/
1 Florida Marine Contractors Association 1 Florida Marine Contractors Association

1 Florida Marine Contractors Association - PowerPoint Presentation

conchita-marotz
conchita-marotz . @conchita-marotz
Follow
446 views
Uploaded On 2016-07-05

1 Florida Marine Contractors Association - PPT Presentation

CRANE AND RIGGING TRAINNG AND CERTIFICATION REQUIREMENTS BY OSHA AND ANSIASME STANDARDS Shawn Khan October 16 2015 Overhead Crane Operators OSHA and ANSIASME require all operators to be trained and tested either verbally or with a written test to include a handson evaluation ID: 391200

operator qualified qualification crane qualified operator crane qualification certification boom equipment cranes person load signal requirements line inspection power

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "1 Florida Marine Contractors Association" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

1

Florida Marine Contractors Association

CRANE AND RIGGING TRAINNG AND CERTIFICATION REQUIREMENTS BY OSHA AND ANSI/ASME STANDARDS

Shawn Khan October 16, 2015Slide2

Overhead Crane OperatorsOSHA and ANSI/ASME require all operators to be trained and tested either verbally or with a written test to include a hands-on evaluation.If the training and testing is not documented, OSHA says it did not happen!Reference OSHA 1910.179, ASME B30.2, B30.11, B30.16 & B30.17

2Slide3

Riggers and Signal PersonsRiggers and Signal Persons are required to be trained and tested and designated as Qualified per OSHAEmployers are to document who is designated for each lifting project.Reference OSHA 29CFR Subpart CC, 1910.184, 1926.251, ANSI/ASME B30.9, B30.10, B30.20, and B30.26

3Slide4

Maintenance Versus ConstructionOSHA looks at lifts “in kind” as maintenance, where they will use the General Industry Standards.If anything is lifted that is different in any way, OSHA will use the Construction Standards. These lifts include different materials, weights, model numbers, products, and sizes of the products that are being lifted.

4Slide5

5

CRANES and DERRICKS IN CONSTRUCTION SUBPART CC7 years in the making

The new standard includes more SHALL and MUST statementsChanges are still not clearLetters of InterpretationsClarificationsGuidance Documents (fact sheets and presentation)“Case Law”Slide6

6

WHAT IT APPLIES TO

Articulating cranes (such as knuckle-boom cranes)Crawler cranesFloating cranesCranes on bargesLocomotive cranesMobile cranes (such as wheel-mounted, rough-terrain, all-terrain, commercial truck-mounted, and boom truck cranes)Multi-purpose machinesDedicated pile driversService/mechanic trucks with a hoisting deviceCrane on a monorailTower cranes (such as fixed jib (“hammerhead boom”), luffing boom and self-erecting)Pedestal cranesPortal cranes

Overhead and gantry cranesStraddle cranesSideboom cranesDerricks. . . and variations of such equipment. Equipment that can hoist, lower and horizontally move a suspended load………Slide7

7

EQUIPMENT EXEMPTIONS

ExcavatorsBackhoesTrack LoadersSelf Propelled Elevating Platforms (aerial lifts)Forklifts (exceptions)Including when machines are fitted with slings, chains, or other rigging equipment to lift suspended loadsConcrete Pump Trucks w/boomPower ShovelsVehicle Mounted Work PlatformsArticulating/Knuckle Boom Cranes – when making deliveries only.Light Duty Cranes under 2,000lb capacity much of the standard does not apply Slide8

8

SUPPLEMENTAL REQUIREMENTSTower Cranes

Erecting, climbing, dismantlingSignsSafety devicesOperational AidsInspectionsDerricksFloating Cranes/Derricks and Land Cranes/Derricks on BargesDedicated Pile DriversSideboom CranesEquipment with less than 2,000lb capacitySlide9

