Fundamentals of Test & Balance PowerPoint Presentation

Fundamentals of Test & Balance PowerPoint Presentation

2015-11-25 89K 89 0 0

Description

for Engineers. Objectives. Help the CxA understand and identify challenges of the TAB Agency. Explain what can be accurately measured in the field in an HVAC system. Obtain an understanding of the proper use & limitations of TAB instrumentation. ID: 205184

Embed code:

Download this presentation



DownloadNote - The PPT/PDF document "Fundamentals of Test & Balance" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.

Presentations text content in Fundamentals of Test & Balance

Slide1

Fundamentals of Test & Balancefor Engineers

Slide2

Objectives

Help the CxA understand and identify challenges of the TAB Agency

Explain what can be accurately measured in the field in an HVAC system

Obtain an understanding of the proper use & limitations of TAB instrumentation

Promote a team approach between the CxA and TAB Agency

Assist in delivering a project to the owner meeting system design intent

Slide3

Specification Challenges

One of the most beneficial and productive parts of the Cx process is a specification and drawing review.

Utilize common sense; what is the goal or intent?

If the CxA is utilizing the project specifications to establish PFC’s and FPT’s make sure they are applicable. (Who performs their own PFC’s?)

Slide4

Specification Challenges:TAB Data

Understand what is meaningful data. Just because the specification calls for a “measurement”, that does not mean it is relevant or useful.

For example; Wet-bulb temperatures – a single point measurement is not extremely accurate and a steady state load needs to be introduced. Is this data really needed? Will this data provide a benefit to the owner? The coil should be ARI certified.

Try to think of

how data will be obtained and what data will be required

before requesting the data:

Will the requested data be

accurate

,

repeatable

and

meaningful

?

Slide5

Specification Challenges:Measurement Tolerances

Avoid ±5% tolerances

Adds cost, but not necessarily value.

May not be feasible, depending on the system and its components.

Reserve tight tolerances for special applications, not comfort cooling/heating. Keep in mind, that in Labs and ORs, the main criteria for airflow is ACH and room pressurization. Typically the room envelope dictates the amount of airflow required to maintain proper pressurization.

The TAB equipment manufacturer’s tolerances sometimes are greater than the specification tolerances.

Slide6

Specification Challenges:Marking Damper/Valve Positions

Verify that all balancing damper handles are exposed and visible on externally insulated ductwork. Do these need to be marked? If so, make sure that quadrant style damper handles with standoffs and locking devices are specified and installed so they can be clearly marked. Marking the external duct insulation is not accurate/helpful.

If valve handles required to be marked, make sure the specified and installed valve has provisions for marking. Recording the valve position in the TAB report should suffice in most situations.

Slide7

Specification Challenges:Marking Damper/Valve Positions

Slide8

Specification Challenges:Controls

Make sure that access to the control system is made available to the TAB agency and CxA. This includes any required hardware and software.

This seems to be a regional issue, not a manufacturer’s issue.

Slide9

Specification Challenges:Seasonal Testing

Make sure that the “Seasonal Testing” required is affected by the season.

Utilize the DDC system for trending data.

Typically airflows and water flows are tested at maximum flow conditions and the season does not affect the test data.

Slide10

Specification Challenges:Sheaves

Sheave changes

are NOT automatically the responsibility of the mechanical contractor or TAB agency.

It is difficult to define who is responsible -- Manufacturer, contractor, engineer? How many are required? At bid time, sheaves are an unknown cost and unknown quantity.

Sheave changes for fans should be included as an allowance in the project or handled as a

cost plus change order

.

Slide11

Specification Challenges:Domestic Water Systems

Is

domestic water

balancing required?

Most TAB equipment manufacturers prohibit the use of their equipment on potable water systems due to potential contamination and liability.

Consider having temperature sensors installed on the domestic hot water recirculation loop that can report the temperatures to the DDC system

.

Plumbing pumps, fire pumps, steam condensate pumps

: Typically cannot be accurately tested without a constant, established water flow.

Slide12

Specification Challenges:

Domestic Water Systems

Slide13

Specification Challenges:Duct Air Leakage Testing

Duct leakage testing

needs to be coordinated in the specification

Who does the testing? Define responsibilities; providing sheet metal blank offs, providing of test equipment, who signs off, etc.

