File No: 9429/2022 Online Proposal No: 286752/2022
Description: File No: 94292022 Online Proposal No: 2867522022 THIRU.V.SIVARAMAN Welcomes Honorable Chairman Members of State Level Expert Appraisal Committee (SEAC), Tamilnadu Existing Rough Stone Quarry 2.02.00 Ha Category : B2 No.48 A, 2nd
Related Topics
Download Presentation
"File No: 9429/2022 Online Proposal No: 286752/2022" is the property of its rightful owner. Permission is granted to download and print the materials on this website for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Presentation Transcript
slide1. File No: 9429/2022 Online Proposal No: 286752/2022 THIRU.V.SIVARAMAN Welcomes Honorable Chairman & Members of State Level Expert Appraisal Committee (SEAC), Tamilnadu Existing Rough Stone Quarry – 2.02.00 Ha Category : “B2” No.48 A, 2nd Main Road, Ram Nagar South Extension, Pallikaranai, Chennai -600100 Schedule : 1 (a) Mineral: Minor 1<br>
slide2. PROJECT SUMMARY 2<br>
slide3. PROJECT SUMMARY 3<br>
slide4. PROJECT SUMMARY 4<br>
slide5. Land Ownership:
It is a Patta Land
Statutory Approvals
Precise Area Communication Letter : Roc.No.235/Mines/2019 dated 27.04.2022
Mining Plan Approval Letter : Roc.No. 235/Mines/2019 dated 09.06.2022
Special Conditions:
7.5 m safety distance for the adjoining Patta lands. APPROVALS 5<br>
slide6. ENVIRONMENTAL SETTINGS 6<br>
slide7. DFO LETTER 6A<br>
slide8. ENVIRONMENTAL SETTINGS 7<br>
slide9. LOCATION OF THE SITE 8<br>
slide10. GEO-LOCATION OF THE SITE 9<br>
slide11. 1 KM GOOGLE IMAGE MAP 10<br>
slide12. NEARBY HABITATIONS 11<br>
slide13. TOPO MAP 12<br>
slide14. ENVIRONMENTAL SENSITIVITY MAP 13<br>
slide15. QUARRY SITE PHOTOS 14 NORTH
10° 2'18.54"N 77°26'47.30"E
Theni SOUTH
10° 2'14.24"N 77°26'45.62"E
Theni West
10° 2'16.91"N 77°26'42.93"E
Theni East
10° 2'14.97"N 77°26'50.85"E
Theni<br>
slide16. PATTA 15<br>
slide17. 500 m RADIUS LETTER and Existing Pit 16<br>
slide18. 500 m RADIUS LETTER CONTI… 17<br>
slide19. PRECISE AREA COMMUNICATION LETTER 18<br>
slide20. MINING PLAN APPROVAL LETTER 19<br>
slide21. MINING PLAN APPROVAL LETTER CONTI.. 20<br>
slide22. VAO LETTER 21<br>
slide23. SURFACE PLAN 22<br>
slide24. YEARWISE DEVELOPMENT PLAN 23<br>
slide25. YEARWISE DEVELOPMENT SECTION 24<br>
slide26. CONCEPTUAL SECTION 25<br>
slide27. CONCEPTUAL PLAN 26<br>
slide28. GEOLOGICAL RESERVES 27<br>
slide29. MINEABLE RESERVES 28<br>
slide30. MINEABLE RESERVES CONTI… 29<br>
slide31. YEARWISE DEVELOPMENT 30<br>
slide32. YEARWISE DEVELOPMENT CONTI… 31<br>
slide33. LAND USE BREAKUP 32<br>
slide34. WATER CONSUMPTION ENERGY AND FUEL CONSUMPTION 16 liters diesel will be consumed for per hour excavation for mining and loading.
Total diesel consumption is around 222656 liters of HSD for the entire period of project life. 33<br>
slide35. MANPOWER REQUIREMENT 34<br>
slide36. GREENBELT DEVELOPMENT PLAN 35<br>
slide37. GREENBELT DEVELOPMENT PLAN 36<br>
slide38. PROJECT COST The total project cost is Rs. 66,27,000/- for deployment of machinery and creation of infrastructural facilities like approach road, Mine office / Workers Shed, First Aid Room etc., including electrifications and water supply. 37<br>
slide39. ENVIRONMENTAL MANAGEMENT PLAN 38<br>
slide40. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 39<br>
slide41. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 40<br>
slide42. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 41<br>
slide43. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 42<br>
slide44. ENVIRONMENTAL MANAGEMENT PLAN CONTI…. 43<br>
slide45. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 44<br>
slide46. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 45<br>
slide47. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 46<br>
slide48. ENVIRONMENTAL MANAGEMENT PLAN 47<br>
slide49. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 48<br>
slide50. Total EMP Cost – Rs. 98,55,171(Rs. 99 Lakhs) ENVIRONMENTAL MANAGEMENT PLAN CONTI… 49<br>
slide51. CORPORATE ENVIRONMENTAL RESPONSIBILITY (CER) The following Corporate Environment Responsibility (CER) activities will be carried out for proposed mining activity. 50<br>
slide52. PROPOSED CER SCHOOL PHOTOS & LETTER 51<br>
slide53. THANK YOU…!<br>
slide54. FMB 53<br>
slide55. Open cast mechanized mining is being carried out with 5.0 meter vertical bench with a bench width is not less than the bench height.
The Rough Stone is proposed to quarry at 5 m bench height and width with conventional Opencast mechanized method.
