Douglas Wilhelm Harder MMath Department of Electrical and Computer Engineering University of Waterloo Outline This talk focuses on case studies which have shaped Canadas common law Liability for the tort of negligence ID: 663646
Download Presentation The PPT/PDF document "Precedent Cases in Canadian Common Law" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Precedent Cases inCanadian Common Law
Douglas Wilhelm Harder,
M.Math
.
Department of Electrical and Computer Engineering
University of WaterlooSlide2
Outline
This talk focuses on case studies which have shaped Canada’s common law
Liability for the tort of negligence
Fundamental breaches and the “true construction” approach
Bid and tender contracts: “Contract A”
Equitability in contracts
Implied terms in contractsSlide3
Liability for the Tort of Negligence
First, we look at three cases which defined liability for the tort of negligence
The seminal case was
Donoghue
v.
Stevenson
The significance of disclaimers was defined in
Bryne
v.
Heller
This was upheld in the Superior Court of Ontario with
Wolverine
v.
Noranda
Slide4
Liability for the Tort of Negligence
Donoghue
v.
Stevenson
, 1932
The friend of the plaintiff, Ms.
Donoghue
, purchased a ginger beer at an establishment
Ms.
Donoghue
drank some of the beer as part of a sundae
Before Ms.
Donoghue’s
friend drank any, a decomposed snail was discovered in the bottle
No contract existed between either Ms.
Donoghue
and the establishment or the manufacturer of the ginger beer (the defendant)
The House of Lords, however, decided that the defendant liable for an unintentional tort of negligence Slide5
Liability for the Tort of Negligence
Hedley
Bryne
v.
Heller & Partners Ltd.
, 1964
Without consideration, the defendant provided advice on the creditworthiness of a client of the plaintiff
No contract existed
The defendant gave a favourable response but stipulated that the response was made “without responsibility”
The client went bankrupt costing the defendant £17,000
Heller’s response was found to be negligent misstatement
Despite no contract, the court found that in their professional capacity, the defendants owed a duty of care to the plaintiff
The
only
mitigating factor was that the misstatement was explicitly given “without responsibility”Slide6
Liability for the Tort of Negligence
Hedley
Bryne
v.
Heller & Partners Ltd.
, 1964
This is a fascinating precedence:
The court created a precedence for the duty of care of professionals with regard to the making of statements even outside the scope of contracts
The only reason the court did not enforce this decision was because of the stipulation of “without responsibility”Slide7
Liability for the Tort of Negligence
Wolverine Tube (Canada) Inc.
v.
Noranda
Metal Industries Ltd. et al.
, 1994
A confirmation of
Bryne
v.
Heller
in Ontario
An environmental consultant prepared an audit and assessment
The report included the statement
This report was prepared...for...
Noranda
, Inc. ... Arthur D. Little accepts no responsibility for damages...suffered by any third party as a result of decisions made or actions taken based on this report.
The report was presented to the plaintiff by
Noranda
as part of a business dealSlide8
Liability for the Tort of Negligence
Wolverine Tube (Canada) Inc.
v.
Noranda
Metal Industries Ltd. et al.
, 1994
The assessment was found to be inaccurate and the plaintiff claimed that the defendant owed them a duty of care
The courts found that the disclaimer was sufficient to isolate the defendant from the damages claimed by the plaintiffSlide9
Fundamental Breach
Next, we will look at the concept of a fundamental breach of a contractSlide10
Fundamental Breach
Harbutt's
Plasticine
Ltd.
v.
Wayne Tank and Pump Co. Ltd.
(1970)
House of Lords
The contract with the defendant had the liability limited to £2300
The methods used by the defendant were “thoroughly” and
“wholly” unsuitable for is purpose
The damage to the plaintiff was £170,000
The court found in favour of the plaintiff that the limited liability
could not be used for such serious breachSlide11
Fundamental Breach
Photo Production Ltd.
v.
Securicor Transport Ltd.
(1980)
House of Lords
Harbutt
v.
Wayne
was minimized with this case
An employee of the defendant started a fire which cost the plaintiff £615,000
This was not seen to be a fundamental breachSlide12
Fundamental Breach
Hunter Engineering Co. Inc.
v.
Syncrude
Canada, Ltd.
(1989)
Ontario High Court of Justice
The defendant supplied gear boxes for the plaintiff which failed shortly after installation
The plaintiff claimed a fundamental breach of contract in an attempt to void a limitation clause
The court applies the “true construction” approach of interpreting the contract and found the contract to be clearly wordedSlide13
Fundamental Breach
Tercon
Contractors Ltd.
v.
British Columbia (Transportation and Highways)
(2010)
This involves a breach of a “Contract A”
Bidding was restricted to six proponents; however, one proponent entered into a joint partnership
The plaintiff asserted this was a fundamental breach
The decision of the Supreme Court of Canada was:
“With respect to the appropriate framework of analysis the doctrine of fundamental breach should be ‘laid to rest’.”