9

KEY DATESNovember 8, 2010

– Qualified Signal Person, Qualified Rigger, Qualified Operator, and Most Other Provisions Become Effective/EnforceableNovember 10, 2017 – Operator Certification Requirements Effective/Enforceable November 8, 2010-November 10, 2017: Employer must ensure that all operators are competent to operate the equipment safely and are trained and evaluated on that training before operating the equipment.November 2011 – Insulating link/device (November 2013 for existing inventory)Slide10

10

IMPORTANT TOPICSSignal Person Requirements – Qualified & Evaluated (third party or in-house)

Rigging Person Requirements – Qualified & EvaluatedOperational Aids/Safety AidsGround ConditionsFall Protection (Employee Training and Manufactured Equipment Requirements - Research)Authority To Stop OperationsInspection CriteriaOperator Certifications/RequirementsPower Line SafetyTraining – All Personnel Synthetic slings – requires paddingSlide11

11

HIGHLIGHTS

Definitions (100+)

Training RequirementsRiggerSignalerOperatorCrew MembersEquipment ExemptionsOperational AidsGround ConditionsAssembly/DisassemblyA/D DirectorLift DirectorInspectionsWire RopeSafety DevicesPower Lines Slide12

12

KEY DEFINITIONSControlling Entity – Entity that has the overall responsibility for the construction of the project – (GC, CM, Owner/Developer)

Qualified PersonQualified EvaluatorQualified RiggerQualified Signal PersonProximity AlarmSlide13

13

RIGGERMust be QUALIFIED:Qualified person means a person with a recognized degree or certificate of professional standing or trained with extensive knowledge and experience. The qualified person must be able to demonstrate the ability to solve or resolve problems relating to the subject matter or the project

….KEY DEFINITIONSSlide14

14

….KEY DEFINITIONSSignal Person

Know and understand signals to be used, as well as all forms of signals Be competent in the application of the type of signals to be usedHave basic understanding of crane operation and limitations, including the crane dynamics involved in swinging and stopping loads and boom deflection from hoisting loadsMust be able to effectively communicate to crane operatorOral or Written test and through a practical test!Evaluated by a Qualified Evaluator – 3rd Party, In-houseSlide15

15

SIGNAL PERSON QUALIFICATIONWho determines who is qualified:

Must obtain documentation from a third party qualified evaluator showing that the signal person meets the qualification requirements established in the standard; OR Obtain documentation from the employer’s qualified evaluator (not a third party) showing that the signal person meets the qualification requirements established in the standardAt no cost to the employeeSlide16

16

Signal Person Qualifications

Qualified ByDocumentationPortable

3rd Party Qualified EvaluatorYes

Yes

Employer Qualified Evaluator

Yes

No

*Note – Must document the specific type of signaling they are qualified to perform – hand signals, radio, etc.Slide17

17

AUTHORITY TO STOP OPERATIONSAnyone can give the emergency stop signal!!

Whenever there is a concern for safety, the crane operator shall have the authority to stop and refuse to handle loads until a qualified person has determined that safety has been assured.Slide18

18

MANDATORY TRAINING OF EMPLOYEES FOR SPECIFIC TOPICSOverhead Power Lines

Signal PersonsCompetent/Qualified PersonsCrush/Pinch Points – Exposed EmployeesAssembly/DisassemblyTag-OutOperatorsFall ProtectionSlide19

19

WORKERS IN THE LOAD AREANo worker can be within the fall zone while the operator is moving a suspended load, except for the following situations:

Workers engaged in hooking, unhooking or guiding a load; Workers engaged in the initial attachment of the load to a component or structure; or Workers operating a concrete hopper or concrete bucket (and other times). Slide20

20

When workers must be in the fall zone the following criteria must be met: The materials being hoisted must be rigged to prevent unintentional displacement.

