/
Figure 1: The Subsea Test Valve, installed in a modified BOP cavity, i Figure 1: The Subsea Test Valve, installed in a modified BOP cavity, i

Figure 1: The Subsea Test Valve, installed in a modified BOP cavity, i - PDF document

briana-ranney
briana-ranney . @briana-ranney
Follow
418 views
Uploaded On 2016-05-15

Figure 1: The Subsea Test Valve, installed in a modified BOP cavity, i - PPT Presentation

58NovemberDecember 2006 RILLIN are apparent and Table 2 shows the Noting that the POOH times are on averings using an SSTV which can be writventionally ID: 321317

58November/December 2006 RILLIN are apparent and

Share:

Link:

Embed:

Download Presentation from below link

Download Pdf The PPT/PDF document "Figure 1: The Subsea Test Valve, install..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Figure 1: The Subsea Test Valve, installed in a modified BOP cavity, is designed to be 58November/December 2006 RILLIN are apparent, and Table 2 shows the Noting that the POOH times are on aver-ings using an SSTV, which can be writ-ventionally” (Potential Savings)Dwd = water depth (ft)DBML = depth below mudline (ft)(ft/hr)(ft/hr)a BOP test when operating in a given time to actually perform the BOP testing same whether using an SSTV or testing conventionally. When using an SSTV, the 3 shows that in 5,000 f t of water, with the drill bit 5,000 f using an SSTV to test the BOPs could Using the 5,000-ft curve as a baseline, rig rate, a single test using an SSTV in 5,000 f each required BOP test point as the savings are possible by using an SSTV required BOP testing. Although data using an SSTV may prove to be benefi-benefit from using an SSTV, particularly conditions make tripping pipe difficult.at the 2006 IADC European Well Control Variation of $ Saved PER TEST w/ DBML @ 5000' WDSemi-Submersible Average$100,000$200,000$300,000$400,000$500,000$600,000$700,000$800,000$900,0000500010000150002000025000BML (ft)Value of Time Savings $750K Da y $500K/Da $250K/Da Variation of Time Saved PER TEST w/ DBMLSemi-Submersible Average0500010000150002000025000BMLTime Savings(Hours) 1000’ WD5000’ WD 000’ WD miscBMLPOOHBMLwdtesttVDDVDDt+++=22 Figure 3 (above): In 5,000 ft of water with the drill bit 5,000 ft below the mudline, using an SSTV can save up to 12½ hrs of tripping time. Figure 4 (below): With the 5,000-ft