1-2013

(common) Coupler design completed February 2013

(+ Test Box !)

2013

2014

2015

2016

LHC Crab Cavity Cryostat, 14 Dec 2012

February

Eric

Montesinos

29

Slide30

LHC Crab Cavity Cryostat, 14 Dec 2012SM18 tests

Important to verify as much as possible before installation in SPS

Leak tight cold

Heat loads

RF performance of power couplers and cavities

C

ompatibility for cryogenic connections between SM18 and SPS

2 K – 4 K heat exchanger, valves

Opportunity also to verify SPS flexible connections30

Slide31

LHC Crab Cavity Cryostat, 14 Dec 2012Conclusions

Three cryostats, one for each cavity type

Each will contain two cavities of the same type

Tight thermal constraints for SPS operation

Tight mechanical constraints for SPS installation

Plus motion requirement

Vertical cavity tests

Cryostat test at SM18 before tunnel installation

Verify thermal performance within SM18 constraints Verify, as-installed in cryomodule, coupler and cavity RF performance at SM1831