/
KSTAR Operation Status and KSTAR Operation Status and

KSTAR Operation Status and - PowerPoint Presentation

lindy-dunigan
lindy-dunigan . @lindy-dunigan
Follow
392 views
Uploaded On 2016-05-11

KSTAR Operation Status and - PPT Presentation

Plan for 20092010 July 27 2009 M Kwon and the KSTAR Team National Fusion Research Institute EPICS Technical Meeting NFRI July 2729 2009 Outline Introduction Operation result in 2008 ID: 314597

plasma amp operation ech amp plasma ech operation pre kstar 2009 2010 ionization wall system shot discharge limiter control

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "KSTAR Operation Status and" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

KSTAR Operation Status and

Plan for 2009-2010

July

27

2009M. Kwon and the KSTAR TeamNational Fusion Research Institute

EPICS

Technical

Meeting

,

NFRI

,

July

27-29,

2009Slide2

Outline

Introduction

Operation result in 2008

Operation plan for

2009-2010

Longterm PlanKSTAR CollaborationSummarySlide3

KSTAR objectives and parameters

To develop a steady-state capable advanced superconducting

tokamak

To establish the scientific and technological base for an attractive fusion

reactor as a future energy source

Major radius,

R

0

Minor radius,

a

Elongation,

Triangularity

,

Plasma volume

Plasma surface area

Plasma cross section

Plasma shape

Plasma current,

I

P

Toroidal

field,

B0 Pulse lengthN Plasma fuelSuperconductorAuxiliary heating /CDCryogenic

PARAMETERS

1.8 m0.5 m2.00.817.8 m3 56 m2 1.6 m2 DN, SN2.0 MA 3.5 T300 s5.0H, D-DNb3Sn, NbTi~ 28 MW9 kW @4.5K

KSTAR

6.2 m2.0 m1.70.33830 m3 680 m2 22 m2 SN15 (17) MA5.3 T 400 s 1.8 (2.5)*H, D-TNb3Sn, NbTi73 (110) MW

ITER

* M. Shimada, et al., Nuclear Fusion, vol. 47, pp. s1 (2007)

KSTAR & ITER

KSTAR Parameters

KSTAR missionSlide4

Status of the KSTAR

tokamak

in 2008

KSTAR tokamak

Helium distribution system

Supercritical, 4.5K, 600 g/sVacuum pumping system

VV : 42,400 l/s,

Cryostat : 36,900 l/s

ICRH

30~60MHz, 2 MW, 300s

ECH

84GHz, 500kW, 2s

TV

ECE

Visible spectroscopy

H

Filterscope

mm-wave interferometer

Movable hall probeSlide5

Status of the KSTAR

tokamak

July 10, 2009

New Deck for

Movable Prove and XCSSlide6

Minimum

in-vessel components

were installed for the first plasma.

In-vessel components 2008

ICRH antenna

ECH antenna

Movable hall probe

Inboard limiter

Poloidal

limiter

Glow discharge,

Gas injection

Magnetic Diagnostics

Rogowski

coils

Vessel

curent

monitor

Diamagnetic loop

Flux loop

Magnetic probes

Hall probes

Optical Diagnostics

Visible camera

H

Visible spectroscopy Filterscope ECE mm-wave interferometerSlide7

Most of Magnetic Diagnostics , Full scope of Inboard Limiter

In-vessel components 2009

Inboard limiter

Inboard Limiter BoundarySlide8

In-Vessel Component

1

2

2

3

5

4

6

7

1

Inboard Limiter (

2009

)

2

Divertor (for double null, 20 sec,

2010

)

3

Passive Stabilizer (

2010

)

4

Poloidal Limiter (

2010

)

5In-vessel control coil (2010)6NB armor (NBI-1, Port L, 2010)7

In-vessel Cryopump (2010 ~ 2011)Slide9

Upgrade Sequence of In-Vessel Component

9

1

2

3

4

5

6

7

8

Partial Installation of the Inboard Limiter

Full Installation of the Inboard Limiter

Installation of the IVCC

Installation of the Divertor System

Installation of the NB Armor

Installation of the Passive Stabilizer

Installation of the Poloidal Limiter

Upgrade for 300sSlide10

Operation results in 2008Slide11

Startup scenarios

Startup scenarios were prepared considering the limited capacity of power supply.

