overpressure release VParma TEMSC with contributions from VBaglin PCruikshank MKarppinen CGarion APerin LTavian RVeness Chamonix 3 rd February 2009 ID: 552207
Download Presentation The PPT/PDF document "Insulation vacuum and beam vacuum" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Insulation vacuum and beam vacuum overpressure release
V.Parma ,TE-MSC, with contributions from:V.Baglin, P.Cruikshank, M.Karppinen, C.Garion, A.Perin, L.Tavian, R.Veness
Chamonix, 3rd February 2009
Content:Insulation vacuum:Present overpressure release schemeEvidence from sect.3-4 incidentMaximum Credible Incident (MCI)New overpressure release schemefor sectors remaining coldfor warmed up sectorsBeam vacuum overpressure releaseSummary
Acknowledgements (EN,TE,GS): S.Atieh, J.P.Brachet, P.Coly, M.Duret, B.Delille, G.Favre, N.Kos, T.Renaglia, J.C.Perez, J.M.Geisser, M.Polini, and many others...
1Slide2
Present configuration of pressure relief devices in standard arcs
50m50m100mQuench valves on cold mass circuit (QV): 3 QV, DN50 each, open on quench trigger; CM pressure ≤ 20 bars
Insulation vacuum pressure relief devices (SV):
Designed to keep internal pressure ≤ 1.5 bars, for a helium release with mass flow ≤ 2 kg/s (helium release from cold mass to insulation vacuum without electrical arc) 2 spring-loaded valve devices, DN90 each, 100m spaced Opening at Δp= 70 mbar, full open at Δp= 140 mbars, Experimentally validation on QRL test cellCryostats:
Vacuum vessel, interconnect sleeve bellows: not a pressure vessels according to European Directives (provided Δp≤ 0.5 bars). Design pressure: 1 bars external; 1.5 bars internal Vacuum Barrier. Is a pressure vessel. Design pressure: 1.5 bars; Test pressure: 1.87 bars 2Slide3
Existing pressure relief device
Mounted on SSS 3Slide4
Pressure Forces on SSS with vacuum barrier
Vacuum barrier
jack
2/3 load directly to vessel
1/3 load through support post
Forces
Δ
p =
1.5 bars
across
vac. Barrier
120
kN
(40
kN
through support post, 80
kN
through Vacuum Barrier)
120
kN
taken by 1 jack fixed to
ground
Strength
limits:
Support post
. Load capacity up to 80
kN
(
Eq.to
3 bars) without collapsing (but additional testing needed to confirm value)
Vacuum barrier
: 1.5 bars design pressure, (tested to 1.87 bars). Buckling safety factor ~3, strength limit: ~ 4.5 bars (but testing mandatory to confirm value)
Note:
if support post collapses, Vacuum Barrier collapses, but not necessarily
viceversa
! Slide5
Sect.3-4 incident: Ins.Vac.overpressureQ23Q25
Q24Q26Q27
214 m
(DN90) (DN90)Collateral damage observed in sect.3-4:Primary damage (direct effect of pressure/flow):3 SSS with vac. barrier uprooted and longitudinally displacedFloor break at jack fixations, but also studs brokenMLI damage, sootBellows damage (CM and beam vacuum lines)
Avoidable by limiting pressure rise and improved ground fixationSecondary damage (consequence of SSS displacements):”Tug of War” effect . Damage to
chain of
interconnects/dipoles
Break of dipole support posts and cold masses longitudinal displacement in vessel
1 SSS without
vac.barrier
uprooted and longitudinally displaced
Secondary arcs in damaged interconnects
Additional MLI damage and soot propagation to adjacent vacuum subsectors
Avoidable if primary damage avoided
5Slide6
Development of pressuresG. De Rijk
6Slide7
Pressure estimate from elasto-plastic deformation of interconnect bellows
1055mm DR=20mm1016 mm
Assumptions: Elastic-plastic material, yield stress= 275MPa, 2D FE model with large displacements
Proportional loading Pressure to have DR ~20mm = 7 barsC.Garion7Slide8
Helium mass-flow rateA.Perin
Temperature (K)Hypothesis: Helium temperature given by sensor P4_34:LQOAA_25R3_TT821All helium discharged through 1 hole. No plug major failure.Constant hydraulic diameter 54 mm Total mass of helium = 214 m x 0.026 m3/m x 147.8 kg/m3 = 822 kgEstimated mass flow
Pressure (bar)Time (s)
Recorded data (cold mass)Mass flow (kg/s)Temperature (K)Time (s)Temperature P4_34:LQOAA_25R3_TT821Temperature P4_34:LQOAA_25R3_TT8218Slide9
Evidence in sect.3-4
Other cases: floor broke AND studs F> 120-150 kN ? Q28 3R: weak floor broke, not studs F < 120-150 kN
9Slide10
Maximum Credible Incident (MCI)Slide11
MCI scenarioIn the sect.3-4 incident, the electrical arc has burnt the M3 pipe, the E line (partially), the V2 line and the V1 line (partially).Could an electrical arc at a higher current burn also the M1 and/or the M2 line simultaneously ? With additional arcs on MQ bus-bar ?
