/
CROSSTOWN LRT CROSSTOWN LRT

CROSSTOWN LRT - PowerPoint Presentation

cheryl-pisano
cheryl-pisano . @cheryl-pisano
Follow
397 views
Uploaded On 2017-11-19

CROSSTOWN LRT - PPT Presentation

Construction Liaison Committee June 14 2017 Agenda Leaside Station Update Laird Station Update Leaside Station Concept Aerial View Main Entrance Secondary Entrance 60 rendering Accessible Entrance ID: 606381

excavation station support entrance station excavation entrance support main stage laird work secondary area leaside shoring sewer mining underway

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "CROSSTOWN LRT" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

CROSSTOWN LRT

Construction Liaison Committee

June 14, 2017Slide2

Agenda

Leaside Station Update

Laird Station UpdateSlide3

Leaside Station Concept:

Aerial View

Main Entrance

Secondary Entrance

*60% rendering

Accessible Entrance

Accessible Entrance

Outdoor bicycle parkingSlide4

Leaside Station: 2016 in Review

Demolition at 1787 Bayview Ave completed

Median Removals & temporary traffic signals installations

Utility relocations (hydro & telecommunications), underway or complete

Support of excavation (shoring) work started at Main Entrance

4Slide5

Year

Quarter

Construction

Activity / Closure

2017

Q1

(Jan-March)

Bell,

hydro and other telecom u

tility relocations

Support of excavation (shoring) underway at Main Entrance

Stage one for support of excavation activities in right of way (work will be completed in 4 stages)

Q2(April-June)Stage one ongoingDrill to move to Secondary Entrance in late June/early JulyTemporary Site Service Connections (hydro)Dewatering System InstallationQ3(July-Sept)

Stage one

B

Stage two support of excavation activities in right of way

Q4

(Oct-Dec)

Stage three of support of excavation activities in right of way

Leaside Station: What to Expect in

2017Slide6

How We’re Building Leaside Station

:

Support

of Excavation

Shoring

is a common step in the process of installing the foundation of a building.

In the first stage, an area the size of the station’s footprint (about 100m x 20m) will have steel piles installed around the perimeter. Then a shallow area

is excavated and braces and tie-backs are installed around the sides to support the excavation.Decking is then placed over the excavation to allow the crew to work under the roadway safely while traffic flow resumes above.

The shoring stage at Leaside Station started in January and will take approximately 15 months to complete.Slide7

How We’re Building Leaside Station:

Excavation and Mining

During the excavation, crews continue to work safely beneath the roadway.

At Leaside Station a section of the station box will also be mined during this time.

With the mining method, the underground area to be excavated is divided into manageable segments and the segments are excavated in a planned sequence.

The excavation creates a shotcrete-lined cavern

underneath Eglinton Avenue East.

Within the cavern, the station box is constructed accommodating the rail tunnels, associated platform and rail infrastructure. Slide8

Support of Excavation (shoring

): Station Box

Mined AreaSlide9

Support

of Excavation

(shoring): Stage OneSlide10

Proposed Stage 1BSlide11

Proposed Stage 2Slide12

Progress

Picture – Main Entrance Slide13

Progress

Picture – Station BoxSlide14

Laird Station Concept:

Aerial View

Main

Entrance (accessible entrance)

Secondary Entrance

*60% rendering

Eglinton Ave E

Laird Drive

SSlide15

How

We’re Building Laird

Station

:

Support

of Excavation

Laird Station will be constructed using a mined method known as Sequential Excavation Method or SEM. The first stage is support of excavation.

Support of excavation (shoring) is a common step in the process of installing the foundation of a building. In the first stage, crews will install steel piles around the perimeter of the entrance. This has been completed at both entrances.

In the second stage, crews excavate the area level by level, installing braces and tie-backs as they progress. This work is underway at the main entrance.Slide16

Mining occurs from inside of the excavated entrances after the support of excavation is

complete.

This work

now underway

at the

secondary

entrance.The

underground area to be excavated is divided into manageable segments and the segments are excavated in a planned sequence.Within the mined area,

the station box is constructed accommodating the rail tunnels, associated platform and rail infrastructure. Laird station has one of the longest station areas with approximately 500m to be mined. This is to accommodate special track to store a LRV between the tracks or for an LRV to change direction in the event of a service disruption.

How We’re Building Laird Station:

Sequential Excavation Mining MethodSlide17

Laird Station:

2016 in Review

Geotechnical Investigation completed

Demolition

at 250-256 Laird Drive completed

Utility relocations (hydro &

telecommunications)

Piling work completed and excavation work started at both entrancesTemporary traffic signals installations

17Slide18

Year

Quarter

Construction

Activity

2017

Q1

(Jan-March)

Site Service Connections -

Completed

Excavation (shoring) underway at Main (underway)

and

Secondary entrance (completed)Long-term closure at Main entrance – in place

Q2 (April-June)Crane erection secondary entrance – completedMining operations at Secondary entrance - underwayDewatering System installation - underwayConcrete pour into tunnels - underwayUtilities protection

Gas Main Support - underway

Sewer Lining - upcoming

Crane erection main entrance – upcoming

Excavation ongoing at Main entrance

Q3

(July-Sept)

Ongoing mining operations at Secondary entrance

Start of mining

operations at Main entrance

Q4

(Oct-Dec)

Mining

continues at both entrances (mid 2017 to late 2019)

Laird

Station: What to Expect in

2017Slide19

Laird Long Term ClosureSlide20

Support Works – Utilities Mitigation

What to expect:

Sewer Lining

Sewer lining is a process intended to increase the durability of the sewers.

A section of the sewer system is cleaned and vacuumed and a CCTV inspection is completed. Then

a liner is inserted

into the sewer section from within the maintenance holesThe process is designed to be generally non-disruptive and eliminates the need for excavation of the entire sewer section. Maintenance holes that will be accessed

are located on Eglinton Avenue East between Sutherland Drive and Brentcliffe Road.Lane closures will be required for this work. Pedestrian access will be maintained.

Above ground pipes will be in place between maintenance holes to bypass pump around the sewer lines during the liner installation. Due to the nature of the work, an unpleasant chemical odour may be noticeable in the vicinity of the maintenance holes and, in some circumstances, in the home. It is not harmful, however it can be limited by covering floor drains while the sewers are being lined.

A public notice with additional details will be distributed prior to work beginning. Slide21

Support Works – Utilities Mitigation

What to expect: Sewer Lining

Sewer Lining Activity ExamplesSlide22

Progress Picture – Main EntranceSlide23

Progress Picture – Secondary EntranceSlide24

Local Area Map

Station(s) under construction Slide25

Community Benefits – Laird Mural

Creation

of a mural that reflects the

Thorncliffe

Park

neighbourhood

Design

concept under

development

Production/painting is scheduled for the first week of July (July 4-7

)

Feedback welcome!Slide26
Slide27