How many tests are required? Define systems to be tested, etc.

Define the standard and test requirements. Test pressure, etc.

Realize there is a schedule impact

Slide14

Specification Challenges

Calibration

of instruments per manufacturer’s recommendations. (As a note, most require calibration every 2 years.)

Help promote identifying each piece of equipment (fans, AHUs, HPs, VAVs, etc.) with a

unique tag

.

Never

rely on

face dampers

for air balancing.

Slide15

Specification Challenges:Vibration & Sound Testing

If required, make sure the specification is specific about

what sound and/or vibration data is required

.

Define where readings should be taken and under what test conditions the readings should be obtained.

Slide16

Airflow Measurement & The Flow Hood

The flow hood is a proportioning device.The airflow measurement of the flow hood may have to be corrected with a “K” factor.

Slide17

Airflow Measurement & Fan Curves

Fan curves

AMCA Tested

Produced under

laboratory conditions

Free inlet

Straight discharge

Ideal traverse plane

Multiple speeds-extrapolated data

Standard temperature & pressure (STP)

Normal manufacturing tolerances

Know the

limitations

of fan curves

Slide18

Airflow Measurement & Fan Curves

ASHRAE Journal Article, November 2005

Slide19

Airflow Measurement:Traverse Locations & Alternatives

Ideal traverse plane

:

For

round duct,

AABC, AMCA & ASHRAE all identify the ideal traverse plane as

2 ½ diameters from condition

(discharge, elbow, etc.) for up to 2500 fpm. Add 1 diameter for each additional 100 fpm.

For

rectangular duct,

E

L

= (4a*b/

π

)

0.5

, where “a” & “b” are the duct dimensions.

Slide20

Example:10,000 cfm, 30” x 20” duct, 2400 fpmEL= (4a*b/π)0.5 =27.6”2 ½ * 27.6” = 69.1” 69.1” (~ 6’) straight duct required

Alternatives to Traverse:Face velocity reading of filters, coils, etc.Summation of airflows at individual outletsSummation of calibrated VAV boxes as read at the DDC computer

Airflow

Measurement:

Traverse Locations & Alternatives

Slide21

Airflow Measurement:Equipment Considerations

Can outdoor air be measured to AHU?

Is there enough ductwork for a proper traverse?

Does unit configuration allow for proper measurement (damper configuration)?

Roof Top Units

Outdoor air measurements are not possible

.

Static pressure profile of RTU is not practical unless factory “ports” are installed.

Slide22

Airflow Measurement:Airflow Monitoring Stations

The AFMS –

Requires calibration and maintenance

Requires filtered air

Will the AFMS work properly in the installed location?

Is the velocity profile acceptable?

Will the AFMS work at minimum airflow, but function improperly at maximum airflow or vice-versa?

Will the control damper create turbulence and measurement issues?

Slide23

VAV Systems and Return Air Balancing

Slide24

Water Flow Measurement:Pump Curves

Design Requirements: 800 gpm @ 68’9” Impeller, 20 hp motor, 5BC,1750 rpm (Point 1)Field Measurements:Shutoff ΔP = 73’ (Point 2)Operating ΔP = 70.0’Results:Actual: 700 gpm w/9” imp12.5% below design Flat Pump Curve – Hard to interpolate.Utilize measured flows at terminals or branches to determine pump total.

Slide25

Water Flow Measurement:Pump Curves

Design Requirements: 800 gpm@ 68’10-3/8” Impeller, 20 hp motor, 4E, 1750 rpmField Measurements: Shutoff ΔP = 104’ Operating ΔP = 72’Results:Actual: 775 gpm w/10-3/8” imp3.1% below design Steep Pump Curve – Immediate Resolution.

Slide26

Pump Flow Measurement

Provide test ports/pump taps at the pumps (Extend outside of insulation).Provide a flow measuring device at the pumpFixed orifice type device preferred, use Multi-Purpose Valves with caution.

Slide27

Water Flow Measuring Stations: Sizing

Flow measuring stations need to be sized to allow for a measurable and useful pressure drop.

