/
Helium Spill Test in LHC Helium Spill Test in LHC

Helium Spill Test in LHC - PowerPoint Presentation

giovanna-bartolotta
giovanna-bartolotta . @giovanna-bartolotta
Follow
450 views
Uploaded On 2016-07-17

Helium Spill Test in LHC - PPT Presentation

tunnel to define length of restricted working areas Actual situation Evolution How to continue S etup of the spilling test How Where When Risks Ongoing work Conclusions 01112013 ID: 408877

helium test lhc spill test helium spill lhc 2013 bremer tunnel johan spilling flow area restricted tunnelset equipment based sector proposal ventilation

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Helium Spill Test in LHC" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1
Slide2

Helium Spill Test in LHC tunnelto define length of restricted working areas

Actual situationEvolutionHow to continueSet-up of the spilling testHowWhereWhenRisksOn-going workConclusions

01/11/2013

Johan BremerSlide3

Helium Spill Test in LHC tunnelActual situation

01/11/2013Johan Bremer

LHC Project Report 684*: header C average flow 1 kg/s

length helium jam 6 m

After discussion (HSE and DSO): make restricted work area of 3 m, centred around release point.

*SUMMARY

OF THE EXPERIMENTAL STUDIES OF COLD

HELIUM PROPAGATION

ALONG A SCALE MODEL OF THE LHC

TUNNEL (2003)Slide4

Helium Spill Test in LHC tunnelEvolution

01/11/2013Johan BremerNew proposal based on scale model

New proposal based on simulations

~100 m

Restricted

w

orking-area

50 + 30 m

(45 % of tunnel)

Vacuum barrier

Pressure relief

d

evice (w/o spring)

Ventilation

Jumper

Restricted

w

orking-area

6 + 6 m

(9 % of tunnel)Slide5

Helium Spill Test in LHC tunnelHow to continue

01/11/2013Johan BremerLarge difference between proposal based on scale model and proposal based on simulation workMake a representative spilling test in the tunnel to check the validity of the different models and calculations and base new access rules on these validated calculations:Liquid helium spill of 1 kg/sTotal spill per test 125 kg (= 1000 liquid liters)

Ventilation flow in access mode: 18000 m3/h, about 0.7 m/s in tunnelSlide6

Helium Spill Test in LHC tunnelSet-up of the spilling test: how

01/11/2013Johan Bremer

Pressurize

dewars

with warm helium gas taken from cylinder. The liquid mass flow will be measured by balances on which the

dewars

will be placed

1450 mm

DN 200

Dewar: Design pressure 2 bar

Safety valve 0.5 bar

Pressure drop system 0.1 barSlide7

Helium Spill Test in LHC tunnelSet-up of the spilling test: how

01/11/2013Johan BremerEquip the tunnel with measurement system25 Temperature sensors (Pt100)25 ODH (special development of fast reacting measurement head)6 cameras4 air velocity sensors2 mass balances (used for calculation of mass flow)

Equipment will be placed on 15 stands, 8 downstream (over 200 meter) and 7 upstream (over 100 meter) of ventilation

direction, at

places referenced to the simulation model

Most sensors will be placed at 1.75 m height, in passage

area

Total of two to three tests will be madeSlide8

Helium Spill Test in LHC tunnelSet-up of the spilling test: where / when

01/11/2013Johan Bremer Test should be made at a point where the ventilation flow is out-going (un-even point)Test should be made at the end of continuous cryostat section, to minimize effect on the chosen sectorTest should be made where there is least interference with on-going workThe ODH sensors have to be developed (fast reacting sensors not available on the market

)

Discussion with SMACC, VSC and coordination:

Test foreseen for end of January 2014 in sector 4-5, left of 5,

300 meter into arcSlide9

Helium Spill Test in LHC tunnelSet-up of the spilling test: risk

01/11/2013Johan Bremer Risk assessment based on LHC sector 3-4 experience and modelisation:Sector 3-4Estimate of situation during helium release*:first 40 sec helium flow: 15 to 26 kg/s (spill: 1 kg/s)helium mass released first 120 sec : 2000 kg (spill: 125 kg)

No explicit damage to tunnel structure, cable trays, electrical cabinets, cryogenic piping / valves

etc

,

directly

related to helium flow

Modelisation

helium spill in XFEL tunnel

**:

Modeled helium flow in the range of spill test;

Maximum temperature drop of mechanical equipment in the tunnel is not going over 40 degrees (if jet not directed onto equipment)

Conclusion: very confident that collateral damage is excluded, but…..

* CERN-ATS-2009-002: Task Force Report: Safety of Personnel in LHC underground areas following the accident of 19

th

September 2008

**Simulation

study of helium release in the XFEL tunnel, WUT-ref:#630333/I22-01Slide10

Helium Spill Test in LHC tunnelSet-up of the spilling test: risk

01/11/2013Johan BremerHelium spill tests will only be performed outside of normal working hours (no access in sector 4-5)Interconnects will be closed in area in which the spill test will find placeAll equipment owners in the area where the spill test will find place, are asked to protect their sensitive material (electronic cards, connectors etc.) against condensation of water during and directly after the spilling test* Simulation study of helium release in the XFEL tunnel, WUT-ref:#630333/I22-01Slide11

Helium Spill Test in LHC tunnelon-going work

01/11/2013Johan BremerPrototype of ODH system under testInstrumentation for test has been ordered, DAQ-chain being programmedFull instrumentation test by end of NovemberTesting of emptying by pressurization at this moment with LN2Discussion with LHC coordination

First discussion on how to implement future test results on “restricted working areas” will start shortlySlide12

Helium Spill Test in LHC tunnelConclusions

01/11/2013Johan BremerNo consistent data to support length of “restricted working areas” in LHC tunnelExisting models have to be verified with “real life” spilling testNecessary equipment and instrumentation has been identifiedPossibility of collateral damage has been classified as minimalEquipment owners have to be aware of eventual water condensation on their equipment

Cost of test: about 110

kCHF

, without helium (6000 CHF / test

)

Tests

will take place during last week of January in sector 4-5 left of 5, first 300 meter

into the continuous cryostatSlide13