Compared between conventional

&

dipole like start up scenariosECH pre-ionization2nd harmonic ECH pre-ionization was achieved at 1.5 T reduced TF field.

Due to ECH pre-ionization, required loop voltage could be lowered to about 2 V.1st harmonic ECH pre-ionization at 3.0 T is planned in 2009.

Startup scenarios and ECH pre-ionization

worked well.

Plasma discharge

Startup scenario

Shot 558

TF = 13.3kA (1.5 T @ 1.6 m)

ECH = 84 GHz, 500kW, 50ms,

Shot 977

TF = 14 kA (1.5 T @ 1.7 m)

ECH : perpendicular launch

ECH pre-ionization test

under TF field only

ECH pre-ionization test

at dipole-like field configurationSlide12

KSTAR succeeded achieving reproducible

tokamak

plasmas

with

strict h/w limits of 1.1 Wb in the first trial by combining a unique magnetic configuration and 2nd harmonic ECH preionization,

Circular ohmic plasma discharge (ECH assisted)Hydrogen plasmaFirst plasma (107 kA, shot No. 794) was achieved on June 13, 2008.

The target of first plasma was achieved.

Plasma discharge

ECH assisted

ohmic

plasma discharge

Basic plasma parameters for first

plasmnaSlide13

ECH

pre-ionization

study (ITPA HPRT)

Pre-ionization study

in terms of

beam

launch direction

ECH pre-ionization test according to beam launch directions

Toroidal

scan : normal,

co- and counter-oblique

injection (+10

0

~ -10

0

)

Vertical scan : (z= +10 ~ -10 cm)

The pre-ionization of oblique beam launch

was

more efficient than the perpendicular

launch

.

ECH antenna

- mirror pivot

R=2800

y=-252 x=-279BtIpNm-portCo-injectionCNT-injection

ECH launch directions

Pre-ionization according to beam launch directionSlide14

ECH

pre-ionization study

ECH power

threshhold

for 2nd harmonic plasma breakdown was about 280 kW.

At least 320 to 350 kW of ECH power was needed for reliable breakdown in KSTAR 1st plasma campaign. The plasma breakdown time has been reduced with higher ECH power.

280 kW(#1078, black)

320 kW(#1079, red)

350 kW(#1080, blue)

ECH pre-ionization according to ECH power

Pre-ionization delay time

No

breakdown

(P

ECH

: 280 kW)

Pre-ionization study

in terms of

beam

powerSlide15

Shot 1127 @ t=543.1

msec

I

pl,mea

= 97.1 kA, Ipl,rec=98.3 kA, Ivv = 59.3 kAzout = -9.1 (cm), Rout = 161.2 (cm), a = 35.2 (cm)

zc = -9.3 (cm), Rc = 164.9 (cm) Good condition no. (7.84 e3) Using all MP’s and FL’s with optimized fitting weight Vacuum vessel and real limiter structure are considered Good agreement with CCD camera

EFiT

Reconstruction

Plasma Current

Zout

RoutSlide16

- The effect of Incoloy is not included

By O. Hopkins

EFiT

Reconstruction

Shot 1127Slide17

Issues for KSTAR

magnetics

KSTAR has an inherent source of magnetization inside the PF & TF coils

Incoloy

908 is the jacket material for superconducting strand Weakly ferromagnetic with max μr~10 (saturation B~1T) Toroidally symmetric but problematic for field-null qualityExperimental findings : Downward shift of plasma Lower measured loop voltage than the calculated by the circuit equations PF coil currents decay faster than the calculated by the circuit equations

=> Need additional up-down asymmetric sources of current and fieldCryostat is a potential source of up-down asymmetry Large current at the lower cryostat will drive plasma downward Other discrepancy might be due to cryostat current also

Incoloy

908

Understanding MagneticsSlide18

A genuine reconstruction code has been developed

to cope with nonlinear magnetization from

Incoloy 908 in CICC and

partially validated with the measurementsstill require better understanding of the magnetic probe measurements and its validation still large discrepancy between the measured and the calculated vessel currentdeveloped analysis tools are directly applicable to ITER TBM analysis

The cryostat is a potential source of up-down asymmetryaccording to the calculations, rather large current flows in the cryostat(~200kA)better agreement with loop voltage measurements with the cryostat circuitpotentially problematic in ITER also

By upgrading and

thorough

validation of the magnetic diagnostics

in next

campaign, these issues will be examined in more quantitative way

Understanding MagneticsSlide19

DC glow discharge cleaning

Glow discharge at zero field condition

at night (H

2 & He)RF discharge cleaning between shots

DC glow is not acceptable due to continuously applied TF field.KSTAR ICRH system (2 MW, 300 sec, 25 -60 MHz) used for discharge cleaning between shots at 30 kW (30 MHz).2 seconds pulse in every 12 seconds for 5-10 minutes just after plasma shot .Wall conditioning (ITPA HPRT)

DC glow discharge using the probe

RF discharge using the ICRF system

Two kinds of discharge cleaning methodsSlide20

Line density variation due to ICRH

He cleaning

ICRH(He)5min

Between shots

Line density decreases

shot by shotICRF-DC was successfully started without major fault due to the appropriate protection system.Line density was affected by the shot to shot discharge cleaning.Exact assessment of residual gas variation due to DC was difficult due to background signals from the pumping lines in RGA system.

Quantitative measurement of wall condition is required with

better-set RGA

system and increasing pulse length of RF power.

RF discharge cleaning effects

856

857

858

RGA signal during DC and plasma shots

Wall conditioningSlide21

Dust

collection

and

analysis

Dust generation was often

observed by visible CCD cameras.Cause : change of heating directions, plasma movement, etc. Events from in-board limiter and MD protectionsCollected dusts at 10 different in-vessel positions using sticky carbon tape.

Large dispersion: 100nm-20um.

Two major peaks at ~100 nm and 2um.

Detected components: C, Si,

Mn

, P, S, Ni, Cr,

Fe

,

Cl

, Ag, Al, Mg

Inboard limiter,

Diagnostics (mirror, etc)

Dust collection and analysis was

possible from

the virgin operation.Slide22

Most of the

targeted values of the 1

st

campaign

were achieved.

Results of the 2008 campaign

Classifications

Target

Achieved

Remarks

Final

Spec.

VV base

pressure

Cryostat base pressure

Total

leak rate

≤ 5.0x10

-7

mbar

≤ 1.0x10

-4

mbar≤ 1.0x10-4 mbar·l/s3.0x10-8 mbar3.0x10

-8 mbar1.7x10-7

mbar·l/sOKOKOK∙SC coil temperature∙Thermal shield temperature (In/out)∙Temperature distribution≤ TF & PF : 5 K≤ 55 / 70 K≤ 50 KTF & PF : 4.48 K51 / 72 K48 KOK

OKOK

∙SC transition temp.∙Joint resistance∙Coil insulation∙TF current ∙TF field at major radius∙PF coil current∙PF Blip periodNb3Sn : 18.3 KNbTi : 9.2 K ≤ 5 nΩ> 100 MΩ≥ 15 kA≥ 1.5 T4 kA≥100 ms

Nb

3Sn : 18±0.2 KNbTi : 9.9±0.1

K

0.5 ~ 2 nΩ> 3,000

MΩ15 kA

1.5 T

4 kA

50 ~ 150 ms

OK

OK

OK

OK

OK

OK

OK

OK

35

kA

3.5 T

25

kA

ECH

for pre-ionization

Plasma current

Plasma duration

Plasma

duration

100 kA

≥ 400 kW (0.2 s)

≥ 100 kA

≥ 0.1

s

480 kW (0.4 s)

133 kA

0.8

6

s

0.33 s

OK

OK

OK

OK

2,000 kA

300 s

300

sSlide23

Operation plan in 2009-2010

Vacuum pumping system operation

Cryo

-facility

operation

Superconducting State

Plasma Exp.

Pumping down / Leak check / Wall conditioning

Cool-down from 300 K to 4.5 K and

warmup

Maintain 4.5 K Slide24

Available operation time in 2009-2010

2009 Operation

2009

1

2

3

4

5

6

7

8

9

10

11

12

2010 Operation

2010

1

2

3

4

5

6

7

8

9

10

11

12

IAEA FEC

In Korea

Vacuum & wall conditioning

Cool-down &

warmup

SC magnet operation

Plasma exp.

Vacuum & wall conditioning

Cool-down &

warmup

Plasma exp.

H/W upgrade

H/W upgrade

SC magnet operationSlide25

System availability for 2009-2010 operation

2008

2009

2010

SC Magnetic system

TF coilsPF coils & leads

15 kA

4 kA

unipolar

Up/Low series

35 kA

4 kA bipolar

Up/Low

series

35 kA

20 kA bipolar

Up/Low separate

(4 more PF PS)

In-vessel system

In-vessel coil

PFC

Wall conditioning

Inboard

limiter

Glow DC, RF DCInboard limiters+ boronizationVertical controlDivertor / limitersPassive stabilizer

+ PFC bakingHeating system

ECHICRHNBILHCD0.5 MW (84 GHz)0.03 MW (30 MHz)0.5 MW (84 GHz)0.3 MW (45 MHz)0.5 MW (84 GHz)0.5 MW (110 GHz)1 MW 1 MW0.5 MWInfra systemGrid Power50 MVA (154 kV)50 MVA (154 kV)100 MVA (154 kV)Slide26

Operational parameters in 2009-2010

2008

2009

2010

Experimental parameters

Peak TF fieldOperation TF field

Flux

Ip

Plasma shape

Gas

1.5 T

1.5

T

~ 1

Wb

< 133 kA

Circular

H

2

(He for DC)

3.5 T

1.5

T, 3.0 T

~ 2

Wb

~ 300 kACircularH2 (He for DC), D23.5 T1.5 T, 2.0 T, 3.0 T~ 4 Wb< 1 MADouble nullH2, D2Control

Plasma control

PF blip & start upIp, Rp , nePF zero-crossingIp, Rp, neIVC controlIp, Rp, Zp, shapeDiagnostics Diagnostic systemsMD/ MMWI/ ECE / Hα/ filterscope/ ViS . TV• MD/ MMWI / ECE / Hα/ filterscope/ Vis. TV• PD / XCS / Soft X-ray / Reflect./ XCS (1 set) / Bolometer (resistive) /• MD / MMWI / ECE/ Hα/ filterscope/ Vis. TV

• PD / XCS / Soft X-ray / Reflect. • TS/ Hard X-ray / Fast neutral / ECEI / IRTV/Fast Ion Loss DetectorSlide27

FY 2008

FY 2009

FY 2010

FY 2011

FY 2012

Operation

(

Vac,CD

& WU)

‘08. 3 ~ ‘08. 8

(6

mon

.)

‘09. 8 ~ ‘09.12

(5

mon

.)

‘10.6 ~ ‘10. 11

(6

mon

.)

‘11. 4~ ‘11. 9

(6

mon

.)

‘12. 2 ~ ‘12. 7 (6 mon.)Experimental GoalsFirst plasma startup2nd Harmonic ECH pre-ionization1st Harmonic ECH Pre-ionizationStartup stabilization

Shaping

control & vertical stabilizationHeating Confinement (L-H)StabilizationHeatingPlasma–Wall InteractionProfile controlRWM, ELM controlOff-axis current driveTargetOperation ParametersBT ~ 1.5 TIP > 0.1 MAtP > 0.1 sTe > 0.3 keVTi ~ 0 keVFlux ~ 1 WbShape ~ CircularGas : H2BT ~ 3 T

IP > 0.3 MA

tP > 2 sTe > 0.3 keVTi ~ 0.3 keVFlux ~ 2 WbShape ~ CircularGas : H2,, D2BT ~ 3 TIP < 1 MAtP ~ 10 sTe ~ 1 keVTi ~ 1 keVFlux ~ 4 WbShape ~ DN(double null)Gas : H2, D2

