Laboratori Nazionali di Legnaro July 23 2015 Gianfranco Prete Project leader Site Acceptance Test Layout Cyclotron 70 MeV 750 m A Proton Beam Beam Dump Room A1 Room A6 ID: 793580
Download The PPT/PDF document "SPES status Safety TAC meeting" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
SPES status
Safety TAC meetingLaboratori Nazionali di Legnaro July 23, 2015Gianfranco PreteProject leader
Slide2Site Acceptance Test Layout
Cyclotron70 MeV
750
m
A
Proton
Beam
Beam
Dump
Room A1
Room A6
RoomA4
RoomA2
Slide3Introduction to the temporary safety system for Cyclotron test Simplified access system: only a reduced area is accessible
nobody is allowed to be at -1 level during test high shielding doors installed Radiological survey system: n-g monitors already available at LNL will be used temporary data acquisition system is under developing Cyclotron interlocks: BEST safety system cyclotron interlocks used (SIL3 contactors)Beam line interlocks: vacuum, overcurrent, beam collimators Beam dump interlocks: Beam Dump hot spot temperature, cooling water pressure, mass flow rateTemp. Safety control system: Standard PLC-based system
DOC_00000033_SATSS
Slide4Temporary Safety system for cyclotron Site Acceptance Test
Start of the cyclotron operation: injection October 2015Low energy commissioning (<1MeV): November High energy commissioning: December High power commissioning: February 2016Development of a temporary safety system:How do you assess our approach? Do we have the appropriate level of care?Are we considering all the critical elements?Is the work sufficiently well coordinated?Are the human resources
adequate
?
QUESTIONS TO THE SSTAC:
Slide5Presentation of speakersSafety Aspects of the Cyclotron Commissioning and SAT (Augusto Lombardi)
description of the cyclotron operation with main reference to the cylotron protection and safety systemThe SPES High Power Beam Dump (Juan Esposito)Status of the design for the 52kW beam dump. Thermomechanics, radioactivity and shieldingSafety Analysis on the Beam
Dump
(
Pasquale Luca de Ruvo
)
Cooling system and critical aspects.
Beam dump safety system
Slide6The Temporary Safety System Structure (Carlo Roncolato)Description of the safety system for cyclotron SAT. Procedures for development and installation
Temporary Safety Control System for the SPES (Jesus Vasquez)PLC implementationTemporal Safety Control SystemVentilation
Beam dumper
Radiation monitors
Gas exhaust radiation monitor
Redundant “ready” status
Radioprotection Aspects
(
Demetre Zafiropoulos
)
General aspects of SPES radioprotection
Improvement on radioprotection analisis
Safety documentation
Slide7Organization for cyclotron
Site Acceptance TestIn charge to WP_B5 Cyclotron: A.Lombardi, M.Maggiore, D.Campo, L.PranoviSystem integration: C. RoncolatoRadioprotection WP_B2: D.Zafiropoulos, L.Sarchiapone Safety analysis WP_B2: J.Esposito, L.deRuvo, D.Benini
Beam dump development working group
:
J
. Esposito
, A. Andrighetto, P. Mastinu, M. Maggiore,
A.Monetti, E.Boratto
Supervisors: D.Zafiropoulos, A.LombardiTemporary Safety Control system WP_B4: J.VasquezExternal companies
involved: installation, sub-system development
of the radiation
survey , beam dump safety control system
