/
EE Pro-commissioning On Surface EE Pro-commissioning On Surface

EE Pro-commissioning On Surface - PowerPoint Presentation

beastialitybiker
beastialitybiker . @beastialitybiker
Follow
342 views
Uploaded On 2020-08-26

EE Pro-commissioning On Surface - PPT Presentation

Man Power Students are coming to CERN this week and next week Hardware 2 DAQ stations including DCS ready 2 Gas stations ready HV and LV power suppliers ready Infrastructure BB5 3 EEL sectors are moved to test area to be commissioned ID: 802620

commissioning dcs march april dcs commissioning april march gas power feb mdt install installation schedule plans support operations 2013

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "EE Pro-commissioning On Surface" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

EE Pro-commissioning On Surface

Man Power: Students are coming to CERN this week and next week.Hardware : 2 DAQ stations (including DCS) : ready2 Gas stations : readyHV and LV power suppliers : readyInfrastructure:BB5: 3 EEL sectors are moved to test area to be commissioned. Need to open gas linesB180: EES sector, transportation frames to be used on location. Gas lines ready

Slide2

EE Installation Schedule

https://edms.cern.ch/file/1219817/1/EE_install_11_01_2013.pdfEELA15: Feb. 21EELA01: March 5thEELA07 and EELA09 : March 8thEESA14: March 25thEESA16: March 28thEESA02: April 2ndEESA04: April 3rd

EESA12: April 5thEESA10: April 15

th

EESA08: April 16

th

EESA06: April 17th

Services:Feb

. 23

rd

to April 20

th

, no gas and alignment services before March 20

th

.

Commissioning Period: March 20

th

to May 15

th

Slide3

MDT EE installation and commissioning from DCS point of view 1/2

Software integration of EE chambers side A into DCS was done already during 2011/12 together with side C – major effort out of the way !Integration is based on pre-defined mapping (LV, HV, allocation) and information in the MDT configuration DB – some surprises to be expectedTo be done:Install few missing HV boardsVerify and properly configure all settingsProperly enable new nodes in the FSMCan Node ID to be changed for a few (known) chambers to avoid conflicts with duplicates on the bus

Adjust alarm settings gas system, activate interlocks

Commissioning and testing/verifcation

DCS operations and manpower:

To my understanding Michel‘s latest schedule forsees EEL install + commissioning 20/2 to 20/3; EES install + commissioning 18/3 to 7/5/2013

Michel‘s schedule forsees infrastructure interventions which seem to be

conflicting

No USA15 rack cooling Feb 18 to Mar 15

 VME crates off, endcap alignment off, remaining DCS partial availability (CanBus not clear, power not clear)

No power on sniffers/AUG tests, power cut: May 2-4 2013

Slide4

MDT EE installation and commissioning from DCS point of view 2/2

DCS operations and manpower continued:My idea is to leave MDT DCS untouched and operational from end of data taking to May 7. From May 7 on we will plan the major upgrade work, especially CanBus and computer replacement, migration to new OS and Can interfaces, ...: DCS fully unavailable over the summer for the detector community (after the summer, continue with development of additional tools, software, procedures, ....)My idea is to have 1 or 2 dedicated DCS experts support the EE commissining

1 „old“ and one of the „newer“ students from NTUA ?Need to plan for financial support on M&O (Ludo)

Experts‘ responsible

Support when needed – on call duty (during the week)

Spending a few hours each day in the control room during commissioning passing on DCS operations to new detector people

From Feb 25 to mid April myself will be absent from CERN, follow things from remote and guide experts if needed

Date when to finish commissioning needs to be firm, need to in the next weeks fix plans with Robert Hart, Agostino and other external people for DCS upgrade work !!

To finalise

To Tiesheng/Gerian: Please make sure you include us in the discussion and changes of plans, so far DCS was not contacted at all w.r.t. To EE commissioning plans !