/
SPS YETS 2015/2016 Planning meeting ( SPS YETS 2015/2016 Planning meeting (

SPS YETS 2015/2016 Planning meeting ( - PowerPoint Presentation

basidell
basidell . @basidell
Follow
343 views
Uploaded On 2020-07-03

SPS YETS 2015/2016 Planning meeting ( - PPT Presentation

No13 270116 David Mcfarlane ENMEF DMcfarlane 1 Lift Maintenance January 2016 2 ENMEF DMcfarlane Still waiting for the February dates Water Availability Water StopRestart dates BA1 BA80 ID: 793926

sps mef 2016 mcfarlane mef sps mcfarlane 2016 sera february access cern pont eca5 edms roulant les document safety

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "SPS YETS 2015/2016 Planning meeting (" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

SPS YETS 2015/2016Planning meeting (No.13)27/01/16

David Mcfarlane

EN-MEF D.Mcfarlane

1

Slide2

Lift Maintenance January 20162

EN-MEF D.Mcfarlane

Still waiting for the February dates!!!!!!!

Slide3

Water AvailabilityWater Stop/Restart dates BA1 – BA80

BA1 – 17/12/15 to 01/02/16BA2 – 18/12/15 to 01/02/16 (EG restrictions)

BA3 – 17/12/15 to 01/02/16 (EG restrictions)BB3 – 18/12/15 to 01/02/16

BA4 – 18/12/15 to 18/01/16 (Main Magnet for Kickers),

remaining circuits 01/02/16 (EG restrictions to 08/02/16)

BA5 – 18/12/15 to 01/02/16

BA6 – 18/12/15 to 01/02/16

BA80 – 14/12/15 to 07/03/16

Slide4

Test AUG/ Access Tests(Access will be blocked)

Location

AUG

test

Access tests

SPS

17

th

December (06:00 to 07:00)

18

th

December

(15:00 to 17:00)

BA111th February1st February (AM)BA219th January1st February (PM)BA312th February2nd February (AM)BA4ECX4TAG4213th January2nd February (PM)3rd February (AM)3rd February (PM)BA5ECX5/ECA58th February4th February (AM)4th February (PM)BA620th January5th February (AM)BA7TT614th February8th February (AM)8th February (PM)BA8023rd February9th February (AM)

4

EN-MEF D.Mcfarlane

Slide5

No access to TA40/TT40/TJ8 and TAG42 today!Veuillez prendre connaissance de la note de coupure « ELECTRICITE - SPS – BB4 ECA4 (BATIMENT 921) – Réseau Secours – Remplacement de l’armoire électrique ESD1/EC4 »

prévue

le mercredi 27 janvier 2016 de 7h30 à 18h00 

https://edms.cern.ch/ui/file/1573412/1/ENNC_EL_2016_027.pdf

EN-MEF D.Mcfarlane

5

Slide6

Le pont PR520 au BA3Le pont PR520 au BA3 (travée côté atelier 929) va être remplacé la semaine prochaine suivant le planning ci-dessous établi par JP

Granchelli (EN-HE-HM) :

 1-Les travaux se dérouleront du Lundi 25 Janvier 14h00 au Vendredi 29 Janvier 2016.

 

2-Les opérations de grutage se dérouleront le mardi 26 Janvier 2016.

La grue sera installée sur le parking du 929 et le parking du 905 (BB3) sera également fermé pour la mise en place des contrepoids de la grue. Voir document « balisage 905-929 » en pièce jointe. LE PARKING SERA INACCESSIBLE LES 25 et 26 JANVIER

 

3-La coupole du lanterneau au-dessus du PR520 sera déposé le mardi 26 Janvier à partir de 8h00

(entreprise

Schultess

)

.

 

4-Dépose ancien pont roulant PR520.L’ancien pont roulant PR520 sera déposé avec la grue 220T  CERN.Elle sera positionné à l’extérieur et l’élingue de levage sera introduite au-dessus du pont roulant par le lanterneau de la toiture.Le pont roulant PR520 sera déposé sur deux remorques, ils sera sanglé et évacué à l’extérieur, à l’extérieur le pont roulant sera déchargé par la deuxième grue 55T fournie par le CERN. L’aire de parking entre le BA3 et la CCC sera également bloquée pour cette deuxième grue (voir document « balisage CCC »). 5-Pose du nouveau pont roulant PR601Le nouveau pont roulant PR601 sera chargé à l’extérieur sur deux remorques, et introduit dans le bâtiment, sous l’ouverture en toiture.L’élingue de la grue 220T sera descendu par l’ouverture en toiture au-dessus de la poutre du pont roulant  PR601.Le nouveau pont roulant PR601 sera élingué et hissé sur la voie de roulement. Lors des deux opération de manutention, pour éviter le palan auxilaire, situé sous la travée intérieur, les poutres devront pivoté de 45°.  Je vous demanderais de bien vouloir éviter le passage entre le BA3 et le BB3/929  entre lundi après-midi et mardi soir. Aucun travail ne doit être effectué dans l’installation Siemens pendant les phases de grutage des ponts.Deux nacelles élévatrices seront ensuite placées sur la dalle béton pour permettre les derniers travaux de modification de structures et de raccordement électrique du pont. Le passage ne sera pas bloqué mais des ouvriers travailleront en hauteur (casque à prévoir si nécessaire).  Merci d’avance pour votre compréhension et pour respecter les consignes sur place.EN-MEF D. Mcfarlane6