Hooks with self-closing latches or their equivalent must be used. The rigging must be done by a Qualified Rigger. Only workers receiving the load can be within the fall zone when the load is being landed….WORKERS IN THE LOAD AREASlide21

21

GROUND CONDITIONSThe Controlling

Entity must ensure that appropriate ground preparations are provided. (Firm, drained and graded, with knowledge of nearby power lines and utilities)Where there is no controlling entity the employer must ensure that appropriate ground preparations are provided. All information known about ground conditions are required to be shared.Slide22

22

ASSEMBLY/DISASSEMBLYTwo options

Manufacturer proceduresEmployer procedures – with oversight!General requirements, such as:A/D Director = “competent & qualified person”A/D Director must:Understand proceduresReview procedures (unless A/D Director has used them before) Check that crew members understand their tasks, hazardsFollow manufacturer’s prohibitionsAll rigging work is done by a Qualified RiggerWhen using outriggers - fully extend or deploy as per the load chartSlide23

23

CRANE INSPECTIONSAfter ModificationAfter Repair or Adjustment

Post AssemblyEach Shift MonthlyAnnual ComprehensiveSlide24

24

Daily/Shiftdoesn’t have to be documented – but if it isn't in writing it doesn’t exist!!!Monthly Inspections

Documented and kept on file for three monthsAdditional Inspection for Tower Crane components upon delivery to site and prior to erection….CRANE INSPECTIONSSlide25

25

Annual Inspection DocumentedDetailed inspection criteriaKept on file for 12 months or next annual inspection

Not in regular use:DocumentedIdle more than three monthsMonthly inspection must be performed….CRANE INSPECTIONSSlide26

26

Crane Inspections

Inspection TypeWho Inspects

Modified or Repaired/AdjustedQualifiedEmployer Qualified Evaluator

Qualified

Shift

Competent

Monthly

Competent

Annual

QualifiedSlide27

27

WIRE ROPE INSPECTION Shift Inspection

Before each shift (doesn’t say to document, but one should)Monthly InspectionAll wire rope, Hooks, Wire Rope Slings, and Chain Slings (Documented)Annual Inspection At least every 12 months, unless not feasible due to set-up.More detailed, including wire rope that is normally hidden during daily/monthly inspections, etc. (Documented)Slide28

28

Wire Rope Inspection

Inspection TypeDocumentationDaily

No DocumentationMonthlyDocumented

Annual

Documented

Deficiencies (I, II, III)

DocumentedSlide29

29

OPERATOR CERTIFICATION/QUALIFICATIONFor the TYPE

of crane to be operated! Capacity was removed in May 2015.No physical examinations or drug testing requirements, but NCCCO requires signature attesting to both.Re-certification / qualification must be completed every five yearsSlide30

30

Option (1) –certification by an accredited crane operator testing organizationAccredited by a nationally recognized accrediting agencyCertification is portableValid for five years

Program must be reviewed by a nationally recognized accrediting agency every three years.….OPERATOR CERTIFICATION/QUALIFICATIONSlide31

31

….OPERATOR CERTIFICATION/QUALIFICATIONOption (2) – qualification by an audited employer program

–Developed or approved by an auditor certified by an accredited crane operator testing organization.Note: NCCCO, NCCER, CIC, and IUOE do not provide audits of In-House Training and Qualification Programs.–Auditor is not an employee of the employerOption (3) – US MilitaryOption (4) – State/LocalSlide32

32

Operator Qualification and Certification Chart

Organization

PortabilityValid

Accredited Testing Organization

Yes

5 yrs.

Employer Qualification Pgm.

No

5 yrs.

US Military

No

Set by issuing establishment

State/Local

No

Set By issuing establishment, but no more than 5 yrs.Slide33

33

….OPERATOR CERTIFICATION/QUALIFICATIONWritten Testing on:– Controls and operational performance

– Ability to calculate the manufacturer’s load/capacity– Procedures for power line contact– Site preparation– Ability to read manuals/charts relevant to the equipment being operated – Technical Knowledge – OperationsSlide34

34

….OPERATOR CERTIFICATION/QUALIFICATIONPass practical examinationAbility to perform a pre-shift inspectionOperational and maneuvering skills

Application of load chart informationApplication of safe shut down and securing proceduresSlide35

35

….OPERATOR CERTIFICATION/QUALIFICATIONEmployer must revoke operators certification if they have reason to believe the employee is not qualified to operate.

