Iteration of Ideas Wendell Bailey Iole Falorio Yifeng Yang Southampton Yann Leclercq Vittorio Parma CERN WP6a 1 Liquid He level DFX Concept Based on a Horizontal Integration ID: 927745
Download Presentation The PPT/PDF document "Towards a DFX Design Concept through" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Towards a DFX Design Concept through Iteration of Ideas
Wendell Bailey, Iole Falorio, Yifeng Yang @ SouthamptonYann Leclercq, Vittorio Parma @ CERN
WP6a
1
Slide2Liquid He level
DFX Concept Based on a Horizontal Integration
Presented in April/June 2017
S
ingle continuous 90
o
bend from vertical entry at the shaft to horizontal
DFX divided into sections for sequential assembly while the SC-Link is installed
A large
GHe
space continuous into the inner vessel of SC-Link flexible cryostat
SC-Link bending and insertion handled by special tooling
Slide3MgB2
Concrete
Shaft
NbTi
Instru
. wire
Safety relief
Heater
Level gauge
Plug to D1
Possible TS cooling line
Cryo
connection:
Return to SD
Inlet
LHe
Return TS E’H
Liquid level
MgB2-NbTi splices
Integration reservation
DFX Concept Based on a Horizontal Integration
Presented in April/June 2017
Slide4Angled entry, 90 degree total bend –
Tooling
Insertion into the a short fulling open end section of DFX
The final bend inside the DFX is achieved by sliding down a straight slope and then swing in to desired shape by articulating the tooling
Slide5Necessary
conditionsThe inserted SC-Link section is housed in the flexible inner continuously but without the outer. A temporary cover for integration in the shaft must be removed before insertion.The inner flexible must be pre-perforated at designed location
The extraction of the SC-Link after the system test shall be performed
Reopen/disassemble DFXUsing the tooling and the reverse procedure of insertion
Others ???
Question R
aised :Inserting Rigid of SC-Link Section without Cable Handling:
Slide6Alternative Integration?
6
Amalia, 19/07/2018
LHC shaft/core
Components of
SC Link
DFX below LHC Shaft
1.3-1.6
m
Slide7DFX Concept
Based on a Vertical Integration
Main Considerations:
Fit within the space constraints
Cryogenic considerations:
Level control
GHe
flow
Cryogenic interfacesEasy assembly within the vertical space under the shaftLTS/LTS splices with a minimum LTS length ahead of the SC-LinkMaintainability
Slide81. DFX in position and fully open, SC-Link lowered from the shaft
2. SC-Link rigid section fixed/welded to DFX lower He vessel
3. LTS/LTS splices completed and DFX lower He vessel closed
4. DFX/SC-Link vacuum barrier in position
Slide95. DFX lower vacuum vessel in position, DFX/SC-Link vacuum membrane welded to the SC-Link rigid top
6. DFX upper vacuum vessel, heater, blow-off/instrumentation outer jackets closed
2. LTS/LTS splices completed and DFX lower He vessel closed
Slide10Slide11Slide121.5 W/m
↑
0.7 g/s
1.6
m
Reduced
vapour space in the range for level control
A height of 250mm with a diameter of < 300mm
Level control within ±125mm
Additional vapour spaces bluff-off/heater extension
cryolines
(50-100mm ID)
Total cross-section ~ 600cm
2
At a continuous liquid He filling rate of 42ml/s for a nominal SC-Link
GHe
mass flow rate of 5g/s
Takes 180s or 3min to overfill to the 125mm high margin if filled at constant rate if the heater went off
The same length of time required to recover from the overfill or reach the underfill limit if the filling is off
A higher filling rate is needed to recover from underfill
The reduced vapour space seems still sufficient for a reasonable control dynamics even in on/off mode
GHe
flow in the vicinity of MgB2/
NbTi
splices to pass from main bath to the vapour space above
Mitigated by an annulus
Impedance into the splice region needs to be optimised
Disturbance to the liquid level stability: bubbles exit at an effective velocity of ~3.6cm/s at 50% quality
Line SD pressure and the management of excess vapour in DFX
Baseline control strategy for level and
GHe
flow, dynamic characteristics (time constant,
alarms, auxiliary instrumentations
suc
as pressure, etc), and their interplays
MgB2
NbTi
Instru
. wires
Safety relief
Heater
Level gauge
Plug to D1
Possible TS cooling line
Cryo
connection:
Return to SD
Inlet
Lhe
CS
Return TS E’H
2
Liquid level
MgB2-NbTi splices
Integration reservation
Concrete
Shaft
Cryogenic Considerations and Initial Feedback from Cryogenics Group
Points raised by Cryogenics Group
Increase the cross-section of
GHe
and
LHe
interface by factor of 4
Avoid
LHe
volume below the sub-cooled region at D1 plug
Slide131.3 m
A
modest vapour space in the range for level control
A height of 250mm and a diameter of 500mm
Level control within ±125mm
Additional vapour spaces bluff-off/heater extension
cryolines
(50-100mm ID)
Total cross-section ~ 2000cm
2 At a continuous liquid He filling rate of 42ml/s for a nominal SC-Link GHe mass flow rate of 5g/sTakes 595s or ~10min to overfill to the 125mm high margin if filled at constant rate if the heater went offThe same length of time required to recover from the overfill or reach the underfill limit if the filling is offA higher filling rate is needed to recover from underfillThe increased vapour space gives a better control dynamics even in on/off mode GHe flow in the vicinity of MgB2/NbTi splices to pass from main bath to the vapour space aboveMitigated by a large annulus for 228ml/s for GHe generated by the heater withinImpedance into the splice region needs to be optimisedDisturbance to the liquid level stability: bubbles exit at an effective velocity of ~1cm/s at 14% qualityMgB2Plug to D1Liquid levelIntegration reservationConcrete
Shaft
1.6 m
With SC-LINK led by ~
2m
LTS cables for LTS/LTS splice horizontally, it is possible to remove large vertical splice section
Enlarge to SC-Link/LTS annulus to 500mm od to increase the
LHe
volume near the liquid level
Possible to limit the 500mm od section of the annulus to about 500m high if necessary
MgB2-NbTi splices
Iterations to Accommodate Points Raised by Cryogenic Group
Slide1414
Revised DFX Concept Based on a Vertical Integration
Points raised by Cryogenics Group
The sacrifice of short LTS cables leads to further simplification for assembly
Only two small welds for the vertical sections in the LHC tunnel
Remove of separate chimneys for heater, instrumentation and burst device
Slide1515
Weld 1
Weld 2
Meeting our Android
Slide16Slide17Slide1818
That’s for now, more to do…, but have decide on which concept soon (less than a week?)Thank you for listening