/
CR3 and Crystal River Energy Complex CR3 and Crystal River Energy Complex

CR3 and Crystal River Energy Complex - PowerPoint Presentation

debby-jeon
debby-jeon . @debby-jeon
Follow
352 views
Uploaded On 2018-11-03

CR3 and Crystal River Energy Complex - PPT Presentation

1 CR3 2013 2019 2 February 2013 Duke Energy announces the permanent shut down of CR3 There are approximately 600 employees greater than 200 security officers and several hundred other contractors on site ID: 712296

isfsi fuel 2019 cr3 fuel isfsi cr3 2019 2013 spent security plan emergency pad pool nrc site safstor transition

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "CR3 and Crystal River Energy Complex" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

CR3 and Crystal River Energy Complex

1Slide2

CR3 2013 - 2019

2

February 2013Duke Energy announces the permanent shut down of CR3There are approximately 600 employees, greater than 200 security officers and several hundred other contractors on siteDuke submits a notice of Permanent Cessation of Operations letter to the NRCSlide3

CR3 2013 - 2019

3

July 2013Approximately 300 employees remain on site in the Decommissioning Transition Organization (DTO), small reduction in security officers, reduced number of contractorsSeptember 2013Submitted the permanently defueled emergency plan (PDEP), emergency action level (EAL) scheme change and the request for exemption from emergency planning standards for NRC reviewDecember 2013Post Shutdown Decommissioning Activities Report and the Detailed Cost Estimate (SAFSTOR option chosen) submitted to NRC and State of Florida

60 + 1 years$1.18B (2013 dollars)Slide4

CR3 2013 - 2019

4

August 2014Duke Energy Board of Directors approve the Independent Spent Fuel Storage Installation (ISFSI) project$173M (trust and regulatory asset)Additional $9.8 M security project managed by the ISFSI team

October 2014Commence ISFSI pad constructionDecember 2014Completed nuclear island constructionCompleted legacy low level radioactive waste shipment projectApril 2015Implemented the Permanently Defueled Emergency PlanSlide5

CR3 2013 - 2019

5

July 2015Transitioned to the SAFSTOR I OrganizationApproximately 70 employees, 110 Security Officers and the ISFSI team (currently 115)September 2015Implemented Permanently Defueled Technical SpecificationsMade the transition from Nuclear Reactor Regulation to Nuclear Material Safety and Safeguards (NRC oversight).

May 2016Submitted the ISFSI only security plan and emergency plan to the NRCJune 2016Received the Historical Site Assessment reportSlide6

CR3 2013 - 2019

6

November 2016Completed the large component disposition project (original steam generators and original reactor head)January 2017Complete ISFSI pad ConstructionFebruary 2017

Completed shipment of batch 19 fuel to Oconee plant.June 2017Commence the spent fuel pool to pad campaignDec 2017Kicked-off update of the Detailed Cost EstimateSlide7

CR3 2013 - 2019

7

January 2018Completed pool to pad activities Submitted notification that all fuel removed from the Spent Fuel PoolImplement ISFSI-Only Technical SpecificationsFebruary 2018

Commence spent fuel pool clean-upMove greater than class C (GTCC) waste from the pool to ISFSI padRemove non-fuel components from Spent Fuel PoolRemove spent fuel racks from Spent Fuel PoolApril 2018

Implement ISFSI–Only Security Plan and ISFSI-Only Emergency PlanSlide8

CR3 2013 - 2019

8

September 2018Complete Spent Fuel Pool cleanup/draindownMarch 2019Relocate personnel to new office/shop locationsJuly 2019

Place in service new electrical, Fire Protection and ventilation systemsComplete remaining SSC abandonmentPower Block cold, dark and deenergizedImplement SAFSTOR II (55 people)Slide9

CR3 2019 - 2074

9

Operate, maintain and secure the ISFSI and various power block structuresDOE takes possession of the used fuel and GTCC waste (2036)Transition to dormancy with no used fuel on site (2036)Commence D&D planning (2068)Complete license termination (2073)

Complete site restoration (2074)Slide10

CR3 ISFSI Pad

10