B

T ~ 3 TIP < 1.5 MA

t

P ~ 10 sTe ~ 1 keV

Ti ~ 3 keVFlux ~ 6

Wb

Shape ~ DN & SN

Gas : D

2

B

T

~ 3 T

I

P

< 2

MA

t

P

> 100 s (0.5 MA)

Te ~ 1

keV

Ti ~ 5

keV

Flux

~ 8

Wb

Shape ~ DN & SN

Gas : D

2

PFC & Wall conditioning

Inboard

limiter (belt)

Gas puff

Inboard limiter (w/o

cooling

)

Boronization

Divertor

/ Passive plate

PFC baking

In-vessel coil

Cryopump

operation

PFC cooling

PFC cooling

Pellet

Magnetic

control

TF : 1.5 T

PF : 4 kA

unipolar

TF : up to 3.5 T

PF : +/-4 kA

TF : up to 3.5 T

PF : +/-10 kA

IVCC : VS, RS

TF : up to 3.5 T

PF : +/-15 kA

IVCC : FEC. RMP

TF : up to 3.5 T

PF : +/-20 kA

IVCC : RMP, RWM

Heating operation

ECH(84G): 0.5MW, 0.4s

ECH(84GHz): 0.5MW,

2s

ICRH(

45MHz

): 0.3MW, 10 s

ECH(84/110GHz): 0.5MW

ICRH(45M

Hz

): 1MW, 10 s

NBI: 1.0MW, 10s

LHCD: 0.5MW, 2s

ECH(84/110GHz): 0.5MW

ICRH(45M

Hz

): 2MW, 10 s

NBI: 2.5MW, 10s

LHCD: 0.5MW, 2s

ECCD(

170G

Hz

):

1MW, 10s

ECH(84/110GHz): 0.5MW

ICRH(

45M

Hz

): 2MW,

300 s

NBI

:5

MW, 300s

LHCD : 1MW, 2s

ECCD(1

70G

Hz

):

1MW, 300s

Diagnostics

MD (77 Ch)/ MMWI / ECE / H

 /

filterscope

/ VS / TV

MD/ MMWI / ECE / H

 /

filterscope

/ VS / TV

PD /

XCS (1 set) / Bolometer (resistive) / Reflect. / Soft X-ray

MD / MMWI / ECE / H

 /

filterscope

/ VS / TV

PD /

XCS / Bolometer / Reflect. / Soft X-ray

Thomson Scattering / Hard X-ray / Fast neutral / IR TV / ECEI

MD / MMWI / ECE / H

 /

filterscope

/ VS / TV

PD /

XCS / Bolometer / Reflect. / Soft X-ray

TS / Hard X-ray / Fast neutral / IR TV / ECEI

MSE / FIR / CES / neutron

MD / MMWI / ECE / H

 /

filterscope

/ VS / TV

PD /

XCS / Bolometer / Reflect. / Soft X-ray

TS / Hard X-ray / Fast neutral / IR TV / ECEI

MSE / FIR / CES / neutron / VUV

MIR

/ BES / CI /

Near-term experiment planSlide28

Research topics in 2009-2010

Power supply control

TF magnet test up to 35 kA ; B

TF

up to 3.5 Tesla @ R=1.8m

PF magnet & power supply control for zero-crossing : Flux up to 2 WeberVertical & radial stability control using IVCC (‘10) Plasma controlPlasma current and position control (Ip, Rp

)

Plasma shape control (

Rp

,

Zp

,

kappa, delta) (‘10)

Magnetic probes & analysis

Refined characterization of the

magnetics

with additional sensors and electron beam system. (quantifying field errors, calibration of magnetic probes)

Understanding the material (Incoloy908) and geometry effects on plasma

MagneticsSlide29

Research topics in 2009-2010

ECH pre-ionization

Full exploitation of 84 GHz &

110 GHz

Gryotron

Further Investigation of ECH assisted pre-ionizationDependence on 1st & 2nd harmonics, injection directions

