Download Presentation The PPT/PDF document "Aviation and Ports Transportation Strat..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Aviation and Ports Transportation Strategy BoardJuly 28, 2010
1Slide2
Aviation 2BradleyThe impact of the global economic crisis on Bradley resulted in a 15% decrease in the number of seats available in 2009 compared to 2008. Nationally the decline was 6%. There were 11.2% fewer passengers (5% nationally) and and a 9.9% decrease in fares (9.7% nationally).DOT believes Bradley experienced downturns greater than the national average due in part to the airport’s position in the highly competitive markets of New York, Boston and Providence.
Slide3
Aviation3BradleyPassenger and Cargo Trends
2006
2007
2008
2009
Passengers
6.9M
6.5M
6.1M
5.3M
Cargo (Tons)
162,384
161,264
146,375
114,689Slide4
Aviation4BradleySeveral new services reported in Moving Forward have since ended:AmsterdamSalt Lake CityPhoenixLos Angeles
(Started in 2005, ended Sept 08, began, 6/10, will end 9/30/10)
Direct flights to Cancun (2008), Denver (3/10)*, LA (6/10) and Milwaukee 9/10 have been added.
*Service started in 2007, ended then began again in March 2010Slide5
Aviation5Bradley JetBlue will begin daily service to Fort Lauderdale and Orlando November 17, 2010.The Murphy Terminal (aka Terminal B) is now closed. Renovations to Terminal A will be completed in August 2010.Public Act 10-98 established the Bradley Development Zone in the towns of Windsor Locks, Suffield, East Granby and Windsor.Slide6
2009 - 2008
2009
2008
2007
Change ($)
Change (%)
BRADLEY
OPERATING
REVENUES
Landing fees
11,626
10,800
8,181
826
7.6%
Airline terminal rent 10,439 11,177 10,704 (738)-6.6%Apron and remote aircraft parking 2,904 3,203 4,039 (299)-9.3%Auto Parking 9,647 9,448 9,254 199 2.1%Rental cars 6,888 7,930 7,515 (1,042)-13.1%Terminal concessions 3,050 3,440 3,372 (390)-11.3%Other Concessions and operating revenue 4,381 4,745 4,799 (364)-7.7%Land rent 3,334 3,404 3,033 (70)-2.1%Total operating revenues 52,269 54,147 50,897 (1,878)-3.5%
FOR THE YEARS ENDED JUNE 30, 2009, 2008 AND 2007(in thousands)
6Slide7
Aviation7BradleyCRCOG allocated STP Urban funds for the relocation of Bradley Park Road, but was not able to secure the necessary 20% nonfederal share. The Air National Guard is pursuing funding through military sources, but funding is not likely in the near term.The Suffield town administration has changed and support no longer exists for development of a new northern route to/from Bradley. A new development now occupies a piece of the property that the route was to pass through.Slide8
Aviation8BradleyThe recommendation to evaluate and if feasible implement express bus service from Hartford to Bradley is complete. ConnDOT met with business groups in Hartford and determined that there does not seem to be a demand for the service at this time.Slide9
Aviation9TweedUS Airways is currently operating 4 flights per day from New Haven to it’s hub in Philadelphia down from 12 in 2007. It is the only passenger service available at Tweed.The annual operating grant to Tweed increased in SFY 10.SFY 10 - $1,425,000 - paid in 3 installments SFY 09 - $570,000SFY 08 - $600,000SFY 07 - $600,000SFY 06 - $600,000Slide10
Aviation10TweedSafety Improvements at Tweed are advancing.Phase I – All expected to be completed in 2010.Phase II – Projects are proceeding based on the FAA approved State of Connecticut Capital Improvement Plan and are being implemented within available funding.Phases III/IV - Tweed is acquiring the necessary properties and easements as they become available on a voluntary basis. The remainder of the projects in these two phases are scheduled to be completed as federal funds become available.
Slide11
Aviation11OtherConnDOT provides State Grant in Aid funds to municipalities to evaluate and possibly purchase privately owned airports, to aid in the preservation of such airports.Legislation was passed to provide funding to certain privately owned, public use airports for capital improvements. This would be a cost sharing program with the airports. To date no funding has been allocated for this program. Slide12
2007 Recommendations Aviation - Bradley 12Support the strategies and tactics (including the traffic improvement recommendations) adopted by the Bradley Board of Directors to strengthen Bradley as the State’s major commercial airport for both passenger and air freight services for the State and the rest of Western New England.Slide13
2007 RecommendationsAviation - Bradley13Encourage the Bradley Board of Directors to work with appropriate State agencies and neighboring municipalities to:define economic development goals and priorities for Bradley;
establish procedures to pre-approve development sites on Bradley property; and
Work with adjacent towns and encourage support for complementary and coordinated multi-town economic development plans.
