/
SPES  status Safety TAC meeting SPES  status Safety TAC meeting

SPES status Safety TAC meeting - PowerPoint Presentation

altigan
altigan . @altigan
Follow
344 views
Uploaded On 2020-07-02

SPES status Safety TAC meeting - PPT Presentation

Laboratori Nazionali di Legnaro July 23 2015 Gianfranco Prete Project leader Site Acceptance Test Layout Cyclotron 70 MeV 750 m A Proton Beam Beam Dump Room A1 Room A6 ID: 793580

beam system cyclotron safety system beam safety cyclotron spes target dump isol line tis temporary level chamber control storage

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "SPES status Safety TAC meeting" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

SPES status

Safety TAC meetingLaboratori Nazionali di Legnaro July 23, 2015Gianfranco PreteProject leader

Slide2

Site Acceptance Test Layout

Cyclotron70 MeV

750

m

A

Proton

Beam

Beam

Dump

Room A1

Room A6

RoomA4

RoomA2

Slide3

Introduction to the temporary safety system for Cyclotron test Simplified access system: only a reduced area is accessible

nobody is allowed to be at -1 level during test high shielding doors installed Radiological survey system: n-g monitors already available at LNL will be used temporary data acquisition system is under developing Cyclotron interlocks: BEST safety system cyclotron interlocks used (SIL3 contactors)Beam line interlocks: vacuum, overcurrent, beam collimators Beam dump interlocks: Beam Dump hot spot temperature, cooling water pressure, mass flow rateTemp. Safety control system: Standard PLC-based system

DOC_00000033_SATSS

Slide4

Temporary Safety system for cyclotron Site Acceptance Test

Start of the cyclotron operation: injection October 2015Low energy commissioning (<1MeV): November High energy commissioning: December High power commissioning: February 2016Development of a temporary safety system:How do you assess our approach? Do we have the appropriate level of care?Are we considering all the critical elements?Is the work sufficiently well coordinated?Are the human resources

adequate

?

QUESTIONS TO THE SSTAC:

Slide5

Presentation of speakersSafety Aspects of the Cyclotron Commissioning and SAT (Augusto Lombardi)

description of the cyclotron operation with main reference to the cylotron protection and safety systemThe SPES High Power Beam Dump (Juan Esposito)Status of the design for the 52kW beam dump. Thermomechanics, radioactivity and shieldingSafety Analysis on the Beam

Dump

(

Pasquale Luca de Ruvo

)

Cooling system and critical aspects.

Beam dump safety system

Slide6

The Temporary Safety System Structure (Carlo Roncolato)Description of the safety system for cyclotron SAT. Procedures for development and installation

Temporary Safety Control System for the SPES (Jesus Vasquez)PLC implementationTemporal Safety Control SystemVentilation

Beam dumper

Radiation monitors

Gas exhaust radiation monitor

Redundant “ready” status

Radioprotection Aspects

(

Demetre Zafiropoulos

)

General aspects of SPES radioprotection

Improvement on radioprotection analisis

Safety documentation

Slide7

Organization for cyclotron

Site Acceptance TestIn charge to WP_B5 Cyclotron: A.Lombardi, M.Maggiore, D.Campo, L.PranoviSystem integration: C. RoncolatoRadioprotection WP_B2: D.Zafiropoulos, L.Sarchiapone Safety analysis WP_B2: J.Esposito, L.deRuvo, D.Benini

Beam dump development working group

:

J

. Esposito

, A. Andrighetto, P. Mastinu, M. Maggiore,

A.Monetti, E.Boratto

Supervisors: D.Zafiropoulos, A.LombardiTemporary Safety Control system WP_B4: J.VasquezExternal companies

involved: installation, sub-system development

of the radiation

survey , beam dump safety control system

Slide8

SPES project status and items related to safety

Slide9

ISOL bunker 1

ISOL bunker 2Cyclotron Applications HRMS

1+ RIB to ALPI

10kW UCx Direct Target: 10

13

f/s

Slide10

SPES Facility Layout

ALPI

Tandem

~ 54 x 67 m

2

CB

NC RFQ

Exp. Halls

1&2

Exp. Hall 3

New infrastructure for:

cyclotron

RIB (Radioactive Ion Beam)

application facility

Slide11

Power supply room

RF amplifiersCyclotron and beam line PSCyclotron consolleInside the building: upper level

Slide12

Plant area (on top of cyclotron vault)

Control roomArea for ISOL infrastructures (on top of ISOL bunker)

Vertical access to TIS

Inside the building: upper level

Slide13

2013

20142015

II

III

I

II

III

I

II

III

Final Assembly and Testing

Factory Commissioning

Disassembly

and Shipping

Installation at LNL

Commissioning at LNL

SPES: Cyclotron Schedule (2013-2015)Inside the building: level -1

Slide14

MAIN TENDERS

Vacuum systems

ALPI

New Cyclotron Building

Existing Building

RFQ

1+ Beam transport

ISOL production

n+ Beam transport

HRMS

CB

LARAMED

NEPIR

Evaluated construction cost: ~50 M€

2010-2012

2015

2013-2014

2016

2017

ISOL target Cyclotron and Building

Laser source

Charge Breeder, n+beam transport

Safety, UCxLab,

Infrastructures, RFQ1+beam line, ISOL systemHigh Resolution Mass Separator

18,5 M€

8,6 M€

12,9 M€

8

,2 M€

2

,3 M€

Slide15

Other work in progress, beyond the cyclotron installation and commissioning

Slide16

Transport Line to SPES RFQ

1+ Stable Sourcen+ Magnetic LineRFQMass SeparatorCB

1+ RIB line

M.Comunian, L.Bellan, A.Russo

Safety item: maintenance of the CB plasma chamber

Slide17

Exotic Beam reacceleration

1+ Stable Source

Mass Separator

Charge Breeder

1+ RIB

N+ RIB

2x electrostatic quadr. Triplets

4x electrostatic quadrupoles

4x magnetic dipoles

6x mag. Quadr. Triplets

3x mag. Solenoids

10x mag. Steerers (ALPI)

10x

mag. Quadr.

Triplets (ALPI)

Tender for beam line and mass separator: 1.5M€

Slide18

Validation of the SPES-CB

Charge Breeder Beams:

Global capture up to 90%

!

Selected beam

EFFICIENCY*

[%]

ION

Q

SPES req

Best LPSC

SPES-CB

Cs

26

5

8,6

11,7

Xe

20

10

10,911,2Rb19≥ 56,57,8Ar8

≥ 1016,215,2*results obtained for the same 1+ injected current

Ar

8+

:

ε

norm,rms

~

0,03*

π

*mm*mrad (96%)

Efficiency

~

15%

τ

CB

~

80 ms

LPSC-Grenoble

April 4

th

, 2015

1+ Beam

N

+ Beams

A.Galatà

Slide19

Other SPES Safety aspects being investigatedNot

included in your review today

Slide20

RAD-HARD

versionWG-05

Off-line FE

On-line FE

Critical materials

Teflon with glass fibres -> alumina

Polyethylene

->

peek

Viton

O-rings -> EPDM/Indium

Plastic cable insulator -> air (close the target)Normal motors -> RAD HARD motors

On-

Line

Front End

fast connectors

Slide21

SPES handling system

Horizontal handling system

A two cartesian axis system mounted onto an AGV unit allows the handling and transfer of the TIS.

Test bench handling

A test-bench Front End coupling table

allows to

verify the TIS connection /disconnection from proton and RIB beam lines.

A tool to disconnect the puller was developed too.

Coupling table

Puller removing system

Once per year it is expected to change the puller, an highly activated component.

The handling system is equipped with a tool able to extract the puller and to store it in a shielded box.

TIS

Slide22

Comparison Old set-up

N

ew set-up

(taking into account the SAC suggestions)

Storage of several 700 kg of lead box containing

the target chamber

Storage of the target chamber (40 kg) inside

many lead boxes

TIS storage system

3 rows x 10 boxes x 2 layers = 60

Storage locations

Slide23

A

n acceptable level of radiation dose is achievable, with values always below 20 µSv/h in the corridor.An optimized thickness of Lead vs. concrete of walls is ongoing to study.Results have to be validated by RP service. Target repositoryDose rate evaluation

corridor

lead

concrete

ceiling

s

hielding under evaluation

Slide24

CLEAN CHEMISTRY LABORATORY

WALL

DOOR

STORAGE (semi finished products and chemicals)

