GUJARAT RAIL INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED Status Update amp Way Forward 1 About GRIDE Implementation Structure Projects Process of identification Identified Projects Future projects identification ID: 805642

amp project line railway project amp railway line kms equity projects state ride rail vayor port cost total gujarat

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "GUJARAT RAIL INFRASTRUCTURE DEVELOPMENT..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

GUJARAT RAIL INFRASTRUCTURE DEVELOPMENT CORPORATION LTD.

GUJARAT RAIL INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED

Status Update & Way Forward

1

Slide2

About G-RIDE

Implementation StructureProjectsProcess of identification

Identified ProjectsFuture projects’ identification

Projects Status & Way Forward 2

Agenda

Slide3

About G-RIDE

3

Announcement in Railway Budget

:

26

th

of February, 2015

Date of Signing of JV Agreement b/t GoG & Ministry of Railways

:

17th of August, 2016

Incorporation of Company

:

6

th

of January, 2017

Key Management:

 

 Chairman:Sh. M. K. Das, IAS , Principle Secretary (Industries & Mines),GOG. Managing Director (MD):Sh. Ashwini Kumar, IAS , Sect. to CM,GOGDirector (BDev. & Finance):Full Time (State Nominee)Director (Project & Planning):Full Time, IRSE (Railway Nominee)Part Time Directors:  State Nominee:3 NosRailway Nominee:3 Nos

Slide4

Organization Set up

4

Independent

Part Time

Full Time

Full Time

Full Time (IRSE)

Part Time

Independent

Total

One

Three (including Chairman)

One

Managing Director

One

Three

OneEleven

Slide5

Organization Set up – Key Management

5

KEY MANAGEMENT:

Chairman

-

Sh. M. K. Das, IAS , Principle Secretary (Industries &

Mines),GOG

Managing Director (MD) -

Sh. Ashwini Kumar, IAS

,

Sect. to CM,GOG

2 (TWO) WHOLE TIME DIRECTORS:

Director (BD & Finance) –

Sh. Z A Khan, IRAS/OSD-GIDB (GOG Nominee)

Director (Project & Planning) –

Sh. Santosh Kumar, IRSE (MOR Nominee)

PART TIME DIRECTORS:State Nominee- 2 Nos. Shri Mukesh Kumar, IAS /VC & MD, Gujarat Maritime Board Shri Hurbert Christian, Deputy Secretory & Financial Advisor (Industries)Railway Nominee- 3 Nos. Shri Sanjay Rastogi, IRSE , PED/SPV/Railway Board Shri S.K.Garg, IRSE, CPM, Ahmedabad/WR Shri Chittranjan Swain, IRTS, CTPM/WR

Slide6

Key Objectives of G-RIDE

6

T

o act as a

"

nodal agency for railway infrastructure

in the State of Gujarat.

T

o realize the vision for

Cooperative Federalism

that caters more efficiently to local aspirations

Promote and encourage innovation and best practices in these railways infrastructure development’

including in conceptualization, design, construction and maintenance

‘Generate greater financial resources through greater participation’ of the State, other stakeholders, including the private sector in project specific SPVs

Slide7

Key Objectives of G-RIDE

7

To deliver technical expertise for railway infrastructure development’

through the commissioning of DPRs and other studies as also through in-house expertise and external experts.

To identify and connect the identified un-served regions’

in the state offering all citizens equitable access to convenience, facilities and opportunity.

To speed up the Development of Railway Projects on state’s priority and

deliver the top 6 priority railway infrastructure projects of the State by 2025

To deliver railway infrastructure that complements the states objectives

of encouraging trade, tourism, economy and overall growth in the state.

Slide8

Project Implementation Structure

8

G-RIDE – 51% Government of Gujarat and 49% Ministry of Railways

Initial equity infusion of INR 100 Cr.

Specific project SPVs to be created with min. 26% equity infusion by G-RIDE

Further debt raising in project SPVs to finance individual projects

Ministry of Railways

49% equity

Government of Gujarat

51% equity

Gujarat Infrastructure Development Corporation Limited (G-RIDE)

Debt raising through Multilateral Agencies, Infra Bonds etc.

Other Equity Participants (Private/ Government)

Min. 26% equity by G-RIDE

Debt raising through banks, Financial Institutions etc.

Project SPVs

Slide9

Projects: Process of identification

9

A Task Force Committee comprising 5- GOG Members & 4 MOR

Members was formed in 2016-17 to identify and prioritize the projects in G-RIDE.

Identification of projects was based on the following two principles:

 

Project should be financially viable;

OR

2.

Project should be economically viable provided Viability Gap Funding (VGF)/ Subsidy for such project is available as per the present guidelines.

Task Force Committee identified 12 rail projects in State of Gujarat.

Slide10

Projects: Future Projects’ Identification

10

RAILWAY MASTER PLAN FOR THE STATE OF GUJARAT

Review the current railway capacity, and establish the gap between this capacity and the requisite railway infrastructure;

Assess the demand/requirement of Railway Infrastructure (both passenger and freight) in State in totality for next 30 years horizon period;

Propose a railway development strategy and comprehensive integrated Master Plan;

Prepare a suitable organizational, regulatory, legal and financial structure to implement the Master Plan;

Assist State Government in implementation of the Master Plan.

Slide11

Projects: Future Projects’ Identification

11

RAILWAY MASTER PLAN FOR THE STATE OF GUJARAT

Under 5 key themes

,

87 different projects and 4800+ kms of route interventions which

needs to be developed across the state identified for 30 years horizon period

Theme (No. of Projects)

2020-30

2030-40

2040-48

2048+

DFC

3

2

 

 Port Connectivity8221Industrial Connectivity651 Mobility and Accessiblity63245Tourism37  Total (No. of projects)264876Total 87 Projects identified across 5 themesTheme (Estimated Investment ‘000 Crores)2020-302030-402040-482048+DFC1.33.2  Port Connectivity3.11.39.21.5

Industrial Connectivity

3.1

1.04

1.4

 

Mobility & Accessibility

14.7

24.8

16.8

9.9

Tourism

1.5

4.9

 

 

Total (Broad estimate of investment ‘000 Crores)

23.7

35.2

27.4

11.4

Total Estimated Investment: ~97.7 Thousand Crores *

*: Based on Industry benchmarks and thumb-rule estimates

Slide12

Projects: Future Projects’ Identification

12

RAILWAY MASTER PLAN FOR THE STATE OF GUJARAT

I

nterventions across Rail Network Augmentation, New rail lines, Bypass lines, Multimodal Logistics parks, ICD’s, Private fright terminals have been proposed for improvement on increasing the modal share of railways for freight movement in the state.

Semi High-speed rail corridors projects such as Ahmedabad-Rajkot Semi High Speed Rail System, New line for connecting the unserved tribal areas, Regional Rail System for four major growth centres, Metro systems for 4 major urban centre, Station Redevelopment and Connectivity to tourism destinations have been proposed for improvement of passenger facilities in the state.

Slide13

Infrastructure Set-Up

13

G-RIDE has set up its new office (Carpet area measuring 5503 Sq. Ft.) at Block no. 6, 7

th

Floor, Udyog Bhawan, Gandhinagar

New Office started on 23

rd

October 2018.

Slide14

Organization Set up – General Consultancy Team

14

GENERAL CONSULTANCY TEAM:

CORE STAFF:

Team Leader – K K Sharma (IRSE Rtd. PCE, With 35 Yrs. experience)

Alignment cum Estimation cum Drawing Expert – Ramakrishna with Total 35 Yrs. Railway experience.

GM Civil – S K Roy (IRSE SG. Dy. CE Rtd. With 25 Yrs. experience)

GM Electrical – H P Sharma (Dy. CEE Railway on Deputation)

SENIOR MEMBERS:

Civil Engineer - 2

CAD & GIS – 1

S&T Engineer– 2

Electrical Engineer - 1

ASSOCIATE MEMBERS:

Information Technology – 1

S&T - 1

Slide15

Organization Set up – Other Staff Members

15

Retired Railway Staff – 04

Other Technical Staff – 13

Non technical Staff – 06

Housekeeping Staff – 05

Security Staff – 03

Total Staff

- 31

Slide16

Current Equity Structure of G-RIDE

16

S.No.

Particulars

State Govt.

(Rs in Cr.)

Ministry of Railways

(Rs in Cr.)

Total

(Rs in Cr.)

1.

Equity Released

(Upto March 31

st

, 2018)

10.00

9.61

19.612.Equity Released(FY 18-19)8.007.6915.693.Total Equity (Mar-19)18.0017.3035.304.Total Equity after receiving matching application by MOR8.017.6951.07GOG has made a budgetary provision of Rs. 51.0 Cr total equity contribution in G-RIDE for FY 2018-19Additional matching equity contribution will be raised by MOR for Rs.7.69 CR of total Rs.51.0 CR contribution.Additional Share Application Money of Rs. 8.01 Cr. has been received from GOG. The shares will be allotted once the matching contribution is received from MOR.

Slide17

Current Status of the Projects

17

S. No.

Project Name

Project Cost

Status

1.

Katosan- Becharaji- Chanasma- Ranauj (65 Kms)

528 Cr

Project sanctioned by Railway Board in Sept’18. Project SPV namely BRCL incorporated.

EPC Tender at Rs 487 Cr. Invited with Bid due Date 02.05.2019.

PMC tender to be invited.

GRIDE Projects.kmz

2.

Arnej – Tarapur (45.62 kms)

1103 Cr

Feasibility cum Bankability study being done

by Ernest and Young (E&Y).Meeting with prospective Stakeholders undertaken. Revalidation of Traffic estimation data & financial analysis is underway by Ernest and Young (E&Y).3.Surat-Kosad- New Sanjali(DFC Station) -30 kms623 CrFeasibility cum Bankability study being done by Etude Services.Detailed Traffic estimation & financial analysis in next slides

Slide18

Current Status of the Projects

18

S. No.

Project Name

Project Cost

Status

4.

Bedi

Port Last Mile Connectivity Project: Windmill Station to old

Bedi

Port (Phase-1: 3.03 Km),

Rail Connectivity to New

Bedi

and

Rozi

Port (Phase-II: 11.32 Km)

Phase-I: 44 Cr.

Phase-II: - 150 CrGujarat Maritime Board (GMB) along with its agency Sagarmala Development Company has expressed its in principle approval as equity partners in project SPV to undertake the proposed project. G-RIDE is in the process of obtaining in-principle approval from Railway Board to allocate the project & form a project SPV jointly with GMB & Sagarmala Development Company.5.Nargol Port Last Mile connectivity (approx. new BG line 23 kms) 181 CrGMB has advised G-RIDE to undertake Financial/ Technical feasibility study for proposed port connectivity project vide letter dated 22.03.2019. The same is being pursued by G-RIDE.6.Vayor to Koteshwar New Rail line (38.76 kms) connectivity290.34 CrFeasibility cum bankability study completed by GIDB in consultation with G-RIDE through M/s. Aarvee Consultants. Details in next slides.

Slide19

SPV Status (Bahucharaji Rail Corporation Limited- BRCL)

for KTRD-RUJ Gauge Conversion project

19

SPV (BRCL) was incorporated on 13.12.2018 with a total authorised equity capital of Rs 1 Crore.

Equity Structure:

Description

Share

% Project Cost

Rs (In Cr.)

Equity

GRIDE (Govt. of Gujarat)

20.91

110.45

GRIDE (Ministry of Railways)

20.09

106.12

Maruti Suzuki India Limited

33.00174.31GIDC26.00137.33Total Equity100.00528.22DebtNILNILNILTotal100.00528.22First Board meeting was conducted on 9th January, 2019. Minutes of meeting are approved.Share holder Agreement is under process.Initial Authorized capital has been called from respective stakeholders. G-RIDE and MSIL has contributed their share respectively. Shares will be allotted to stakeholders after GIDC contribution is received.EPC Tender was floated on 28th Feb, 2019. The last date for submission of tender is 02.05.2019.

Slide20

New BG line between Surat-

Kosad- New Sanjali

(DFC Station) -30 kms- Project benefits

20

DFC rail connectivity to industry and port in Hazira area,

KRIBHCO

fertiliser

siding,

KRIL PFT, ONGC siding, IOC siding and

proposed Adani Hazira Port

Panoli

(existing station on WR)-New

Sanjali

(proposed station on DFC) already proposed.

Traffic to/ from DFC without surface crossing,

avoiding loss of sectional capacity and

congestion.high rise OHE - double stack container movement

Slide21

Surat-

Kosad- New Sanjali (DFC Station) 30 kms New BG Line –

OD Traffic Projections

21

Commodity/ class

From

To

2019

2025

2030

2035

Remarks

POL

ONGC Kosad

Panki

0.19

0.19

0.190.19No growth Fertiliser KRIBHCO HaziraBijnor1.731.731.731.73No growthImport FertliserPortUP0.10.20.20.2Port Projection Finished Steel KRIBHCO PFTGhaziabad0.660.991.321.658% simple growthImport SteelPortGhaziabad0.10.140.180.228% simple growth Container /steel

KRIBHCO PFT

Pali KRIL siding

0.26

0.39

0.52

0.65

8% growth till 2025

Imported Coal

KRIBHCO PFT

GNVF, BH

0.25

0

0

0

Imp coal loaded from port

Slide22

Surat-

Kosad- New Sanjali (DFC Station) 30 kms New BG Line –

OD Traffic Projections

22

Commodity/ class

From

To

2019

2025

2030

2035

Remarks

Imported Gypsum

KRIBHCO PFT

Sardarnagar

0.02

0.02

0.020.02No growthImported mineralsPortNE Rly1.131.81.81.8Port ProjectionContainerPali PFTKRIL PFT0.110.110.110.11No growthPOL KanalusIOC Kosad0.480.480.48

0.48

No growth

Container Import

Port

Dadri

0

260000

390000

390000

10% growth in rail traffic

Container Export

Dadri

Port

0

260000

390000

390000

10% growth in rail traffic

Agri Product

MP

Port

0.4

0.52

0.52

0.52

Port projection

Slide23

New BG line between Surat-

Kosad- New Sanjali (DFC Station) -30 kms Estimated Traffic Commodity wise

23

Traffic estimated

Sr. No

Category

Traffic Estimated 2025

(In MMT)

Traffic Estimated

2055

(In MMT)

1.1

Containers

0.39

0.76

1.2

Fertilizers

1.751.751.3Gypsum/Minerals1.821.821.4POL0.190.191.5Steel1.131.871.6Coal1.61.61.7Total (MMT)6.887.991.8EXIM Container Cargo (TEUs)260,000390,000The project line is scheduled to commence commercial operations in FY-2025

Slide24

Vayor

to Koteshwar New Rail line (38.76 kms) Connectivity- An extension of Bhuj-

Naliya- Vayor

(125.4 kms) line

Existing SPV for gauge conversion of Bhuj-

Naliya

(101.4km) with extension to

Vayor

as BG line (24km) consisting of 3 stake holders namely RITES, Shapoorji-Pallonji and PCM Cements conducted financial feasibility study of above line. Findings detailed below:

24

Bhuj-

Naliya

-

Vayor

section to be executed on SPV model (70:30 D/E Model)

(Base Case)

Length

126.0 KmCost of the project (including Land and soft cost)827 CrProject IRR3.83%Average DSCR0.19Expected Return of Equity14%Weighted Average Cost of Capital11.9Bhuj-Naliya-Vayor section to be executed on SPV model (70:30 D/E Model)(considering Inflated mileage of 40%)Cost of the project (including Land and soft cost)827 CrProject IRR14.71%EIRR17.12%Average DSCR1.39Expected Return of Equity14%Weighted Average Cost of Capital11.55%

Slide25

Vayor

to Koteshwar New Rail line (38.76 kms) Connectivity- An extension of Bhuj-

Naliya- Vayor

(125.4 kms) line

Considering the

demands of Federation of Kutch Industries Association,

GIDB in consultation with G-RIDE conducted Feasibility cum bankability study for

Vayor

to

Koteshwar

(38.76 kms) new line project. Findings detailed below:

25

Vayor-Koteshwar

Stand Alone Project executed on SPV model (100% Equity Model)

(Base Case)

Length

38.76 KmCost of the project (including soft cost)290.34 CrProject IRR-3.39%Project NPV-21023.30 LakhVayor-Koteshwar Stand Alone Project executed on SPV model (100% Equity Model) (considering Inflated mileage of 40%)Length38.76 KmCost of the project (including soft cost)290.34 CrProject IRR4.35%Project NPV-12410.49 LakhIRR is less than 14%

Slide26

Vayor

to Koteshwar New Rail line (38.76 kms) Connectivity- An extension of Bhuj-

Naliya- Vayor

(125.4 kms) line

26

Bhuj-

Naliya

-

Vayor-Koteshwar

(164.76 Kms) line as a Single Project executed on SPV model (48:52 D/E Model)

Cost of the project (including soft cost)

1117 Cr

(827.1 Cr for Bhuj-

Naliya

-

Vayor

+290.34 Cr for

Vayor-Koteshwar including land)IRR15.80%NPV @10% discounting rate412 CrEIRR20.21%In light of the poor financial viability of the 38.76 kms line from Vayor to Koteshwar, possibility of taking up the entire line from Bhuj-Naliya-Vayor to extension upto Koteshwar (164.16 kms) as a single project may be explored.

Slide27

Issues for discussion

Approval of Plan, Design & Drawings (Civil, S&T and Electrical)

Standardization of Cost Estimation (Soft Costs) for the project on EPC

Approval for siding connectivity from Project area

Model Concession Agreement