Slide7

EN-MEF D.Mcfarlane7

Slide8

Magnet change campaignEN-MEF D.Mcfarlane

8

Position

Sextant

Aimant sorti

Nouvel

aimant

date installation

51330

5-

MBB 44

MBB 199

05/01/2016328103+QF 87QM 16506/01/2016409304-MBB 83MBB 28906/01/2016224302+MBA 244MBA 16207/01/2016226702+MBB 82MBB 08807/01/2016228302+MBA 301MBA 15907/01/2016125101+QD 152QM 14008/01/2016108101-QF 53QM 15511/01/2016101101-QD 173QM 158

11/01/2016

53510

5+

QD 127

QM 027

12/01/201662210

6+

QF 3

QM 018

12/01/2016

10850

1-

MBA 5

MBA 354

14/01/2016

10130

1-

MBB 381

MBB 235

14/01/2016

42230

4+

MBA 97

MBA 17915/01/2016210706 MDSV 007 15/02/2016211606 QTS 053 15/02/2016

Slide9

Open issues from VacuumEN-MEF D.Mcfarlane

9

The TT20 magnets are still foreseen for the last week of the YETS. One magnet is fully ready, the second one is still undergoing tests of the magnet coils. So as the 2 magnets are in 2 different sector, we could do one of the 2 this coming Friday and the second one on the 10-11 of February (to gain one weekend of

pumpdown

before the end of the YETS). If there is no possibility in doing one of the two this week, then If we could at least do both of them on the 10

th

of February it would be great. I know transport and Jeremie will hate me :D;

TT20 Cherenkov Detector: as you read in the mail exchange, the installation is postponed to a later stage, as they found a problem in the positioning system of the crystal. A fast solution would have taken anyhow 10 days of work, so unfortunately we had to cancel it;

Water on ion pumps connectors: I guess you have been through some mail exchange for water spilled on our equipment: please underline that more care is needed, F.

Daligaut

had to change the connectors of few pumps that were sparking because of the presence of water;

I sent an email to the LHC transport guys with the list of things to be moved across the QRL in point 2 for the TED intervention, I had no reply yet. So the strategy is: we will try to move all needed equipment from P2. In case of need during the installation we will ask for opening the door between SPS and LHC.

Slide10

Access into ECA5EN-MEF D.Mcfarlane

10

After discussion between BE-safety Unit, GS-ASE and E. Carlier, it was decided that following your

transparencies

on ECX5/ECA5,

 after week

2

(4th Jan.2016, shielding will be removed) until end of YETS 15/16, all people who must enter in ECA5 will access by BA5.In order to keep the patrol and the integrity of the area safe, the lift in ECA5 should not be used during this period, only for evacuation.

By accessing through BA5, we can guarantee that people are

registered

and they have their SPS safety courses.

A security panel with a chain should be installed at the bottom of the lift : "

Do not use the lift, only for evacuation" by the TSO (Franck Bais)If one of the 3 ECA5 doors at the top of the cavern is forced, the CSA will re-arm it at the end of the day.

Slide11

ECX5/ECA5 Week 5(25th to 29

th Jan)

EN-MEF D.Mcfarlane

GS/SE

Floor drying.

No access into area.

EN/EL

De-cabling works in ECX5 and LSS5

(below passageway)

EN/EL will be working with 2 shifts. From 06:00 hrs to 22:00 hrs

Area closed to everyone except EN/EL

11

Slide12

ECX5/ECA5 Week 6(1st to 5

th Feb)

EN-MEF D.Mcfarlane

EN/HE

Start to remove waste via ECA5 if needed.

To check with GS/SE to make sure the floor is dry.

EN/EL

De-cabling works in ECX5 and LSS5

(below passageway)

EN/EL will be working with 2 shifts. From 06:00 hrs to 22:00 hrs

Area closed to everyone except EN/EL

12

Slide13

ECX5/ECA5 Week 7(8th to 12

th Feb)

EN-MEF D.Mcfarlane

EN/HE

R

emove waste & equipment via ECA5 (Mon & Tue)

ECX5 & LSS5 open

EN/EL & EN/MEF

Removal of scaffolding

EN/HE

Re-install shielding wall (Wed,

Thur

, Fri)

NO Access into ECA5 & BB5 except for transport.13EN/MEFTransport of scaffolding from BA6.