ICRH heating and RF discharge cleaning

Exploitation of ICRH heating

Exploit RF discharge cleaning between shots

Commissioning of additional heating

hevices

NBI (1 MW), LHCD (0.5 MW) (‘10)

Heating researchesSlide30

Research topics in 2009-2010

Wall conditioning & wall interaction

Quantitative approach on wall conditioning & wall recycling

Hydrogen recycling/retention under different wall condition(

Boronization

, RFGDC, ICRH DC)Characterization of the dust behaviorExperimentsDisruption studiesPossible MHD Studies ;

sawtooth

manipulation, locked

mode

Experiments based on the collected proposals (domestic /international)

Data access and collaboration

Data access, analysis, logging

Remote experiments participation & operation

Other researchesSlide31

Experimental Proposals

37 experimental proposals registered through internet

In 7 categories

System commissioning (5)Magnetic configuration and equilibrium reconstruction (7)

Startup and current ramp-up (4)Diagnostics (4)Heating and current drive (3)Wall conditioning (3)Instabilities (7)Transport and confinement (4)28 domestic / 9 international NFRI (18) Postech (7)

KAERI (3)GA (5)PPPL (2)ORNL (1)Far-Tech (1)Slide32

Remote Experiment (2009, Collaboration with GA)

discussion

discussion

KSTAR site

RSL

H323

Non-PCS parameter confirm

PCS

parameter

input

PCS

Confirm

“Next Shot is ready”

DSL

CMO

Y

N

Run Shot

parameter

Input

/ limit check

Result transfer

Shot analysis

Shot log

Wait for live shot updates

Shot summary put to web portal

EPICS / H.323

MDSplusRemote siteAuthorizationtoolsDeputy session leader (DSL)Remote session leader (RSL)Chief Machine Operator (CMO)Local operators

Assistant

PhysicsOperatorConnection / transferSupportH323 video.PCS remote GUIWeb logbook & summaryPCS wave server RDB serverElectronic authorization layer MDSplusSlide33

Long-term Operation planSlide34

Operation target by 2012

H-mode operation control

Plasma wall interaction research

FEC and RWM control with

ELM suppression using IVCCNTM suppression with ECCD

Key milestones

Physics targets

1

st

KSTAR operation

phase ends

Achieve knowledge on

supeconducting

tokamak

characteristics for H-mode operationSlide35

Long-term plan (mainly by 2017)

Physics target

Targetted

for a milestone of ITER construction completionPlays a role as an

ITER pilotSteady-state operation control H-mode plasma stabilization for long pulseAT mode (high beta) operation achievement with available heating systemsSlide36

Long-term experiment planSlide37

EU Support & Collaboration

Domestic Core Research Centers

World Leading Experts

(International)

Fusion R&D Collaboration (International)

KSTAR Collaboration Framework

EU-WLEs

US-WLEs

JA-WLEs

Profile Diag.

Visualization

(POSTECH)

Reactor Engineering

(SNU)

Heating & CD

(KAERI

)

Edge Diag.

(

Hanyang

U.)

Divertor

& Simulation

(KAIST)

International Collaboration and Experts Participation

ITER Pilot R&D

ITER-IO

Simulation R&D

SciDAC

(US)IPERC (JA), etc.Co-ExperimentsITER MembersNon-ITERUS Support & Collaboration JA Support & Collaboration Slide38

Summary

KSTAR

first-plasma milestone

achieved,

even

with limited hardware capabilities in wall-conditioning, diagnostics, power supply systems etc.2008 operation campaign was accomplished in 5 months without any serious fault. International collaborations were essential to achieve the milestones.To get meaningful results in 2009 & 2010 campaign,Acceleration in hardware upgrade,

Careful system operation and concentrated experiment plan,

Accurate measurement and in-detail understanding on SC

tokamak

operation, and

Stronger domestic and international collaboration are required

.

KSTAR control system played a key role to achieve

first-plasma

milestone.Slide39

Thank you for your attention !

At the beginning of the KSTAR cool-down (April. 3, 2008)