August 05 2013 Startup 2013 Machine Status Proton Source Commissioning and Studies RFQ Injector Line RIL Linac Booster Main Injector Startup and Tuning Power Outages PS3 Power Outage ID: 628708
Download Presentation The PPT/PDF document "All Experimenters’ Meeting" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
All Experimenters’Meeting
August 05, 2013Slide2
Startup 2013Machine Status:Proton Source Commissioning and Studies RFQ Injector Line (RIL)LinacBooster
Main Injector
Startup and Tuning
Slide3
Power OutagesPS3 Power Outage Oil Switch ReplacementImpacts PS3, PW5, & PC3Run on generator for ~1 weekConnect generator Monday, July 29th @ 0800 – 1000Disconnect generator Friday, August 9th @ 0800-1000Slide4
Power FailuresFeeder 46B Wednesday, July 24th @ 2142Impact – Possible F0 ventilation systemFault located between P71 & F4Further isolation and repairs necessarySlide5
Kautz Road SubStationStatusMI backfed from Master SubStationUsing Feeder 45 for MI conventional power which is normally T85 on KRSWe ordered 6+ new surge arrestors (4.7k each) from Hubbell and they were delivered on Friday, July 26
th
Schedule: (Weather Dependent)
Monday, August 5
th
replace T85 surge arrestors
No machine impact (In Progress)Tuesday, August 6th replace T87 surge arrestorsNo beam during work 8-10 hoursAfter replacement, test both T85 and T87
There will be a 20 minute MI conventional power outage to remove the
backfeed
, not scheduled.Slide6Slide7
MI Startup Activities (~1 Week)Turn on power supplies and establish rampsEstablish 8 Gev beamMatch MI8 line lattice with IPM
Tune abort line @8
Gev
Establish 120
Gev
beam Smooth orbits up the ramp
Tune abort line @
120
Gev
High field Orbit smoothing (quad moves)
(Have data for 1
st
)
Requires tunnel access (2x8
hrs
)
Calibrate tune table
MI8 line lattice matching (1st of 2 passes complete)Dedicated beam study Extraction line tune up (NuMI) (Attempting extraction)Tune up for operation Deliver low intensity beam to NuMI beam line for target scansEstimated to take an additional week after MI is tuned up for operations Slide8Slide9
Shutdown 2012Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations Schedule
Direct
link to schedule
-
http
://
www-ad.fnal.gov/ops/schedule.html Slide10
We have removed all of the antiproton equipment, which comes to over 1,400 feet of beamline components.Electron cooling removalStochastic Cooling tanks removal from the 200 and 100 tunnel locations Decommissioned
the two Recycler Pbar
injection and extraction lines (~1,000
ft.
of beam line
components).
The A150 Beam line was decommissioned (~800 ft. of beam line)
More than
~1.3 Million feet
of cable have been pulled to support the new transfer lines and
instrumentation upgrades.
~500,000
feet was a complete replacement of the Recycler BPM
system
~700,000 feet of new cabling for instrument cabling
IPM’s, Toroid's, DCCT’s, Multiwires, Schottkies,
~10,000 ft. of RF cabling
~10,000 ft. of 500 MCM cable
~12,000 ft. of 350 MCM cable~25,000 ft. of correction element cables ~6,000 ft. of radiation damage cable
~
25,000 ft. of kicker system cables
We have installed a new transfer
lines; a new Injection line into the Recycler and a new transfer line out of the Recycler Ring into the Main Injector
New injection line spans from the MI-8 line Q848 location to the Recycler Q104 location
New extraction line spans from Recycler Q230 to Q308 in the MISlide11
Approximately 590 tons of material has been moved~ 40 Tons of lead blankets were installed to reduce the radiation levels to reasonable levels such that work can be completed (~25 tons in the MI30 straight section, ~5 tons in the new injection line and ~10 tons in various other locations around the ring.Installed 3 shielding walls ( 2 for MI-31 stub and 1 at the 304 tunnel location ~ 20 tons each)
~
490
Tons of magnets moved
3
ILAM we moved/relocated
6 3Q120 magnets were removed from the A150 line reworked and reinstalled in the NuMI beam line to replace existing magnets
1 MI wide aperture Quad was relocated
1 new Wide aperture C Magnet was installed in the MI abort line
~40 20 inch Quads were removed from the RR30 Cooling insert
3 ADCW were installed ( main vertical bend Magnets)
Entire Ecool Cooling section and return line were removed
18 20 inch Quads were installed in the RR 30 section
10 20 inch Quads were installed in the new RR extraction line
20 20 inch Quads were relocated/installed in the RR injection line
Removed/installed/relocated a total of 14 cavities
2 old RR RF cavities/6 MI coalescing cavity/ 2 MI studies cavities/ 2 new MI RF cavities and 2 new RR cavities
~30 tons of stands and misc. parts/components were removed and or installedSlide12
Keeping true the Recycler name, we are reusing ~70 percent of the instrumentation, ~30 percent of the vacuum components ~85 percent of the magnetsA completely new 53 MHz RF cavity system was installed into the Recycler
2 New RF cavities were installed a place holder for a third
Relocated
and
repurposed
the 3 existing
Recycler wideband RF cavities into a damper system
.
A
complete rework of the Recycler Abort system to allow full turn proton abort along with gap
clearing.
5 Gap clearing kicker and 2 new Full turn kickers were relocated from the Main Injector to the Recycler
The RR30 straight section was rework from a cooling lattice back to a standard FODO
lattice
~45 Recycler 20 inch quads were removed
~900 feet of beam pipe was removed and reworked for the new Lattice configuration
New insert was prepped for 2.5 MHz RF cavity system to be installed in the Recycler 305-306 region.
Relocated radiation sensitive equipment from the MI/RR 30 straight section to minimize future radiation dose to equipment and Technicians.
MI and RR Coasting Beam safety system
MI and RR DCCT’s
RR schotkies
Installed 2 new 53 MHz in the MI
Relocated 4 RF cavities to make roomSlide13