Download Presentation The PPT/PDF document "SMACC Twelfth report" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1Slide2
SMACC Twelfth report[20 min]18/10/2013
Jean-Philippe
Tock
(TE-MSC)
On
behalf
of the SMACC
project
Slide3
Activities since last LSC (27/09/2013)
Arc splices installation
By Activities
By sectors
Globally
SIT
DFBA
DN200
Dashboards
Activities
for the next 2
weeks
ConclusionsSlide4
Sector 56 :
Work on
non-conformities
including repair of overheated cableReclosure (not in priority) and final leak testSector 67 (Priority sector)Complete installation of insulation boxes and injectionRewelding of M sleevesLeak test of M linesReclosure of interconnections and final leak testsDFBA consolidationSector 78Installation of shunts – start installation of electrical insulationQuadrupole diodes consolidationDFBAs consolidationReconnection of Q5L8Sector 81Complete ElQC of existing splicesDesoldering / Resoldering of splicesInstallation of shuntsOther sectors:S12: Start ElQC of existing splicesS23: Open busbar lines and diodes containersS34 & 45: Reconnection of replacing magnetsAdvanced opening for outliers and CSCM segmentsInspection of connection cryostats
SMACC Main activities for the next 2 weeks
3
From last LSC (27.09.2013)
On-going
Completed but NCs, 63 ICs insulated
(yesterday)
1/3 done; see later
Overheated splice redone, ≈120 ICs reclosed, 3 subsectors validated, 4 under final leak test
Completed (but NCs)
Completed but NCs
On-going, 9/14 vac subsectors validated
>100
Ics
reclosed, 5/14 sub-sector under final leak test
> ½ sector completed
Desoldering
almost completed;
resoldering
is on-going
Completed (≈ 28%)
> ¼ of S12
ElQC tested, compatible with 30% of splices to redo
On-going
½ of M lines open, all diodes containers open
4 in S34 reconnected, 2 in S45 almost reconnected
Slide5
SEQUENCE AND STATUS
OK to open
8 sectors
Open ICs> 7 sectorsInstall DN200100 %Open M sleeves> 5 sectors
ELQC
(old splices)
>
4 sectors
Undo / Redo splices
≈ 4 sectors
ELQC
(new splices)
Machine Cu
>
3.5 sectors
ELQC
after Cu mach.
>
3.5 sectors
Install shunts
≈
3
.5 sectors
ELQC
after shunt
≈ 3.5 sectors
Insulate splices
≈
2.3 sectors
Weld
M
≈ 2 sectors
Leak test M
>
1.5
sector
Close IC
≈
1
sector
Final LT
≈ 1/5 sector
Consolidate
Q diodes
≈ 2.5 sectors
Availability
of components
Cancelled
CompletedSlide6
SMACC Progress report by activity
Opened
interconnections in 8
sectors, > 7 sectors-eq are openedSlide7
SMACC Progress report by activity
M line
cutting
: ≈ 5.5 sectors equivalent Replacing team trained at the surface, will go in the tunnel next weekTakes in charge the insulation removal activitiesSlide8
SMACC
Progress report by activity
Courtesy H
PrinDesoldering : Completed in S56 & 67 & 78 and @ 65 % in S81Resoldering completed in S56 & 67 & 78 and @ 50% in S81 Rates are compatible with the 30 % of splices to redo and the baseline rateFrom last LSC (27.09.2013)From last LSC (27.09.2013)
100
80Slide9
SMACC Progress report by activity
Shunts are
installed
in ≈ 3.5 sectors-eq (1/2)Rate in 81 is sticking to the baseline«Last 10% effect» in 3 sectorsDelay reduced: < 1/2 week (nominal rate)Shunt weekly installation rate (4 weeks sliding average)Slide10
SMACC Progress report by activity
Shunts are
installed
in ≈ 3.5 sectors-eq (2/2)Slide11
SMACC Progress report by activity
Installation of
insulation
box: 56 & 67 are completed and 1/3 in 78, Courtesy H Prin / M Duret63 Ics are completed in 78Rate is still too low but improving (41 is the maximum achieved so far, average of the last 4 weeks: 33)Progress curves will be integrated with the new baselineSlide12
SMACC Progress report by activity
Quadrupole
diodes
> 6 sectors are opened / ≈ 2.5 sectors are consolidated Components to cover 78 and 1/3 of 81 (3.3 sectors) Not on the immediate critical pathSecond order launched for critical components (expensive) Delivery expected in a month timeA third solution (reasonable price) is under investigation as a fall back solutionVisit of the 1st company today (Delay issues and also NC components)Courtesy L Grand-Clement / F SavarySlide13
SMACC Progress report by activity
M
Welding
: 410 ICs welded, ≈ 2 sec-eq: No welding this week to build a buffer of ICs ready to be welded (Announced @ last LSC)Holes in 56 and 67 will be done next weekWork at a rate of 35-40 IC/week to start next week in 78 (About 70 ICs will be available on Monday), to sustain up to end 2013Will be integrated in the overall rebaseliningSlide14
SMACC
Progress report by activity
M
sleeves leak testing : (320 ICs) are leak tested (≈ 1.5 sec-eq)All possible subsectors of S56 (11/14) are leak tested9/14 subsectors are leak tested in 67Present situation will be included in the general rebaseliningCourtesy P Cruikshank / L MourierSlide15
SMACC
Progress report by activity
Reclosure
of interconnections : On-going in 67 (priority) and 56 (> 1 sec eq), 120 ICs are reclosed in 56 and 100 in 67Priority is on S67Global rate to increase and reach baseline value with the reinforcement of part of the DN200 teamSlide16
SMACC
Progress report by activity
Final
leak test: Starting3 subsectors validated9 more under test (4 in 56 and 5 in 67)Almost 1 sec eqResults in 2 weeks timeSlide17
SMACC Progress report by sector
Main activities are on non-conformities
Overheated cable
resoldered, now to be shunted and reinsulatedUninstall shunts to remove the DFBAK shuffling moduleSimilar repair (Sandwich) to be applied in other ICs Courtesy M Duret, N Dalexandro, P Voisin, R PrincipeQQBI.27R8
QBQI.18R8Slide18
SMACC Progress report by sector
All non-problematic ICs are shunted, insulated and
rewelded
Main activities are the leak test of M lines, the reclosure and the final leak testsThis sector should be the first to be ready for pressure testPlanned to be completely reclosed for end of NovemberSlide19
SMACC Progress report by sector
All non-problematic ICs are shunted
Main activities are the installation of the electrical insulation and the
rewelding of M lines (to start next week)Slide20
SMACC
Dashboards
Opening
is ahead of schedule Shunting is almost back on scheduleCritical activity is the insulation (Progress curve soon to be included)Welding and M leak test are limited by release rate, confident that nominal rate can be achieved, margin has been eaten upReclosure: Not yet nominal rate, to be increased
Final leak test on-
going for almost 1 sec eqSlide21
SMACC Progress report by sectorSlide22
SMACC DashboardsSlide23
SMACC DashboardsSlide24
SMACC Progress report SIT
SIT
All
cryomagnets are reconnected, except the 2 dipoles in S45 and the Q5L8 (SAM)Standard reconnection will be done by the train when it will arriveJust started: Interventions on SAM He level gauges: Accessible for MME intervention (Not critical)On hold: Intervention on the triplets braid Disconnection of the DFBAK SHM that will start next Monday (See TE-CRG presentation)Courtesy N Bourcey, S Le NaourSlide25
SMACC Progress report DFBA
DFBA:
See
TE-CRG presentationImpact of interventions to fix the M bellows is under integration in the new baselineDFBAK shuffling module to be disconnectedDFBAO on-hold Courtesy TE-CRG, TE-MSC and EN-MME?Slide26
SMACC Progress report DN200
DN200 :
Work
completedCourtesy Jose Manu Gomes de Faria, A Musso and collaboration with DUBNADN200 to install on removed cryomagnets and for the installation of the cryogenics BLMPart of the team is staying and is trained to assist the opening/closure of interconnections and also the upgrade of the IC thermal shieldsSlide27
SMACC
Dashboards
Baseline: 38.1 % (30.9 %)
Completed: 33.7 % (27.0 %)Delay 12 (11) daysBaseline: 54.6 % (49.6 %)Completed: 45.8 % (38.7 %)Delay 30 (28) daysBaseline: 56.6 % (47.4 %)Completed: 37.4 % (32.0 %)Delay 39 (38) days
Baseline: 100 % (100 %)Completed: 100 % (88.2 %)
Completed
Delay stable
Delay stable
Not representative
To be
rebaselinedSlide28
SMACC
Dashboards
Progress:
Baseline: 42.8% (36.3 %) Completed: 36.8% (30.1 %)Delay 18 (18) daysStable ; Δbaseline ≈ ΔcompletedSlide29
SMACC Summary on progress
Main 13 kA Splices:
Delay stabilised to 2 weeksSpecial Interventions: Delay stable, new activities (DFBAK SHM)DFBA: To be rebaselinedDN200: CompletedSMACC: About 3 weeks (stable)Delays are stableNominal rate achieved these last 5 weeks !Slide30
Sector 56 :
Work on
non-conformities
including installation of all shunts, completion of M weldingDisconnection of DFBAK SHMReclosure (not in priority) and final leak testSector 67 (Priority sector)Leak test of M linesReclosure of interconnections and final leak testsSector 78Installation of electrical insulationM lines rewelding (35-40 ICs /wk)Quadrupole diodes consolidationDFBAs consolidationReconnection of Q5L8Sector 81Desoldering / Resoldering of splicesInstallation of shuntsOther sectors:S12: ElQC of existing splicesS23: Open busbar lines S34: Opening of interconnectionsS45: Reconnection of replacing magnets and opening of diodes containersInspection of connection cryostatsSMACC Main activities for the next 2 weeksSlide31
Conclusions
DN 200 installation is completed
Repair the overheated cable in 56 completed as planned
Delays are stabilisedMargin has been eaten up for some activities (M welding, M leak test)Solution is under implementation for the components of the quadrupole diodesIssues:Consolidate the splices production rates and increase the rate of installation of the insulation systems keeping qualityImpact of repair of DFBA bellows (SIT & Vac subsectors)So far, not so bad …Slide32