BI Technical Board 922017 Agile for TS Activity Tracking Emphasis on information exchange not control Create highlevel JIRA issues for each task if not already existing Eg Port class ABC from FESA2gtFESA3 ID: 536548

migrate fesa3 issues lhc fesa3 migrate lhc issues control l866 class upgrade summary psb elena sps update jira bisw

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Update on BISW EYETS activities" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Update on BISW EYETS activities

BI Technical Board 9/2/2017Slide2

Agile for TS Activity Tracking

Emphasis on information exchange – not control!

Create high-level JIRA issues for each task (if not already existing)

E.g. Port class ABC from FESA2->FESA3Add specific watchers & allow comments from other sectionsAdd labels to gather statisticsSprint created for each TSAssign the issues to the sprintUse Scrum board to move change status of issuesToDo->InProgress->DoneOnce the TS is finished, unfinished issues stay in backlogAnd can be assigned to the next TS for exampleSlide3

Link to Board

https://issues.cern.ch/secure/RapidBoard.jspa?rapidView=239Slide4
Slide5
Slide6
Slide7

Summary LHC

Upgrade BCTDCLHC to L866

Upgrade BPMITLHC to L866

Change BQBBQLHC installationUpdate BSRTSLHC class for new digital cameraUpgrade BPMLHC and BPMDLHC to L866Migrate BWSLHC to FESA3 while separating FECs for B1/B2Migrate BSTLHC to FESA3Migrate BTVDD to FESA3Migrate BOBR instances to FESA3/L866Create new class BOWC for TCTW Wire ControlUpgrade BLDMLHC to FESA3/L866Eradicate BCTFRLHC class based on DAB64x module (replace with VFC)LHC Schottly BOBR replacement serverLHC Schottly Signal generator control serverLHC BCTFVFC in the dump linesLHC BCTFVFC in the ringLHC BSRALHC minor modifications + logging interfaceSlide8

Summary SPS, LEIR & LN4

SPS

Migrate BLMI to FESA3

Migrate BFCTSR to FESA3 / L866 and VFCMove SPS IN-OUT devices to FESA3BPMI firmware and lib upgradeLEIRDeploy BPMLE FESA3 version (find correct fw config) 

LN4

Migrate BOSEMCTRL and BOPLCIO to FESA3

BPML4 update

TOF calculation for Linac4 and PSB injection BPMsSlide9

Summary PS, PSB, EA, ADE, ELENA

PS

Migrate PS complex SEM-grid servers to FESA3

Migrate BPMOPS server to FESA3PS 1000 Turns to be operationalPSBNew Orbit acquisition system in the PSBEAMigrate EA servers to FESA3ADE / ELENACreate a new BQSB instance for ELENA using latest FESA3 deploymentElena scraperImprove BPM class and make changes compatible with Hw

changesSlide10

Summary Others

New

FESA class to control ISEG VDS 4

New control software for the Isolde scanners (BSISO)HIE Isolde Beam Diagnostic Boxes (Motors + Faraday Cup + Slit scans)BTVI, horizontal image mirroringHIE Time of Flight (HREXTOF)HIE Digitizer (HREXDIGI)Migrate BQSB to FESA3 (Deploy in PSB, PS, ADE, SPS)Slide11

Notable Changes 1/2

Moving to 64 bit O/S of critical systems

BPMLHC, BPMDLHC, BCTDCLHC

Don’t expect any problemsBPMITLHC (LHC interlock BPMs)XPOC average 1024 turns -> bunch-by-bunch measurements over last 147 turnsTriggered by issue in existing firmwareGives Nicolas Magnin more flexibility in post-analysisBTVDD – FESA 3 migrationCareful handing of porting to not break XPOC interface and disturb ABPSlide12

Notable Changes 2/2

BSRTSLHC

Connected to interlock

Renaming & moving BQBBQLHC devicesAwaiting ECRNeed to analyse impact on LHC sequencer and feedback service unitFeedback Service UnitAn epic of 12 separate issuesEradication of BPMLHCConcNew FGC3/FGCLite devicesSwitch on RefOpticsMagic (real-time RM recomputation)

…Need careful testing at startupSlide13

Summary

BISW will try to organize TS planning using JIRA tools

First attempt to organize like this came late so is very rough

Focus is on keeping as light as possibleOthers from outside BISW can use the dedicated JIRA issues to update / communicate informationMost EYETS tasks are well underwaySome will start progress in coming days / weeksE.g. BWSLHC Many in-progress issues are almost doneInteresting note24 BISW entries on Smooth Upgrades Wiki versus 41 in our sprint!When developers have control in JIRA they can maintain the list better