Transmission Planning at PJM Interconnection LLC Paul McGlynn Director System Planning PJM Interconnection PJM as Part of the Eastern Interconnection KEY STATISTICS PJM member companies 800 ID: 763176
Download Presentation The PPT/PDF document "Transmission Planning at PJM Interconne..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Transmission Planning atPJM Interconnection LLC Paul McGlynn Director, System Planning PJM Interconnection
PJM as Part of the Eastern Interconnection KEY STATISTICS PJM member companies 800+ millions of people served 61 peak load in megawatts 165,492MWs of generating capacity 183,604miles of transmission lines 62,5562012 GWh of annual energy 793,679generation sources 1,376square miles of territory 243,417area served 13 states + DCexternally facing tie lines 191 27% of generation in Eastern Interconnection28% of load in Eastern Interconnection20% of transmission assets in Eastern Interconnection 21% of U.S. GDP produced in PJM As of 6/1/2013
PJM Backbone Transmission System
Total RTEP
RTEP Development Drivers
Transmission Drivers - Public PolicyGeneration Retirement DriversEPA RegulationsHEDD RegulationsOther Environmental RegulationsGeneration Addition DriversRenewable Portfolio StandardsWind Generation Development Solar Generation Development Marcellus Shale Demand Response / Energy Efficiency Programs
Generation Retirement Announcements As of 7/15/2013
Generation Deactivations
Forecasted Reserves in PJM
Test -- Transmission system’s capability to deliver energy from aggregate of all capacity resources to an electrical area experiencing a capacity deficiency. 7/31/2013 10 PJM©2013 Load Deliverability Test
Strength of the transmission system to ensure that the aggregate of generators in a given area can be reliably transferred to the rest of PJM. 7/31/2013 11 PJM©2013 Generator Deliverability Test
Changing Composition of PJM ResourcesThe “Gasification” of PJM continues…
Composition of Active Queue Projects MW Capacity Value MW Energy Value
Queued Generation
RPS Study Overlay
Questions?