Slide14
2007 RecommendationsAviation – Bradley14Establish the improvement of cargo service as a priority for the Bradley Board of Directors and the Department of Transportation.Recognize the success of Bradley’s marketing and route development efforts and support continuation of those efforts.Include business and community leaders from Western Massachusetts in Bradley Airport planning and service development.Slide15
2007 RecommendationsAviation - Bradley15Support and fund implementation of the Capitol Region Council of Government’s Bradley Area Transportation Study including:
Relocation of Bradley Park Road
Development of new northern route to/from Bradley
Route 75 Gateway
Improved Transit Services
Slide16
2007 RecommendationsAviation-Bradley16Evaluate, by January 1, 2008 and, if feasible, implement express bus service between Bradley and downtown Hartford. (Completed)Establish through legislative and/or administrative action the process and the funding needed for land banking to mitigate the environmental impact of airport development including safety improvements.Slide17
2007 RecommendationsAviation-Tweed17Support Tweed’s ability to serve the travel needs of business and institutional travelers in Southern Connecticut to complement Bradley.Continue the state’s annual operating assistance grant to the Tweed-New Haven Airport Authority.Slide18
2007 RecommendationsAviation-Tweed18Support the implementation of the Safety Improvements described in Phases I and II of the Tweed Master Plan within the planned three to five year period.Evaluate Phases III and IV of the Tweed Master Plan as Phases I and II are being implemented, including the fiscal and other impacts to adjacent municipalities.Slide19
2007 RecommendationsAviation-Other19Assist airport operators in addressing obstruction issues which cannot be resolved locally.Support efforts to retain and preserve private airports open to the public, including an adequate number of reliever airports.Slide20
Maritime20Memorandum Of Agreement between ConnDOT and the Bridgeport Port Authority to initiate feeder barge service expired on April 30, 2009.Public Act 08-101 established a Harbor Improvement Account (HIA). The HIA is designed to provide funds to facilitate dredging projects and other harbor infrastructure improvements in support of or at times in place of Federal funds. To date, no funding has been allocated to this account.The rail line in New Haven across the Tomlinson Bridge and along Water Street is complete.
ConnDOT
has postponed completion of the rail line connections to the individual terminals in New Haven due to budgetary constraints. Slide21
Maritime - Change in Freight Traffic 2004-2008 PORT
FREIGHT TRAFFIC
(TONS)
CY2004
FREIGHT
TRAFFIC
(TONS)
CY2007
%
CHANGE
BRIDGEPORT
5,671,230
7,627,957
+34%
NEW HAVEN
10,855,9349,574,406-12%NEW LONDON 1,534,6481,255,763-18%21Slide22
22Activity
FY06
FY07
FY08
FY09
Rocky Hill
Crossings
8,874
10,522
12,002
7,366
Vehicles
14,840 17,071 20,549 11,574Passenger only5,697 6,773 7,992 5,447Chester Crossings19,562 19,712 20,026 19,990Vehicles36,750 38,449 40,803 38,335Passenger only3,409 3,555 4,141 2,841 Total
Crossings
28,436
30,234
32,028
27,356
Vehicles
51,590
55,520
61,352
49,909
Passenger only
9,106
10,328
12,133
8,288
Rocky Hill-Glastonbury and Chester-
Hadlyme
FerriesSlide23
Rocky Hill-Glastonbury and Chester-Hadlyme Ferries2008/2009 Operating Expenses23Rocky HillPersonal Services
Other
Expense
Building Expense
Total Expenses
2008
$234,955
$42,999
$1,856
$279,810
2009
$216,883
$4,508
0
$241,391
Chester2008$307,603$54,697$2,501$364,8012009$268,209$49,125$3,568$320,901Slide24
2007 Recommendations MARITIME24Determine the State’s role in the funding and prioritization of dredging projects.Complete the rail link to the Port of New Haven and evaluate the potential for improved rail connections to the state’s other commercial deep water ports.Inventory and prioritize statewide dredging needs and develop an estimate of the non-federal funding required for each such project. (Completed
)Slide25
2007 Recommendations MARITIME25Expedite the long overdue dredging of Bridgeport harbor.Support continued federal funding for development and completion of a Dredged Material Management Plan (DMMP) for Long Island Sound.Review the feasibility and viability of the proposed Bridgeport to New York feeder barge service. Entertain, and potentially fund, proposals for feeder barge services from ports other than Bridgeport.