20 min 18102013 JeanPhilippe Tock TEMSC On behalf of the SMACC project Activities since last LSC 27092013 Arc splices installation By Activities By sectors Globally ID: 382484

sectors smacc completed progress smacc sectors progress completed report leak ics sector activity rate test activities final installation weeks baseline splices delay

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "SMACC Twelfth report" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1
Slide2

SMACC Twelfth report[20 min]18/10/2013

Jean-Philippe

Tock

(TE-MSC)

On

behalf

of the SMACC

project

Slide3

Activities since last LSC (27/09/2013)

Arc splices installation

By Activities

By sectors

Globally

SIT

DFBA

DN200

Dashboards

Activities

for the next 2

weeks

ConclusionsSlide4

Sector 56 :

Work on

non-conformities

including repair of overheated cableReclosure (not in priority) and final leak testSector 67 (Priority sector)Complete installation of insulation boxes and injectionRewelding of M sleevesLeak test of M linesReclosure of interconnections and final leak testsDFBA consolidationSector 78Installation of shunts – start installation of electrical insulationQuadrupole diodes consolidationDFBAs consolidationReconnection of Q5L8Sector 81Complete ElQC of existing splicesDesoldering / Resoldering of splicesInstallation of shuntsOther sectors:S12: Start ElQC of existing splicesS23: Open busbar lines and diodes containersS34 & 45: Reconnection of replacing magnetsAdvanced opening for outliers and CSCM segmentsInspection of connection cryostats

SMACC Main activities for the next 2 weeks

3

From last LSC (27.09.2013)

On-going

Completed but NCs, 63 ICs insulated

(yesterday)

1/3 done; see later

Overheated splice redone, ≈120 ICs reclosed, 3 subsectors validated, 4 under final leak test

Completed (but NCs)

Completed but NCs

On-going, 9/14 vac subsectors validated

>100

Ics

reclosed, 5/14 sub-sector under final leak test

> ½ sector completed

Desoldering

almost completed;

resoldering

is on-going

Completed (≈ 28%)

> ¼ of S12

ElQC tested, compatible with 30% of splices to redo

On-going

½ of M lines open, all diodes containers open

4 in S34 reconnected, 2 in S45 almost reconnected

Slide5

SEQUENCE AND STATUS

OK to open

8 sectors

Open ICs> 7 sectorsInstall DN200100 %Open M sleeves> 5 sectors

ELQC

(old splices)

>

4 sectors

Undo / Redo splices

≈ 4 sectors

ELQC

(new splices)

Machine Cu

>

3.5 sectors

ELQC

after Cu mach.

>

3.5 sectors

Install shunts

3

.5 sectors

ELQC

after shunt

≈ 3.5 sectors

Insulate splices

2.3 sectors

Weld

M

≈ 2 sectors

Leak test M

>

1.5

sector

Close IC

1

sector

Final LT

≈ 1/5 sector

Consolidate

Q diodes

≈ 2.5 sectors

Availability

of components

Cancelled

CompletedSlide6

SMACC Progress report by activity

Opened

interconnections in 8

sectors, > 7 sectors-eq are openedSlide7

SMACC Progress report by activity

M line

cutting

: ≈ 5.5 sectors equivalent Replacing team trained at the surface, will go in the tunnel next weekTakes in charge the insulation removal activitiesSlide8

SMACC

Progress report by activity

Courtesy H

PrinDesoldering : Completed in S56 & 67 & 78 and @ 65 % in S81Resoldering completed in S56 & 67 & 78 and @ 50% in S81 Rates are compatible with the 30 % of splices to redo and the baseline rateFrom last LSC (27.09.2013)From last LSC (27.09.2013)

100

80Slide9

SMACC Progress report by activity

Shunts are

installed

in ≈ 3.5 sectors-eq (1/2)Rate in 81 is sticking to the baseline«Last 10% effect» in 3 sectorsDelay reduced: < 1/2 week (nominal rate)Shunt weekly installation rate (4 weeks sliding average)Slide10

SMACC Progress report by activity

Shunts are

installed

in ≈ 3.5 sectors-eq (2/2)Slide11

SMACC Progress report by activity

Installation of

insulation

box: 56 & 67 are completed and 1/3 in 78, Courtesy H Prin / M Duret63 Ics are completed in 78Rate is still too low but improving (41 is the maximum achieved so far, average of the last 4 weeks: 33)Progress curves will be integrated with the new baselineSlide12

SMACC Progress report by activity

Quadrupole

diodes

> 6 sectors are opened / ≈ 2.5 sectors are consolidated Components to cover 78 and 1/3 of 81 (3.3 sectors)  Not on the immediate critical pathSecond order launched for critical components (expensive) Delivery expected in a month timeA third solution (reasonable price) is under investigation as a fall back solutionVisit of the 1st company today (Delay issues and also NC components)Courtesy L Grand-Clement / F SavarySlide13

SMACC Progress report by activity

M

Welding

: 410 ICs welded, ≈ 2 sec-eq: No welding this week to build a buffer of ICs ready to be welded (Announced @ last LSC)Holes in 56 and 67 will be done next weekWork at a rate of 35-40 IC/week to start next week in 78 (About 70 ICs will be available on Monday), to sustain up to end 2013Will be integrated in the overall rebaseliningSlide14