Slide14

Start-up CalendarEN-MEF D.Mcfarlane

14

Presentation from James Ridewood

Slide15

Access into the False Floors during the YETS (Update)EN-MEF D.Mcfarlane

15

Slide16

PlanningEN-MEF D.Mcfarlane

https://edms.cern.ch/document/1542997/1

16

Slide17

SRRs and ECRs: status for SPS

ECR - EDMS: 1531376

“Rename of standard vacuum chambers in SPS ring”

Author: J.A. Ferreira Somoza (TE/VSC)

Schedule: starting in 2015 (?) (mostly CAD and databases work)

EDMS Status:

In Work 

Document being prepared?.

ECR - EDMS: 1572331

“Change of Layout Names for Beam Position Detectors in TT41”

Author:

L. Jensen (BE/BI)

Schedule: Q1- 2016EDMS Status: Under Approval  Deadline: 2016-01-28 2016-01-20Sonia Bartolomé EN-MEF-DC

Slide18

SRRs and ECRs: status for SPS

ECR - EDMS: 1567571

“Removal of Helium 2K Pumping Units from the Alcove Region of SPS Point 4” Author

:

G.

Vandoni

(BE/RF) et al.

Schedule: YETS 2015-2016EDMS Status:

Released (2016-01-19)

ECR - EDMS: 1562102

“Installation of a Cherenkov Detector in TT20”

Author: S. Montesano (EN/STI)Schedule: YETS 2015-2016 EDMS Status: Released (2016-01-07) 2016-01-20Sonia Bartolomé EN-MEF-DC

Slide19

SRRs and ECRs: reminderAll changes to the machine that will impact the beam shall be documented by SRRs/ECRs:

SRR: Space Reservation Request (“light ECR”)ECR: Engineering Change Request

Templates available on:MS Word: ‘New’

‘My

Templates’

SPS https://quality.web.cern.ch/templates-requests

To be sent to:

Sonia.Bartolome@cern.ch or

ecr-configuration@cern.ch

2016-01-20

Sonia Bartolomé EN-MEF-DC

Slide20

Contractor's visit to the SPS tunnel during YETS15-16.EN-MEF D.Mcfarlane

20

If you have an external company that you would like to take into the SPS in order to prepare for some future works, then all the information you need do organise this can be found in the following document:

https://edms.cern.ch/ui/#!

master/navigator/document?D:1149472277:1149472277:subDocs

Slide21

Access rights and safety equipmentEveryone who enters the SPS

MUST have the following:

Completed the correct courses. (sir.cern.ch)

CERN

Safety

Introduction.

Electrical Safety Awareness. (19 choices)

Self Rescue Mask Training

. (4 choices)CERN – Beam Facilities.

SPS – Machine.

The

correct access

authorisation

(via EDH).Zone Code “SPS” for access into the SPSZone Code “NA_TARG” for access into BA80Zone Code “TAG41 - AWAKE (ex-CNGS) (TAG41)” for access into the old CNGS areasZone Code “SPS-KN-000” for “Autorisation conduite RTL”Zone Code “SPS-KN-001” for “SPS Shutdown Padlock” (only used during Long Shutdowns)PLEASE CHECK THAT YOUR ACCESS RIGHTS DO NOT EXPIRE AT THE END OF THIS YEAR!!!!A valid approved IMPACT. (with their name included on this IMPACT)They must know the number of this IMPACT.Safety shoes.Biocell.Electronic dosimetre.Passive dosimetre.All contractors must all have a company passive dosimetre!!!Helmet plus Light.Please note that personnel are not allowed to work in the tunnel alone!!EN-MEF D.Mcfarlane21

Slide22

Important ContactsUseful Contact Numbers

SPS Coordination TeamDavid MCFARLANE- 164247Franck BAIS – 165467

Control RoomSPS CCC – 77500TI CCC – 72201

CSA

- 62511

RP

Christophe Tromel – 163199

Angelito Herve – 163168

Nadine Conan (BA1) – 160641

Kurt Weiss (BA7) -160759

EROS Engineering Referent for Operational

Safety

Emmanuel Paulat – 163870

John Etheridge - 164647EN-MEF D.Mcfarlane22

Slide23

A.O.B.

EN-MEF D.Mcfarlane

23

Slide24

Useful websitesLink to SPS planning meetings on INDICO

http://indico.cern.ch/category/6541/

Link to the SPS planning in EDMShttps://

edms.cern.ch/document/1542997/1

Roadmap: Schedule beyond LS1

http://ls1ls2.web.cern.ch

/

Next meeting

03

/02/2016

30-7-010

EN-MEF D.Mcfarlane

24

Slide25

EN-MEF D.Mcfarlane

25