In case it occurs, the mass-flow discharged to the vacuum enclosure could increase by a factor 3 (~ 60 kg/s). What about He temperature in vacuum enclosure ?11Slide12
Possible MCI arc damage ?
MCI ?Sect.3-4 incident
L.Tavian12Slide13
Maximum flow for MCIThe pressure evolution of the cold-mass allows to assess the overall mass flow (Sect.3-4: average ~15 kg/s, peak ~20 kg/s)
But we know from visual inspection that additional holes (secondary arcs) has been created by mechanical rupture of an interconnect.What is the part of the total mass-flow due to this mechanical rupture ? If not negligible, mass flow of peak ~20 kg/s is a conservative valueBurning of 3 M lines will create a free opened section of 6 x 32 = 192 cm2.
But the free section available in the cold mass is about 2 x 60 = 120 cm2.
consequently, this section will limit the maximum flow to two times the flow produced by the sect.3-4 incident (~40 kg/s)L.Tavian13Slide14
Overpressure estimatesL.Tavian
(MCI)(sect.3-4)(initial estimate)
14Slide15
What can we do on cold sectors without warming them up?(sect.2-3, 4-5, 7-8 and 8-1) “Making the best use of existing ports”Slide16
Existing ports: all on SSS
Every SSS: 5 ports 4 DN100 ports (2 for vac. equip., 2 for BPM cable feedthrough)
1 DN63 port (for cryogenic instrumentation feedthrough)
Every standard vacuum sub-sector: 4 SSS, i.e. 20 ports: 16 DN 100 ports 4 DN63 portsBPM DN100BPM DN100Vac.inst. DN100cryo.inst. DN6316Slide17
Use of portsLayout drawing LHCLSVI_0020
214 m8 DN 100 ports for insulation vacuum equipment:2 for safety relief devices (VVRSH)2 pumpout ports (VFKBH)1 by-pass pumping group (VPGFA)1 gauge cross (VAZAA)2 blank flanges (VFKBH)8 DN100 ports (not shown in layout) for BPM cable feedthroughs (2 x SSS)
4 DN63 ports (not shown in layout) for cryogenic inst
Use as pressure relief ports
17Slide18
The strategyReplacing clamps with spring-loaded clamps (so-called “pressure relief springs”)
Port acts as an additional relief deviceBlow-off flange, effective full-open area (unlike present valves) General reluctance for safety reasons in applying to instrum.ports: opening by tripping over, BPM on tunnel passage side
“pressure relief springs”
BPM DN100Vac. Equip. DN100Cryo.inst. DN63Use of instrumentation ports should be temporary, until warming up of sectors
18Slide19
Pressure relief spring Patrick Coly
Wim MaanPaul CruikshankCedric GarionMain Functions: Provide leak tightness at initial pumpdown from atm. pressure < 1 mbarl/s. Opening pressure < 0.5 bar Δp Provide adequate sealing Avoid opening due to external forces (e.g. instr.cable forces)Testing of a prototype
Prototype
19Slide20
Status of relief springsProcurement:Relief springs for 432 DN63, 1870 DN100, 1232 DN200 (plus spares)Offer this weekValidate DN63,100, 200 with small pre-series (geometry, installation, opening tests)
Still to define: Flange retention systemProtection measures to avoid hazardous opening (stepping on, hitting…)Safety approval: on-going discussions with GSInstallation: could start from wk 13Input P.Cruikshank20Slide21
Cold sectors, new (temporary) relief schemeKeep existing 2 DN90 relief devicesMount relief springs on 5 DN100 vac. flangesMount relief springs on 8 DN100 BPM flangesMount relief springs on 4 DN63 cryo.instr. flanges
Cross section increase: x 10
SV
SVSV
SV
SV
21Slide22
Overpressure in vacuum vessel
2.83.3L.Tavian
(MCI)(sect.3-4)
(initial estimate)22Slide23
Consequence of pressure above 1.5 bars (1/2)P> 1.5 bars (ΔP>0.5 bars):According to European Directives (EN13458),
vacuum enclosure is a pressure vessel to be treated accordingly. Safety implications being discussed with GS (B.Delille) 1.5 bars< P < 3 bars:Risk of breaking floor and jack fixations
Improve jack fixations to floor (see next talk by O.Capatina):
under a load equivalent to 3 bars (240 kN), no collapsing allowed (but damage and plastic deformations acceptable). Why up to 3 bars? Because at 3 bars support posts become critical. Important: Evidence in sect.3-4 of floor breaking at p<1.5-1.87 bars (120-150 kN is limit of studs)Jack fixations in tunnel tested up to 1 bars (120 kN) only, during vacuum commisionning (atm./vacuum on vacuum barriers) installation when Vacuum Barriers. Not tested at 1.5 bars Floor strenght should be checked too!23Slide24