Slide8SPES project status and items related to safety
Slide9ISOL bunker 1
ISOL bunker 2Cyclotron Applications HRMS
1+ RIB to ALPI
10kW UCx Direct Target: 10
13
f/s
Slide10SPES Facility Layout
ALPI
Tandem
~ 54 x 67 m
2
CB
NC RFQ
Exp. Halls
1&2
Exp. Hall 3
New infrastructure for:
cyclotron
RIB (Radioactive Ion Beam)
application facility
Slide11Power supply room
RF amplifiersCyclotron and beam line PSCyclotron consolleInside the building: upper level
Slide12Plant area (on top of cyclotron vault)
Control roomArea for ISOL infrastructures (on top of ISOL bunker)
Vertical access to TIS
Inside the building: upper level
Slide132013
20142015
II
III
I
II
III
I
II
III
Final Assembly and Testing
Factory Commissioning
Disassembly
and Shipping
Installation at LNL
Commissioning at LNL
SPES: Cyclotron Schedule (2013-2015)Inside the building: level -1
Slide14MAIN TENDERS
Vacuum systems
ALPI
New Cyclotron Building
Existing Building
RFQ
1+ Beam transport
ISOL production
n+ Beam transport
HRMS
CB
LARAMED
NEPIR
Evaluated construction cost: ~50 M€
2010-2012
2015
2013-2014
2016
2017
ISOL target Cyclotron and Building
Laser source
Charge Breeder, n+beam transport
Safety, UCxLab,
Infrastructures, RFQ1+beam line, ISOL systemHigh Resolution Mass Separator
18,5 M€
8,6 M€
12,9 M€
8
,2 M€
2
,3 M€
Slide15Other work in progress, beyond the cyclotron installation and commissioning
Slide16Transport Line to SPES RFQ
1+ Stable Sourcen+ Magnetic LineRFQMass SeparatorCB
1+ RIB line
M.Comunian, L.Bellan, A.Russo
Safety item: maintenance of the CB plasma chamber
Slide17Exotic Beam reacceleration
1+ Stable Source
Mass Separator
Charge Breeder
1+ RIB
N+ RIB
2x electrostatic quadr. Triplets
4x electrostatic quadrupoles
4x magnetic dipoles
6x mag. Quadr. Triplets
3x mag. Solenoids
10x mag. Steerers (ALPI)
10x
mag. Quadr.
Triplets (ALPI)
Tender for beam line and mass separator: 1.5M€
Slide18Validation of the SPES-CB
Charge Breeder Beams:
Global capture up to 90%
!
Selected beam
EFFICIENCY*
[%]
ION
Q
SPES req
Best LPSC
SPES-CB
Cs
26
≥
5
8,6
11,7
Xe
20
≥
10
10,911,2Rb19≥ 56,57,8Ar8
≥ 1016,215,2*results obtained for the same 1+ injected current
Ar
8+
:
ε
norm,rms
~
0,03*
π
*mm*mrad (96%)
Efficiency
~
15%
τ
CB
~
80 ms
LPSC-Grenoble
April 4
th
, 2015
1+ Beam
N
+ Beams
A.Galatà
Slide19Other SPES Safety aspects being investigatedNot
included in your review today
Slide20RAD-HARD
versionWG-05
Off-line FE
On-line FE
Critical materials
Teflon with glass fibres -> alumina
Polyethylene
->
peek
Viton
O-rings -> EPDM/Indium
Plastic cable insulator -> air (close the target)Normal motors -> RAD HARD motors
On-
Line
Front End
fast connectors
Slide21SPES handling system
Horizontal handling system
A two cartesian axis system mounted onto an AGV unit allows the handling and transfer of the TIS.
Test bench handling
A test-bench Front End coupling table
allows to
verify the TIS connection /disconnection from proton and RIB beam lines.
A tool to disconnect the puller was developed too.
Coupling table
Puller removing system
Once per year it is expected to change the puller, an highly activated component.
The handling system is equipped with a tool able to extract the puller and to store it in a shielded box.
