Download Presentation The PPT/PDF document "PIP Update" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
PIP Update
Nov
1
9
th
2014Slide2
Agenda
Summary Update
Current Activities
Updates
Ken
Domann
- PIP Schedule and Budget
Ryan
Crawford - Anode Supplies & Transformers
Pat Sheehan - Bias Supplies / Ferrites
John
Reid / Matt
Slabaugh
- Booster RF Refurbishment
Dave
Johnson - Laser Chopper Power & Test Slide3
Update
Power switch wreaking havoc
Linac
SBK
: Progressing –
Fernanda inspecting SLAC
for certification testing
Linac LN:
Final
Fiber Amp
still being worked on – Early Nov delivery
date – Possibility to test
Linac Modulator
:
Parts for
53-cell prototype are
arriving –
high-priority to finish
Booster
Beam
:
Cogging
– plan to finish in December
Invesitgating
VIMIN fluctuations
Booster RF:
Booster
RF5 in
testing
Update from John / Matt
Station 20 – Prep underway
Stations 21 & 22 being planned – cavities should be ready in FY16
15
Hz testing
mostly on hold
Perpendicular Cavities – working on design – having regular meetings
Booster
Anode Supplies
–
update from Ryan
C
Booster
Bias supplies
–
update from Pat
Sheahan
Booster
Shielding:
TLM installed and collecting data – modules being built and will be installed
Booster Transformer:
East Install
–
update from Ryan C
Booster Absorber/Kicker:
Running
on new short kickers
New configuration with insert
Slide4
Updated October 7,
2014 by K Gollwitzer
Next one
Dec. 2?Slide5
Recent PIP Budget/News
FY15 Budget:
No issues with spending $$
now – we should be at full speed
Lab upload should be
complete – but not reported back
PIP working on RLS
for changed tasks (SBK, new cavities)Meetings to discuss transition PIP to PIP-II continue
DOE REVIEW of PIP in Jan!! Managers may give talksExpect a 1.5 – 2 day review on PIP and 700 kW plans
Good quality review committee
AAC recommendations
Proceed with the plan to replace the obsolete modulator hardware in the
Linac
.
Develop a plan that itemizes beam loss reduction steps to maintain present levels of beam losses as the intensity doubles. Keep a focus on the laser notching program to demonstrate the feasibility of the system and its reliable operation.