Download Presentation The PPT/PDF document "ELCITA Update" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
ELCITA Update
25th August 2015Slide2
Update – Estate Management
E – Toilets
8 e-toilets
operational and work order p
laced for 4 more e-toilets Under Ground Drainage SystemContract awarded for Survey and design of UGDSurvey work CompletedDesign finalized, BOQ and estimates awaited.Estate survey Technical Evaluation under progressImprovement of road geometry t WIPRO junction Civil works completed, Shifting of RMU’s under progress in consultation with WIPRO
2Slide3
4
Resurfacing
along Tech Mahindra - Hical road, Electronics city Phase II under new
projects
Along Tech Mahindra Road, Electronics City Phase
II
under new
projects
Update – Estate Management
Road Works - Completed
Permanent
Works -
CompletedSlide4
4
Along
Radha
regent
Road, Electronics City Phase I under Maintenance
Update – Estate Management
Permanent Works –
Completed
Permanent Works –
Completed
Along
Haritha
It Cross Road
, Electronics City Phase
I
under
MaintenanceSlide5
3
Installation of 4 Nos E-Toilets
-
Completed
Update – Estate Management
Permanent
Works -
Completed
Along
Shanthipura
Road
, Electronics City Phase
II
under new
projectsSlide6
6
Along
Tessolve
Road, Electronics City Phase
II under new projects
Update – Estate Management
Permanent Works –
Under Progress
Permanent Works –
Under Progress
Along
WIPRO/
Neeladri
Road
, Electronics City Phase
II
under new
projectsSlide7
7
Construction of Ar
ms Clearing Pit @ CSIF Building
– Completed
Update – Estate Management
Construction of 20 feet deep well Rainwater Harvesting Pit at Various locations
Maintenance Works
–
CompletedSlide8
8
Design, Supply, Installation, Testing, Commissioning, Operation and Maintenance of 8 KLD – SBT Sewage/ Waste water Treatment plant in Electronics City Phase – I, Bangalore - 560 100.
Update – Estate Management
Permanent Works –
CompletedSlide9
9
Rain Water Harvesting Works – Under Progress
Construction of
1Lakh Lit Capacity Rainwater
Harvesting System at Fire
Station, Electronics City Phase 1, Bangalore – 560 100,
Update – Estate Management
Supply, Installation & Commissioning of 125 KVA Diesel Generating Set at Pump House, Electronics City PHASE-I.
Permanent Works –
CompletedSlide10
10
Construction of Shelters at SWM Facility
– Under Progress
Update – Estate Management Slide11
11
Construction of RCC Culvert at Y – Junction
Construction
of RCC Culvert at Tech Mahindra
Hical Road & Doddanagamangala Junction.
Update – Estate Management
Cross Drainage Works:Slide12
12
Update – Estate Management
Sewage Treatment Plant Civil Works –
Under Progress
Design, Execution and Construction of 300KLD Conventional STP in Plot No. 3 (P) in Sy. No. 20 & 22 (P) of Konappana Agrahara Village in West Phase of Electronics City. Total Project Cost - Rs. 75,72,798/- (Including Civil & STP works)Slide13
Contracts Awarded
Proposed construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs from C-DOT to
DMart
Road Junction at Electronics City Phase 1, Bangalore - 560 100
.Proposed construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along Quasitum Road at Electronics City Phase 2, Bangalore - 560 100.Providing and laying of Asphalting using 60/70 grade bitumen from C-DOT to D-Mart Road Junction Electronics City Phase 1, Bangalore - 560 100.13Slide14
Proposal
for property inventory, asset management and development of web based e-governance GIS application software for Management of Electronic City Industrial Township Authority (ELCITA).Providing and laying of Asphalting using 60/70 grade bitumen from Wipro Avenue 4th cross to Wipro Avenue 5th cross road via Y-junction at Electronics City Phase 1, Bangalore - 560 100.
Providing and laying of Asphalting using 60/70 grade bitumen from Wipro
Gate 5 to Wipro Gate 16 at
Electronics City Phase 1, Bangalore - 560 100. Providing and laying of Asphalting using 60/70 grade bitumen from Haritha IT Park to Fire-station at Electronics City Phase 1, Bangalore - 560 100.Proposed construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along Bhavani Industries Road at Electronics City Phase 2, Bangalore - 560 100.14
Contract on AnvilSlide15
Proposed
construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along Radel Road at Electronics City Phase 1,
Bangalore - 560 100.
Proposed construction of Drains, laying of Pavers,
Kerb stones and Drain cover slabs along TCS Road at Electronics City Phase 2, Bangalore - 560 100.Proposed construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs from Fire station to Canara bank road Junction at Electronics City Phase 1, Bangalore - 560 100.Providing and laying of Asphalting using 60/70 grade bitumen from Fire station to Canara bank road Junction at Electronics City Phase 1, Bangalore - 560 100. 15
Contract on AnvilSlide16
Thank You