All programs shall have provisions for retraining employees.The current training records must be on file during the operator’s employment.Slide36

36

….OPERATOR CERTIFICATION/QUALIFICATIONMany States, and/or Cities now require operators of essentially all cranes to provide proof of license in addition to certification upon request by an investigator.

An employer may be cited by the governing entity for a violation of the requirements, as well as the revoking of the license from the operator.Slide37

37

….OPERATOR CERTIFICATION/QUALIFICATIONThere is a four (4) year phase, currently in process, for the employer to get their operators to obtain certification by 11/10/2017.

New operator training will be allowed under the continuous supervision of a certified operator with some minor exceptions.Slide38

38

OPERATIONAL AIDSBoom Hoist Limiting Devices

Luffing Jib Limiting Devices Anti-two blocking–(February 28, 1992)(November 8, 2011-Lattice Boom Cranes)Boom Angle or Radius Indicator Jib Angle Indicator Boom Length Indicator Load Weighing and Similar Devices. Slide39

39

OPERATIONAL AIDSThey are required, but a temporary alternate measure is permitted when being repaired.

Example – If boom hoist limiting device is not working, the boom angle indicator can be utilized or mark the boom hoist cableNote: There are different categories for replacement parts (I, II, III) – Changes must be communicated to all affected employeesSlide40

40

SAFETY DEVICESThe following safety devices

are required on all equipment unless otherwise specified in parts of the standard: Crane Level Indicator Boom/Jib Stops (except for hydraulic booms & derricks) Locks on Equipment with Foot Pedal Brakes Integral Holding Device/Check Valves on hydraulic outrigger jacks and hydraulic stabilizer jacks Equipment on rails must have rail clamps/stops HornSlide41

41

POWERLINESIdentify Work ZoneMarking boundaries

or360 degrees around crane up to maximum working radiusSlide42

Could you get within 20 feet of power line?

YES

NO

Option #1

Deenergize & Ground

Encroachment Prevention Measures

(Equipment Operations)

Option #3

Ask Utility for Voltage and

Use Table A

(

with minimum clearance distance)

Option #2

20-foot clearance

No further action

Planning meeting

If tag lines used they are to be nonconductive

Elevated warning lines, barricade or line of signs

PLUS

one of the following:

Proximity alarm, spotter, warning device, range limiter, or insulating link

42Slide43

Must Show

:

Staying outside zone is infeasible Infeasible to deenergize and ground

Intentionally Working Closer Than Table A Zone

All

of the following are required:

Power line owner –

sets minimum approach distance

Planning meeting – minimum procedures

- Dedicated spotter

- Elevated warning line or barricade

- Insulating link/device

- Nonconductive rigging

- Range limiter (if equipped)

- Nonconductive tag line (if used)

- Barricades - 10 feet from equipment

- Limit access to essential workers

- Prohibit non-operator workers from touching

above insulating link

- Properly ground crane

- Deactivate automatic re-energizer

- Insulating line cover-up installed

43Slide44

Table A – Minimum Clearance Distances

Voltage (nominal, kV, alternating current)

Minimum clearance distance (feet)up to 50

10over 50 to 200

15

over 200 to 350

20

over 350 to 500

25

over 500 to 750

35

over 750 to 1000

45

over 1000

(as established by the power line owner/operator or registered professional engineer who is a qualified person with respect to electrical

power transmission and

distribution)

44Slide45

45Slide46

46

SUMMARYRead the standardDo research

Ask a lot of questionsGet clarificationDon’t be afraid to call OSHA and ask for clarificationReview OSHA’s presentation on line and their fact sheetsSlide47

47

Presented by

Shawn Khan

Sales Account ManagerShawn.Khan@cicb.comPhone: (800) 327-1386Local: (407) 277-0884