The court did however, did indicate the exclusion clause was ambiguous and should be construed
contra
proferentem
Slide14
“Contract A”
The request for bids or tenders has with sufficiently large construction projects become so involved that the request itself has become a contract separate from the final construction contractSlide15
“Contract A”
Imperial Glass Ltd.
v.
Consolidated Supplies Ltd.
(1960)
British Columbia Court of Appeals
The
defendant/offeror made a unilateral mistake in a calculation of a price in a contract
The plaintiff/offeree was aware of the mistake but chose to
accept the
contract
The court found there were moral or ethical questions in the conduct of the offeree but the behaviour was not fraudulent
The contractor was not relieved of his obligations Slide16
“Contract A”
Belle River Community Arena Inc.
v.
W.J.C. Kaufmann Co. et al.
(1977)
Ontario
High Court of Justice
The defendant submitted a bid of $641,603 which was $70,000 lower than intended and attempted to withdraw the bid
The plaintiff accepted the bid of the contractor and had to go to the next lowest bidder
The plaintiff sued for the difference
The court held that there was no contract between the plaintiff and the defendantSlide17
“Contract A”
Ron Engineering et al.
v.
The Queen in right of Ontario et al.
(1981)
Supreme Court of Canada
The
defendant submitted a bid of $2,748,000 which was $750,058 lower than intended
The defendant had given a bid deposit cheque of $150,000
The defendant attempted to withdraw from the tendering and to get the bid deposit back
The Supreme Court of Canada found that the tender contract was separate from the bidding contract and the defendant was required to forfeit the bid depositSlide18
Equitability
We look at some questions of equitability in contractsSlide19
Equitability
Conwest
Exploration Co. Ltd. et al.
v.
Letain
(1963)
Supreme Court of Canada
The contract required
that a company must be incorporated by a certain date for a
n
option to be exercised
The optionee (plaintiff) indicated that the
incorporation could
not be
completed on
time and the
optionor
(defendant) implied the date was extended
The court
estopped
the
optionor
from reverting to a strict reading of the contractSlide20
Equitability
John Burrows Ltd.
v.
Subsurface Surveys Ltd. et al.
(1968)
Supreme Court of Canada
The contract required specific monthly interest payments
The contract indicated if a payment is overdue after 10 days, the full principal amount would be immediately due
The plaintiff began to regularly make payments which were more than 10 days late but which were still accepted
Without notification, the defendant reverted to the original terms of the contract and attempted to collect on the principal
The court estopped the defendant from enforcing the strict terms of the contractSlide21
Equitability
Owen Sound Public Library Board
v.
Mial
Developments Ltd. et al.
(1979)
Ontario Court of Appeals
The owner/plaintiff was required honour payment certificates issued by the architect within seven days
The plaintiff requested a document from a subcontractor to be sealed
The defendant agreed but did not obtain the seal until after the seven-day time limit passed
The defendant claimed a breach of contract
The court estopped the defendant from a strict interpretation of the contractSlide22
Implied Terms
Finally, we conclude two cases which define the implied terms of a contractSlide23
Implied Terms
The Moorcock
(1889)
England
A ship was docked and when the tide went out, the ship was damaged
The contract did not have an obligation that the ship would be safe while the ship was moored
The judge found that the safety of the ship was an implied term in the contract
“...
what the law desires to effect by the implication is to give such business efficacy to the transaction as must have been intended at all events by both parties who are business men; not to impose on one side all perils of the transaction, or to emancipate one side from all the chances of failure, but
to make each party promise in law as
much,
at all events as it must have been in the contemplation of both parties that he should be responsible for in respect to those perils or chances
.”Slide24
Implied Terms
TBCSlide25
Outline
This talk reviewed cases from five aspects relevant to professional engineers
Liability for the tort of negligence
Fundamental breaches and the “true construction” approach
Bid and tender contracts: “Contract A”
Equitability in contracts
Implied terms in contractsSlide26
References
[1]
D.L. Marston,
Law for Professional Engineers
, 4
th
Ed., McGraw Hill Ryerson, 2008.
[2]
LexUM
, Judgements of the Supreme Court of Canada,
http://csc.lexum.umontreal.ca/en/
, Faculty of Law, University of Montreal, 2010.Slide27
Copyright and Disclaimer
These slides are Copyright © 2010 by Douglas Wilhelm Harder.
All rights reserved.
These slides are made publicly available on the web for anyone to use
No warranty is given that any information in these slides is correct
The use of these slides in studying for the PPE is fully at your own risk
If you choose to use them, or a part thereof, for a course at another institution, I ask only three things:
That you inform me that you are using the slides,
That you acknowledge my work, and
That you alert me of any mistakes which I made or changes which you make, and allow me the option of incorporating such changes (with an acknowledgment) in my set of slides
Sincerely,
Douglas Wilhelm Harder,
MMath
dwharder@alumni.uwaterloo.ca