Consequence of pressure above 1.5 bars (2/2)3 bars<P<4 bars:Strenght of Vacuum Barriers/Support Posts/Jack fixations becomes marginalIf Support Post collapses, Cold Mass moves and collapses Vacuum Barrier
similar chain of events as for sect.3-4, BUT pressure relief from opening of interconnect bellows may not occur, consequences could be more severe than in sect.3-4.Assess the upper limit above 3 bars: rupture testing of supports/VB/jacks fixationsP~ 4 barsStability under external pressure of Plug In Module bellows risk of breaking beam vacuum
24Slide25
New overpressure relief scheme “Adding extra relief devices”To be implemented now on sect.1-2, 3-4, 5-6 and 6-7, and later on remaining sect. when warmed upSlide26
New overpressure relief schemeKeep existing 2 DN90 relief devicesMount relief springs on 4 DN100 blank flangesAdd 12 DN200 new relief devices (1 per dipole) Cross section increase: x 33
SV
SV
SV
SVSV
SV
SV
SV
SV
SV
SV
SV
SV
SV
SV
SV
SV
26Slide27
Overpressure in vacuum vessel
1.221.3OK, well below 1.5 bars design pressure L.Tavian
(MCI)
(sect.3-4)(initial estimate)27Slide28
Additional ports: 1 DN200 on every dipoleCourtesy of TRenaglia
DN200, reasonable upper limit for safe millingTop position is best for safety (personnel, H/W), and for gravity sealing of coverInterconnection sleeve opened for removal of chips and protection of MLI (prevent fire hazard) Left position is best for flow conductance through thermal shield (large openings)
Cross cut on MLI of thermal shield to help prevent plugging 28Slide29
Relief device: detailed viewCourtesy of T. Renaglia
External weld for safety (limited risk of burning MLI) and ease Thick tube for weld quality, and limited distortion of sealing surfaceSt.steel top cover, with O-ring sealingSelf-weight sealing, but spring clamps can be mounted if necessary29Slide30
Trials and qualifications
Trials and qualification stepsW2: Final Design, Material order, 3 off trial nozzles, 1 off cutting tool (ø217.5)W3-4: Welding trial 1 (DMOS in SMA18), Welding trial 2 (QMOS in SMA18 with APAVE), Welding trial 3 (SMI2:MB3118, complete valve and leak tests)
Geometrical check during welding
W5: Production of 20 pre-series valves at CERNW5: Training and qualification of the three intervention teams (Dubna, S-107, S-108)Max.internal T 130°C, 40°C on MLI Thermographic picture30
M.KarppinenSlide31
Provisional Installation Schedule
TotalSector 1-2
Sector 3-4
Sector 5-6Sector 6-7Remarks
W69
9
Surface
W7
69
20
20
20
Tunnel
W8
159
30
30
30
W9
249
30
30
30
W10
339
30
30
30
W11
429
30
30
30
W12
472
14
5
14
10
W13
562
90
W14
616
54
SUM
154
154
154
154
Contract
DUBNA
S-107
S-108
ALL
31
M.KarppinenSlide32
Special cases (1/2)6 DN200 + 4 DN100
L.TavianMid-arc vacuum sub-sectors: ½ length insulation vacuum sub-sector (~100 m)6 dipoles only 6 DN200 relief devices2 SSS 4 DN100
1.8
2.1>1.8 bars needs a 2nd DN200 device on dipoles 32Slide33
Special cases (2/2)DS zones: 20% shorter insulation vacuum sub-sector (~170 m)8 dipoles only 8 DN200 relief devices4 SSS (Q11-Q8), [5 around Pt.3-7 (Q7)] ~ 8 DN100
8 DN200 + 8 DN100
1.41.52
Marginal, >1.5 bars, if T>80K proposed adding 2nd DN200 on dipoles L.Tavian33Slide34
Still pending...Study of overpressure for:Standalone cryo-magnets in LSSTriplets
34Slide35
Radial conductance (area)(passage from cold mass to vacuum vessel)Impedance:Aluminum shielding
MLIConductance:Thermal shield slotsAt support posts (for thermal contractions)At vacuum barriersAt Instrumentation Feedthroughs and diode 100 cm2
1000
cm21000 cm21000 cm2128 cm2128 cm2128 cm2450 cm2
1000 cm21000 cm21000 cm2
1000
cm2
1000
cm2
1000
cm2
1000
cm2
1000
cm2
1000
cm2
TOTAL per vacuum
sub
-
sector
:
12900
cm2
~
100
times
area of
present
over-pressure
valves
~ 10 times
area of
new
overpressure
scheme
for cold
sectors
~
3
times
area of
new
overpressure
scheme
for warm
sectors
Transversal conductance
is
not the «
bottleneck
», if MLI
does
not
restrict
passage
35Slide36
MLI obstruction in sect.3-4