OFF-LINE IONIZATION LABORATORY

STORAGE (TIS system and TIS chamber)

HIGH TEMPERATURE LABORATORY

MECHANICAL WORKSHOP AND ASSEMBLY LABORATORY

TIS SYSTEM CHAMBER

TRANSFER DEVICES

≈ 23 m

2

≈ 17 m

2

≈ 49 m

2

≈ 10 m

2

≈ 22 m

2

≈ 49 m

2

≈ 28 m

2

≈ 31 m

2

≈ 45 m

2

HOT CELL (2 accesses)

HOT CELL LAB

UCx

LAB (characterization/transport)

CHANGING ROOM

≈ 65 m

2

UCx

LAB (production/storage)

Top of ISOL bunker

LEVEL +1

Hot cell for target inspection and components maintainance

R

adioactive materials enter from back

Laboratory for ISOL target preparation

Slide25

≈ 28 m

2

≈ 31 m

2

≈ 65 m

2

TIS SYSTEM CHAMBER

HOOD/GLOVE BOX

CARBURIZATION FURNACE

CARBURIZATION CHAMBER WITH

UCx

CONDITIONING FURNACE

GRAPHITE BOX WITH

UCx

PEOPLE/CHAMBER (POSSIBLY CONTAMINATED) INTERSECTION ZONE

HOOD/GLOVE BOX/REPOSITORY FOR RAW MATERIALS/WASTE

CHARACTERIZATION

DEVICES (XRD

, SEM, PICNOMETRY, BET, POROSIMETER, LASER DIFFRACTION, ETC.)

PRODUCTION DEVICES (MILL, PRESS, ETC.)

≈ 45 m

2

UCx production Laboratory

Under design detailed operation analisis and tender for construction

Slide26

WP_B1, WP_B2, WP_B6 & WP_B7 (Gramegna, Valiente, Bermudez, Sarchiapone, Monetti, Comunian, Bellan)

Mass selection and radiactivity distribution in the SPES transport beam lineHotspot\Dose@1 s (beam) @10 days (beam)

@30 days (beam)

@180 days (beam)

@365 days (beam)

90° dipole

69 Sv/h (135 I)

4.0 Sv/h (135 I)

0.98 Sv/h (135 I)

0.14 Sv/h (94Kr)

0.02 Sv/h (94Kr)

HRMS4.6 Sv/h (94 Kr)

0.02 Sv/h (132 Sn)0.003 Sv/h (132 Sn)

0.003 Sv/h (132 Sn)

0.0025 Sv/h (132 Sn)Charge Breeder (CB) (with HRMS off)

5 Sv/h (138 Xe)0.14 Sv/h (132 Sn

)0.003 Sv/h (134 Sn)

0.003 Sv/h (132 Sn-137Te)0.0025 Sv/h (134 Sn)Radioactivity at the hotspots (considering the source point):132Sn radioactivity at 90° Dipole along 1 year of cooling down

Slide27

Radiologic survey system

Cyclotron and beam lines

ISOL target

ventilation

Target Cooling system

Access Control System

SPES safety system

A SIL3 safety system is under development

Simplified system ready in October for cyclotron test

Slide28

LEGENDA

Rivelatore Full Body

Materiale

radiattivo

a

ccesso con

autorizzazione speciale

a

ccesso con autorizzazione standardAccess from NORTH gate

Zona di

Decontaminazione(sottoscala)

Tornello per ingresso

Con autorizzazione a badge

Montacarichi

Spogliatoio

e zona di

transito

Ingresso materialeReady for temporary system

Lift for materials

Slide29

Back to today safety assessment

Slide30

SATSS: Safety system for SAT See talks: Carlo, Juan, Jesus, Luca

Access control and radiation surveyCyclotron Interlock

Beam dump

Cooling system

Slide31

ConclusionsThe SPES cyclotron is under installation and will be soon ready for testA temporary safety system is under development to operate in a safe way

In the following talks we present the status of the systemWith this meeting we ask for your opinion/suggestions on the work we are doing.Development of a temporary safety system:How do you assess our approach? Do we have the appropriate level of care?Are we considering all the critical elements?Is the work sufficiently well coordinated?

Are the human

resources

adequate

?

QUESTIONS TO THE SSTAC: