Download Presentation The PPT/PDF document "ELCITA UPDATE September 2016" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
ELCITA UPDATE
September 2016
Slide24
Estate Management
Skywalk
M/s
mayaPRAXIS
have submitted the draft report - Preliminary
F
easibility
S
tudy on Skywalk system for Electronics city phase 1.
E
– Toilets
16 e-toilets operational
.
Estate survey
Roads & common area survey completed for Phase 1& 2. Plot Inventory of the Industries
100
% completed
.
GIS Web Application Software Installed in ELCITA server. Testing work in progress.
Slide33
Road Works – Completed
Wipro
Neeladri
Road – Under Progress
Concrete Pavements along
Doddanagamangala
Village Road
Slide44
Drain Works – Under Progress
Drain Work along TCS Road
Drain Work towards Goa Estate
5
Drain Works – Under Progress
Kerbstone
work
for 300KLD STP Road
RCC Culvert
O
pp
MSME Building
Slide66
Drain Works – Under Progress
6KL capacity Sump in KIADB
Ecity
East Phase
Doddathogur
Drain
Slide77
Drain Works – Under Progress
Drain work at
Celstream
RCC Drain work at
Ramsoft
Road
Slide88
Drain Works – Under Progress
Sewer line work
Opp
Canara Bank.
Pavers/Drain work at Amphenol
Slide99
Drain Works – Under Progress
Drain work at Ramakrishna Hospital
SSM Drain
work
along
Rajakaluvae
to continue the Footpath
Slide1010
Drain Works – Under Progress
Drain work at JP IT Park Road
Kerbstone
Raising work at KSSIDC Complex
Slide1111
Drain Works –
Completed
Drain Work
From Wipro Gate 5 to Wipro Gate 16
Drain Work
in front of
CDac
12
Drain/Footpath Works – Completed
Removing the existing pavers & laying the new Pavers at
Salarpuria
Info Zone
Police Station Drain
Slide1313
Misc
Works – Completed
Petty Shop Removed and covered at Tech Mahindra road
Barbed Wire Fencing at Pump House
Slide1414
Misc
Works – Completed
Road Widening
from RS Electronics to Flextronics
Road Widening
at
Pumphouse
Slide1515
Misc
Works – Completed
Replacing the existing chamber cover with RCC heavy slab with
Chequer
Plate.
Slide1616
Pot Hole Filling
Works – Completed
Pot Hole filling work
Slide1717
Painting Works – Completed
Kerbstone
Painting along
Velankani
Road, HP Avenue & Wipro
Avenue etc
.,
Slide1818
Sustainability Projects
RWH works – Under Progress
SI.NO
DESCRIPTION
N
O OF PITS
STATUS
1
RAIN WATER
HATVESTING PIT
47
COMPLETED
2
RAIN WATER
HATVESTING PIT
1
WORK
IN PROGRESS
Slide1919
20 feet deep well Rainwater Harvesting Pit at Various locations
20 feet deep
well Rainwater Harvesting Pit
Slide2020
Estate Management
Contract Awarded
Providing and laying of Asphalting using 60/70 grade bitumen along
Café Corner & JP IT Park Road
MSME Entry Gate to Exit Gate for 300KLD
STP
KSSIDC Complex Road
Construction of Drains, laying of Pavers,
Kerb
stones and Drain cover slabs along
TCS Road
21
Estate Management
Contracts on Anvil
Providing House Keeping Services to ELCITA within
Ecity
Industrial Area.
Providing
Security Services
to ELCITA within
Ecity
Industrial Area.
Construction
of Concrete Drains, laying of Pavers, Kerb stones and Drain cover slabs alongXIME RoadPetrol Bunk Road & Golden Tulip RoadLandscaping work below fly over (Phase 1 & 2)
Providing UGD to connect industries in cluster 2 & 3 to the 300 KLD STP.
Construction
of 500 KLD STP in KIADB Land, Electronics City Phase 2
Slide22Thank You