Too often the flow measuring station is too large and the pressure drop is too low to be useful or accurate. Several balancing valve manufacturers will have different orifices available so the valve is sized for flow quantity.

The use of Multi-Purpose Valves for total pump flow measurement is typically not accurate

Typically sized line size and not for flow (oversized)

Location is not ideal, need 5 pipe diameters before and after the valve.

Slide28

Water Flow Measuring Stations: Strainer Effect

¾” Balancing Valve 50% Open

¾” Balancing Valve 25% Open

Slide29

Water Flow Measuring Stations:Strainer Effect

Slide30

Water Flow Measurement:Automatic Flow Limiting Devices

These devices do not eliminate water balancing.

Ideal for fan coil units, unit ventilators, heat pumps, VAV reheat coils and areas where access to valves is limited (

actual pressure readings might not be obtained for each auto-flow

).

Factory-installed piping kits frequently do not provide access to the ports!!!

Slide31

Water Flow Measurement:Factory-Piped Balancing Valves

Slide32

Water Flow Measurement: AFLD Installation

Slide33

Testing a Water System with Diversity

Repeating water flow measurements in a system with diversity is very difficult. Several considerations are required:

How was the system set up for testing?

What data is required to be reported?

How is the system currently operating?

Slide34

Testing a Water System with Diversity

Understand the goals of the TAB Process & FPT’s in a system with diversity

Verify pump performance

Make sure that all coils/elements can provide heating/cooling

Establish the differential pressure operating setpoint

Set up system to operate as efficiently as possible – Obtain water flow to the coil/element with the most resistance without creating excessive resistance in the system (let the control valve do the

work)

Slide35

Access Challenges

Proper clearance and access must be provided to all dampers, valves, equipment, etc.

Sheetrock ceilings, architectural features, etc.

Locate devices in the corridors outside of OR’s, classrooms, etc.

Access to outlets, dampers, etc. in theatre type seating areas. How will this be accomplished? AHU is typically not in operation when scaffolding is installed.

Slide36

Scheduling Challenges

There needs to be enough time allowed in the schedule for the TAB & Cx work to be completed.

All work must be complete for TAB work to commence.

Clean air filters installed.

All strainers cleaned and start-up strainers removed.

All balancing dampers installed and 100% open.

All manual balancing valves and flow measuring stations installed and 100% open.

Temperature Controls complete and functional.

Slide37

Scheduling Challenges

Phased projects

:

Remember that TAB work is completed

by system, not by area.

Very seldom does the HVAC system match the “Phasing Areas.”

Make sure that the Owner & Architect understand the possibility that the

TAB work might be performed after occupancy.

Variable volume systems (air and water) can have provisions to balance partial HVAC systems.

Constant volume systems can pose major complications if they overlap several phases.

Hydronic systems need to be carefully considered for scheduling issues.

Slide38

TAB Reports

Typically a final TAB report is not available at time of commencement of the Cx FPT’s.

Have an experienced, responsible engineer review the report. It is not just about matching numbers. It is reviewing system performance and employing engineering judgment.

Don’t hesitate to call the TAB agency to review the report together or ask questions.

Keep in mind that there is no benefit to the TAB Agency (

owner’s benefit

) to report problems or deficiencies, it is our responsibility. Be cautious of the “pristine” TAB report.

Slide39

Questions?

Thank you for your time!

Additional Presentation Topics:

Duct Leakage Testing

Testing Hydronic Systems with Diversity

Slide40

Water Flow Measurement:Flow Measuring Stations

Two main types of flow measuring stations:

Fixed orifice or venturi type.

Variable orifice.

Slide41

Water Flow Measuring Stations:Fixed Orifice

<>

Slide42

Water Flow Measuring Stations:Variable Orifice


About DocSlides
DocSlides allows users to easily upload and share presentations, PDF documents, and images.Share your documents with the world , watch,share and upload any time you want. How can you benefit from using DocSlides? DocSlides consists documents from individuals and organizations on topics ranging from technology and business to travel, health, and education. Find and search for what interests you, and learn from people and more. You can also download DocSlides to read or reference later.