SMACC

Progress report by activity

M

sleeves leak testing : (320 ICs) are leak tested (≈ 1.5 sec-eq)All possible subsectors of S56 (11/14) are leak tested9/14 subsectors are leak tested in 67Present situation will be included in the general rebaseliningCourtesy P Cruikshank / L MourierSlide15

SMACC

Progress report by activity

Reclosure

of interconnections : On-going in 67 (priority) and 56 (> 1 sec eq), 120 ICs are reclosed in 56 and 100 in 67Priority is on S67Global rate to increase and reach baseline value with the reinforcement of part of the DN200 teamSlide16

SMACC

Progress report by activity

Final

leak test: Starting3 subsectors validated9 more under test (4 in 56 and 5 in 67)Almost 1 sec eqResults in 2 weeks timeSlide17

SMACC Progress report by sector

Main activities are on non-conformities

Overheated cable

resoldered, now to be shunted and reinsulatedUninstall shunts to remove the DFBAK shuffling moduleSimilar repair (Sandwich) to be applied in other ICs Courtesy M Duret, N Dalexandro, P Voisin, R PrincipeQQBI.27R8

QBQI.18R8Slide18

SMACC Progress report by sector

All non-problematic ICs are shunted, insulated and

rewelded

Main activities are the leak test of M lines, the reclosure and the final leak testsThis sector should be the first to be ready for pressure testPlanned to be completely reclosed for end of NovemberSlide19

SMACC Progress report by sector

All non-problematic ICs are shunted

Main activities are the installation of the electrical insulation and the

rewelding of M lines (to start next week)Slide20

SMACC

Dashboards

Opening

is ahead of schedule Shunting is almost back on scheduleCritical activity is the insulation (Progress curve soon to be included)Welding and M leak test are limited by release rate, confident that nominal rate can be achieved, margin has been eaten upReclosure: Not yet nominal rate, to be increased

Final leak test on-

going for almost 1 sec eqSlide21

SMACC Progress report by sectorSlide22

SMACC DashboardsSlide23

SMACC DashboardsSlide24

SMACC Progress report SIT

SIT

All

cryomagnets are reconnected, except the 2 dipoles in S45 and the Q5L8 (SAM)Standard reconnection will be done by the train when it will arriveJust started: Interventions on SAM He level gauges: Accessible for MME intervention (Not critical)On hold: Intervention on the triplets braid  Disconnection of the DFBAK SHM that will start next Monday (See TE-CRG presentation)Courtesy N Bourcey, S Le NaourSlide25

SMACC Progress report DFBA

DFBA:

See

TE-CRG presentationImpact of interventions to fix the M bellows is under integration in the new baselineDFBAK shuffling module to be disconnectedDFBAO on-hold Courtesy TE-CRG, TE-MSC and EN-MME?Slide26

SMACC Progress report DN200

DN200 :

Work

completedCourtesy Jose Manu Gomes de Faria, A Musso and collaboration with DUBNADN200 to install on removed cryomagnets and for the installation of the cryogenics BLMPart of the team is staying and is trained to assist the opening/closure of interconnections and also the upgrade of the IC thermal shieldsSlide27

SMACC

Dashboards

Baseline: 38.1 % (30.9 %)

Completed: 33.7 % (27.0 %)Delay 12 (11) daysBaseline: 54.6 % (49.6 %)Completed: 45.8 % (38.7 %)Delay 30 (28) daysBaseline: 56.6 % (47.4 %)Completed: 37.4 % (32.0 %)Delay 39 (38) days

Baseline: 100 % (100 %)Completed: 100 % (88.2 %)

Completed

 Delay stable

 Delay stable

Not representative

To be

rebaselinedSlide28

SMACC

Dashboards

Progress:

Baseline: 42.8% (36.3 %) Completed: 36.8% (30.1 %)Delay 18 (18) daysStable ; Δbaseline ≈ ΔcompletedSlide29

SMACC Summary on progress

Main 13 kA Splices:

 Delay stabilised to 2 weeksSpecial Interventions:  Delay stable, new activities (DFBAK SHM)DFBA: To be rebaselinedDN200: CompletedSMACC:  About 3 weeks (stable)Delays are stableNominal rate achieved these last 5 weeks !Slide30

Sector 56 :

Work on

non-conformities

including installation of all shunts, completion of M weldingDisconnection of DFBAK SHMReclosure (not in priority) and final leak testSector 67 (Priority sector)Leak test of M linesReclosure of interconnections and final leak testsSector 78Installation of electrical insulationM lines rewelding (35-40 ICs /wk)Quadrupole diodes consolidationDFBAs consolidationReconnection of Q5L8Sector 81Desoldering / Resoldering of splicesInstallation of shuntsOther sectors:S12: ElQC of existing splicesS23: Open busbar lines S34: Opening of interconnectionsS45: Reconnection of replacing magnets and opening of diodes containersInspection of connection cryostatsSMACC Main activities for the next 2 weeksSlide31

Conclusions

DN 200 installation is completed

Repair the overheated cable in 56 completed as planned

Delays are stabilisedMargin has been eaten up for some activities (M welding, M leak test)Solution is under implementation for the components of the quadrupole diodesIssues:Consolidate the splices production rates and increase the rate of installation of the insulation systems keeping qualityImpact of repair of DFBA bellows (SIT & Vac subsectors)So far, not so bad …Slide32