Splitting of rock mass of considerable volume from the parent rock mass by jackhammer drilling and mild explosives blasting, hydraulic excavators are used for loading the Rough stone from pithead to the needy crushers.
Occasionally hydraulic excavators are attached with rock breakers for fragmentation to avoid secondary blasting. The primary boulders thus splitted are removed from the pits by excavators and further made to smaller sizes by rock breakers attached in excavators. It is a conventional opencast mechanized method of mining. METHOD OF MINING 54<br>
slide2. PROJECT SUMMARY 2<br>
slide3. PROJECT SUMMARY 3<br>
slide4. PROJECT SUMMARY 4<br>
slide5. Land Ownership:
It is a Patta Land
Statutory Approvals
Precise Area Communication Letter : Roc.No.235/Mines/2019 dated 27.04.2022
Mining Plan Approval Letter : Roc.No. 235/Mines/2019 dated 09.06.2022
Special Conditions:
7.5 m safety distance for the adjoining Patta lands. APPROVALS 5<br>
slide6. ENVIRONMENTAL SETTINGS 6<br>
slide7. DFO LETTER 6A<br>
slide8. ENVIRONMENTAL SETTINGS 7<br>
slide9. LOCATION OF THE SITE 8<br>
slide10. GEO-LOCATION OF THE SITE 9<br>
slide11. 1 KM GOOGLE IMAGE MAP 10<br>
slide12. NEARBY HABITATIONS 11<br>
slide13. TOPO MAP 12<br>
slide14. ENVIRONMENTAL SENSITIVITY MAP 13<br>
slide15. QUARRY SITE PHOTOS 14 NORTH
10° 2'18.54"N 77°26'47.30"E
Theni SOUTH
10° 2'14.24"N 77°26'45.62"E
Theni West
10° 2'16.91"N 77°26'42.93"E
Theni East
10° 2'14.97"N 77°26'50.85"E
Theni<br>
slide16. PATTA 15<br>
slide17. 500 m RADIUS LETTER and Existing Pit 16<br>
slide18. 500 m RADIUS LETTER CONTI… 17<br>
slide19. PRECISE AREA COMMUNICATION LETTER 18<br>
slide20. MINING PLAN APPROVAL LETTER 19<br>
slide21. MINING PLAN APPROVAL LETTER CONTI.. 20<br>
slide22. VAO LETTER 21<br>
slide23. SURFACE PLAN 22<br>
slide24. YEARWISE DEVELOPMENT PLAN 23<br>
slide25. YEARWISE DEVELOPMENT SECTION 24<br>
slide26. CONCEPTUAL SECTION 25<br>
slide27. CONCEPTUAL PLAN 26<br>
slide28. GEOLOGICAL RESERVES 27<br>
slide29. MINEABLE RESERVES 28<br>
slide30. MINEABLE RESERVES CONTI… 29<br>
slide31. YEARWISE DEVELOPMENT 30<br>
slide32. YEARWISE DEVELOPMENT CONTI… 31<br>
slide33. LAND USE BREAKUP 32<br>
slide34. WATER CONSUMPTION ENERGY AND FUEL CONSUMPTION 16 liters diesel will be consumed for per hour excavation for mining and loading.
Total diesel consumption is around 222656 liters of HSD for the entire period of project life. 33<br>
slide35. MANPOWER REQUIREMENT 34<br>
slide36. GREENBELT DEVELOPMENT PLAN 35<br>
slide37. GREENBELT DEVELOPMENT PLAN 36<br>
slide38. PROJECT COST The total project cost is Rs. 66,27,000/- for deployment of machinery and creation of infrastructural facilities like approach road, Mine office / Workers Shed, First Aid Room etc., including electrifications and water supply. 37<br>
slide39. ENVIRONMENTAL MANAGEMENT PLAN 38<br>
slide40. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 39<br>
slide41. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 40<br>
slide42. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 41<br>
slide43. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 42<br>
slide44. ENVIRONMENTAL MANAGEMENT PLAN CONTI…. 43<br>
slide45. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 44<br>
slide46. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 45<br>
slide47. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 46<br>
slide48. ENVIRONMENTAL MANAGEMENT PLAN 47<br>
slide49. ENVIRONMENTAL MANAGEMENT PLAN CONTI… 48<br>
slide50. Total EMP Cost – Rs. 98,55,171(Rs. 99 Lakhs) ENVIRONMENTAL MANAGEMENT PLAN CONTI… 49<br>
slide51. CORPORATE ENVIRONMENTAL RESPONSIBILITY (CER) The following Corporate Environment Responsibility (CER) activities will be carried out for proposed mining activity. 50<br>
slide52. PROPOSED CER SCHOOL PHOTOS & LETTER 51<br>
slide53. THANK YOU…!<br>
slide54. FMB 53<br>
slide55. Open cast mechanized mining is being carried out with 5.0 meter vertical bench with a bench width is not less than the bench height.
The Rough Stone is proposed to quarry at 5 m bench height and width with conventional Opencast mechanized method.
Splitting of rock mass of considerable volume from the parent rock mass by jackhammer drilling and mild explosives blasting, hydraulic excavators are used for loading the Rough stone from pithead to the needy crushers.
Occasionally hydraulic excavators are attached with rock breakers for fragmentation to avoid secondary blasting. The primary boulders thus splitted are removed from the pits by excavators and further made to smaller sizes by rock breakers attached in excavators. It is a conventional opencast mechanized method of mining. METHOD OF MINING 54<br>