 LCLS-II Cryomodule Shipping Requirements  LCLS-II Cryomodule Shipping Requirements

LCLS-II Cryomodule Shipping Requirements - PowerPoint Presentation

lindy-dunigan
lindy-dunigan . @lindy-dunigan
Follow
355 views
Uploaded On 2020-04-10

LCLS-II Cryomodule Shipping Requirements - PPT Presentation

Brian Hartsell Shipping Review June 12 th 2018 2 General Shipping Configuration amp Procedure Procedure from a high level Electrical and RF checks Beamline vacuum monitor installed Adapters installed into HGRP ID: 776671

shipping vacuum cryomodule lcls shipping vacuum cryomodule lcls review june 2018 frame transport requirement requirements monitored leak caps coupler

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document " LCLS-II Cryomodule Shipping Requirement..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

LCLS-II Cryomodule Shipping Requirements

Brian Hartsell

Shipping Review

June 12

th

, 2018

Slide2

2

General Shipping Configuration & Procedure

Procedure from a high level:Electrical and RF checksBeamline vacuum monitor installedAdapters installed into HGRPTransport caps installedPull vacuum and leak check transport caps, backfill with dry nitrogenInstall cryomodule on transport frame loaded on trailerClose trailer tarp

LCLS-II Shipping Review, June 12, 2018

Slide3

3

Shipping Configuration – Vacuum systems

LCLS-II Shipping Review, June 12, 2018

Insulating vacuum – positive pressure of dry nitrogen, not monitored. 7

psig relief installed.

Beamline (cavity string) vacuum – under vacuum, monitored and logged throughout transport

Coupler vacuum – under vacuum, not monitored

Slide4

4

Shipping Requirements

Shipping requirements are governed by cryomodule acceptance criteria at SLAC (LCLSII-4.1-PP-0703-R1):

LCLS-II Shipping Review, June 12, 2018

Slide5

5

Shipping Requirements

Upon arrival at SLAC:Insulating vacuum is pumped down and leak checked before removing the transport caps.Requirement: insulating vacuum leak rate < 1E-5 torr-liter/second.Pressure of beamline and coupler vacuum will be read.Requirement: beamline and coupler pressure both < 1E-5 mBar.All shock log devices will be read.Requirement: no shocks over 1.5gVisual inspectionIn general, no mechanical damage or deformation.Cryomodule alignment will be checked relative to measurements at originating lab:Requirement: cryogenic piping flange locations within ±2 mm Requirement: Gate valve and mounting post fiducial locations within ±0.2 mm.Cavity RF and electrical checks:Requirement: ≤±10 kHz cavity frequency shift, all electrical connections functional

LCLS-II Shipping Review, June 12, 2018

Slide6

6

Shipping frame requirements

The shipping frame will:Serve as a shock attenuator between the trailer and the cryomodule.Protect the cryomodule from damage.Provide the ability to lift the cryomodule with a crane inside a protective frame.Each frame (3 in total) has been load tested and reviewed as a below the hook lifting fixture.

LCLS-II Shipping Review, June 12, 2018

Slide7

7

Shipping frame overview

The shipping frame is comprised of two weldments, commonly referred to as the inner and outer frames.These frames are separated by wire rope isolators.Space for 38 isolators, 32 currently in use.Natural frequency of the system is ~10 Hz in the gravity direction.

LCLS-II Shipping Review, June 12, 2018

Slide8

A specification is in place that governs the transport criteria and gives expectations for the condition of a cryomodule arriving at SLAC.A transport frame was designed to attenuate shocks and provide a protective cage around the cryomodule for both transport and lifting.

Summary

LCLS-II Shipping Review, June 12, 2018

8

Slide9