TIS
Slide22Comparison Old set-up
N
ew set-up
(taking into account the SAC suggestions)
Storage of several 700 kg of lead box containing
the target chamber
Storage of the target chamber (40 kg) inside
many lead boxes
TIS storage system
3 rows x 10 boxes x 2 layers = 60
Storage locations
Slide23A
n acceptable level of radiation dose is achievable, with values always below 20 µSv/h in the corridor.An optimized thickness of Lead vs. concrete of walls is ongoing to study.Results have to be validated by RP service. Target repositoryDose rate evaluation
corridor
lead
concrete
ceiling
s
hielding under evaluation
Slide24CLEAN CHEMISTRY LABORATORY
WALL
DOOR
STORAGE (semi finished products and chemicals)
OFF-LINE IONIZATION LABORATORY
STORAGE (TIS system and TIS chamber)
HIGH TEMPERATURE LABORATORY
MECHANICAL WORKSHOP AND ASSEMBLY LABORATORY
TIS SYSTEM CHAMBER
TRANSFER DEVICES
≈ 23 m
2
≈ 17 m
2
≈ 49 m
2
≈ 10 m
2
≈ 22 m
2
≈ 49 m
2
≈ 28 m
2
≈ 31 m
2
≈ 45 m
2
HOT CELL (2 accesses)
HOT CELL LAB
UCx
LAB (characterization/transport)
CHANGING ROOM
≈ 65 m
2
UCx
LAB (production/storage)
Top of ISOL bunker
LEVEL +1
Hot cell for target inspection and components maintainance
R
adioactive materials enter from back
Laboratory for ISOL target preparation
Slide25≈ 28 m
2
≈ 31 m
2
≈ 65 m
2
TIS SYSTEM CHAMBER
HOOD/GLOVE BOX
CARBURIZATION FURNACE
CARBURIZATION CHAMBER WITH
UCx
CONDITIONING FURNACE
GRAPHITE BOX WITH
UCx
PEOPLE/CHAMBER (POSSIBLY CONTAMINATED) INTERSECTION ZONE
HOOD/GLOVE BOX/REPOSITORY FOR RAW MATERIALS/WASTE
CHARACTERIZATION
DEVICES (XRD
, SEM, PICNOMETRY, BET, POROSIMETER, LASER DIFFRACTION, ETC.)
PRODUCTION DEVICES (MILL, PRESS, ETC.)
≈ 45 m
2
UCx production Laboratory
Under design detailed operation analisis and tender for construction
Slide26WP_B1, WP_B2, WP_B6 & WP_B7 (Gramegna, Valiente, Bermudez, Sarchiapone, Monetti, Comunian, Bellan)
Mass selection and radiactivity distribution in the SPES transport beam lineHotspot\Dose@1 s (beam) @10 days (beam)
@30 days (beam)
@180 days (beam)
@365 days (beam)
90° dipole
69 Sv/h (135 I)
4.0 Sv/h (135 I)
0.98 Sv/h (135 I)
0.14 Sv/h (94Kr)
0.02 Sv/h (94Kr)
HRMS4.6 Sv/h (94 Kr)
0.02 Sv/h (132 Sn)0.003 Sv/h (132 Sn)
0.003 Sv/h (132 Sn)
0.0025 Sv/h (132 Sn)Charge Breeder (CB) (with HRMS off)
5 Sv/h (138 Xe)0.14 Sv/h (132 Sn
)0.003 Sv/h (134 Sn)
0.003 Sv/h (132 Sn-137Te)0.0025 Sv/h (134 Sn)Radioactivity at the hotspots (considering the source point):132Sn radioactivity at 90° Dipole along 1 year of cooling down
Slide27Radiologic survey system
Cyclotron and beam lines
ISOL target
ventilation
Target Cooling system
Access Control System
SPES safety system
A SIL3 safety system is under development
Simplified system ready in October for cyclotron test
Slide28LEGENDA
Rivelatore Full Body
Materiale
radiattivo
a
ccesso con
autorizzazione speciale
a
ccesso con autorizzazione standardAccess from NORTH gate
Zona di
Decontaminazione(sottoscala)
Tornello per ingresso
Con autorizzazione a badge
Montacarichi
Spogliatoio
e zona di
transito
Ingresso materialeReady for temporary system
Lift for materials
Slide29Back to today safety assessment
Slide30SATSS: Safety system for SAT See talks: Carlo, Juan, Jesus, Luca
Access control and radiation surveyCyclotron Interlock
Beam dump
Cooling system
Slide31ConclusionsThe SPES cyclotron is under installation and will be soon ready for testA temporary safety system is under development to operate in a safe way
In the following talks we present the status of the systemWith this meeting we ask for your opinion/suggestions on the work we are doing.Development of a temporary safety system:How do you assess our approach? Do we have the appropriate level of care?Are we considering all the critical elements?Is the work sufficiently well coordinated?
Are the human
resources
adequate
?
QUESTIONS TO THE SSTAC: