/
Definition of space required for Definition of space required for

Definition of space required for - PowerPoint Presentation

roxanne
roxanne . @roxanne
Follow
356 views
Uploaded On 2022-06-15

Definition of space required for - PPT Presentation

assembling the SC Link J Fleiter and A Ballarino 14052020 Scope The WP6a activity requires space at the surface in order to perform the integration of the MgB 2 cables inside the cryostat ID: 919311

link cryostat cable terminal cryostat link terminal cable spooled spool assembly corridor perform transport working area empty sequence bring

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Definition of space required for" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Definition of space required for assembling the SC LinkJ. Fleiter and A. Ballarino

14/05/2020

Slide2

ScopeThe WP6a activity requires space at the surface in order to perform the

integration of the MgB

2

cables inside the cryostat

, the connection of the

MgB

2

to the

Nb-Ti

cables at one SC Link termination

, the installation of the

DFH plus current leads

and

the splices between MgB

2

and HTS cables

at the other SC Link termination, the

electrical insulation of the splices

, the

routing and connection of the instrumentation wires

. In addition, the following operations will have to be performed:

R

eception

of

spools of cryostats and of MgB

2

cables – the latter prior to insertion in the cryostat, reception and temporary storage of sub-modules of DFHX and DFHM, re-spooling of final system with DFH connected;

Assembly and test the sub-components and of the final system, i.e. welding and soldering operations,

QA of welds,

pressure tests,

l

eak tests, HV

tests

(5 kV), electrical

continuity test

of instrumentation

Slide3

Installation of MgB2 cable in cryostat, preparation of LTS termination, assembly of DFH and current leads

The space requirement consider the assembly of both Inner

T

riplets and Matching

S

ection SC Link systems The space is subdivided in four different volumes:Three working volumes:One terminal at each extremity called T1 and T2, One corridor linking T1 and T2A transport area adjacent to the corridorA loading and unloading area (near T1) A temporary storage area next T2

Corridor

T2

T1

W_2

L

_2

W_1

L

_1

W_c

L_c

H

_2

H_1

H_c

Transport area

Loading

area

Storage

Slide4

Schematic working sequence

Sequence of work (not exhaustive):

Install a winch in T2

Bring the spooled cryostat to T1

Unwind the cryostat from T1

Remove the empty spool, bring the spooled cable to T1Insert the MgB2 cable assembly in the SC Link cryostat from T1Perform the HV tests after cable insertion [EDMS N. 2376026] Perform assembly of DFHM or DFHX at T2Perform Nb-Ti to MgB2 splices in T1 (for MSs) or in the corridor (for ITs)Install the SC Link transport frame (including its spool) at T1 and start winding the Link at T1Evacuate the spooled SC Link system from T1 and start the next one as from step b

Corridor

Cryostat, Cable in cryostat

Terminal

1

Terminal

2

Winch

DFH, current leads

Cable in spool

Cryostat in spoolLTS extension

Re spooling SC Link

Slide5

Working sequence for

SC-Link

of MS

Terminal

1

Terminal

2

a. Install

winch in

T2

b. Bring

the spooled cryostat to T1

c. Unwind

the cryostat from T1, weld flanges on cryostat

Winch

Cryostat

Spooled cryostat

Empty spool of cryostat

d

)

Remove empty spool, bring spooled cable to T1

Spooled cable

e) Insert

cable in cryostat from T1

Empty spool of cable

Slide6

Working sequence

for SC-Link of MS

f) Perform

dielectric test after cable insertion

g)

Perform assembly of DFHM at T2

h

)

Perform

MgB2 to

Nb-Ti

splices at

T1

i

)

Install

the SC

L

ink

transport frame (including its spool) at T1 and start winding the Link at T1

Assembly of DFHM

LTS splicing

Spooling

Sc

Link

j) Evacuate

the

SC link

Slide7

Working sequence for

SC-Link

of

IT

Terminal

1

Terminal

2

a. Install the

w

inch in

T2

b. Bring

the spooled cryostat to T1

c. Unwind

the cryostat from T1

Winch

Cryostat

Spooled cryostat

Empty spool of cryostat

d

)

Remove

the empty

spool, bring spooled cable to T1

Spooled cable

e) Insert the

cable in

the cryostat

from T1

Empty spool of cable

Slide8

Working sequence for

SC-Link

of

IT

f) Perform HV tests

after cable insertion

g)

Perform assembly of

DFHX

at T2

h

)

Perform LTS splices at

T1

i

) Install the SC

L

ink

transport frame (including its spool) at T1 and start winding

the SC

Link at T1

Assembly of DFHX

LTS splicing

Spooling

Sc

Link

j) Evacuate

the

SC link

Slide9

Determination of volumes and services (1/2)

Terminal 1

shall be at least 16 m long, 8 m wide and 8 m height

Terminal 2

shall be at least 16 m long, 6 m wide and 6 m height

The corridor shall be 120 m long and 3 m wide and 4 m heightA temporary storage area, 16 m x 2 m, shall be adjacent to T2A loading port shall allow to load/unload the Spools or the SC Link system on a truck with a crane. The same crane shall be able to be used at T1Access door(s) to building shall be: H≥ 6m , W ≥ 4 mOverhead crane in the zone T1: loading port (≥ 10 t), height under hook ≥ 8 mOverhead crane in the zone T2: (≥ 5 t), height under hook ≥ 6 mCorridor shall be centered

wrt Terminal 1 and Terminal 2

Corridor

Cryostat, SC Link Cable in cryostat

Terminal

1

Terminal

2

W2=6m

L2=16 m

W1=8m

L1=16m

Wc

=3m

Lc

=120 m

H2

6m

H1

8

m

Hc

=4m

Wt

=3m

Ht=4m

Transport

(Un)Loading port near T1

Temporary Storage area

Ws

=2m

Slide10

Determination of volumes and services (2/2)

Working

space at RT and protected from humidity, equipped with light

Transport area

used

to access Terminal 2 with material (from either Terminal 1 or loading port) and during spooling phases of SC Link (operation performed within one working day)Concrete floor with load capacity > 1 ton /m2 at T1, T2, corridor and transport areaPlanarity of the floor between T1, corridor and T2 (no stairs, no trench….), gaps shall be less than 5 mm The volumes shall be satisfy safety requirements and be equipped with fume detection systemsTerminal 1, Terminal 2, and the zone of the corridor where the DFHX will be assembled be equipped with fume extractorsElectricity outlets shall be available (230 V-16 A and 380 V-32 A) at each terminal T1 and T2 (three outlets at each terminal)