Suction/ripping/clogging through over-pressure valve …yes some clogging at valves, but… full-open DN solution will
be less sensitive
No evidence in sect.3-4 event of full blanket blown apart (Velcro™ fixation holds)36Slide37
Beam vacuum overpressure(work in progress byTE-VSC)Present protection scheme:Rupture disks at arc extremities (mounted on SSS Q8)Damage in sect.3-4 (direct consequence of overpressure)
Pressurized beam tubes (rupture of 1 burst disk)Buckling of beam vacuum bellows (could be secondary damage)Net transport of pollution along beam tubesWill additional burst disk at intermediate positions help?Depends on the ratio of impedance between beem tube and burst disk discharge manifoldUp to what distance does a P of 3 bars die away to vanishingly low values? Work is in progress (R.Veness)If found technically valuable, burst disk can be added at any time (?) at every SSS (ports available with vacuum valves) Approx.cost for all machine ~ 750 kCHF (J.M.Jimenez)Delivery schedulefor large series: 8-10 weeks (P.Cruikshank)
37Slide38
Evidence in sect.3-4ruptured disk
- Internal buckling pressure: ~ 5 bars (relative)- External buckling pressure: ~ 2 bars (not critical: small in plane squirm mode), local critical mode: ~ 9 bars Column buckling due to internal pressureBeam screen bellowsInternal buckling pressure: ~ 3.5 barsExternal buckling pressure: ~ 4 bars
Plug In module bellows
Column buckling due to internal pressureC.Garion38Slide39
Summary (1/2)Evidence from sect.3-4 and MCI:Estimated overpressure in sect.3-4
~7 barsEstimated helium flow rate ~20 kg/s (peak), x10 times initial estimateCollateral damage due high pressure build-up (insufficient pressure relief devices), uprooting of ground fixations of SSS with vacuum barriers, “tug of war”New MCI suggests helium flow rate
~40 kg/s (peak), x2 times sect.3-4 estimate
New overpressure release schemes for MCI (ECR in preparation)Cold sectors, temporary solution with pressure relief springs:Pressure for MCI still high (~3 bars), and above 1.5 bars design pressureCompliance with new safety regulations ?Input for task forces on safety and risk analysisReinforced ground fixations for SSS with vacuum barriers are being studiedFurther testing of support posts and vacuum barriers to assess next structural limit39Slide40
Summary (2/2)Warm sectors, final solution with additional pressure relief devicesAdd 1 DN200 port per dipole (with or without relief springs)
Use of DN100 ports with relief springs, except instrumentation onesPressure for MCI remains within 1.5 bars design pressureFunctional testing of new overpressure scheme: reduced scale test set-up? Special cases:Mid sector and DS sub-sectors require 2 DN200 per dipole to keep pressure below 1.5 barsPending: study of standalones and triplets
Beam insulation vacuum: work still in progressPossibility of adding overpressure devices (burst disks) every 50 m if useful
Other issues: valves?40Slide41
Thank you for your attentionSlide42
Supporting slidesSlide43
Recall of existing clamp functions:Provide leak tightness at initial pumpdown from atmospheric pressure < 1 mbarl/s.Provide leak tightness under nominal vacuum conditions < 1 E-7
mbarl/s.Avoid accidental opening due to external forces:Permanent forces eg cables, gravity,Punctual activities eg cable pulling, climbing on cryostat, equipment handling, tunnel transport, etc.Provide adequate sealing forces/contact surface to overcome joint non-conformities:Flange flatness and form, seal geometry, seal imperfections, scratches, contamination, seal deterioration.
Pressure Relief Springs
43Slide44
Forces on free flange
BPM cablesN, Nm - negligibleInstrumentation cables eg cryo, vac, BPM (except Q7,9 11)< 10 N,< 1 Nm
Flange weight11 NAtmospheric Forcedp 1 bar = 1000 N
Existing clampingforce to limiter ~ 3000 NProposed springloaded clamping10-20% of dp 1 bar ~ 100–200 NDN100 ISO-KWelded flange
Free flange44Slide45
Spring Design
removal forceMax toleranceMin tolerance
o-ring
max typeqtynominal removaldp 1 bar
fingersclampingforce
(N)
(N)
(N)
DN63
6
102
168
509
DN100
8
136
224
991
DN200
16
272
448
3594
45