API 17N Subsea Production System Reliability and Technical Risk Management API 17N Subsea Production System Reliability and Technical Risk Management

API 17N Subsea Production System Reliability and Technical Risk Management - PowerPoint Presentation

olivia-moreira
olivia-moreira . @olivia-moreira
Follow
344 views
Uploaded On 2019-11-01

API 17N Subsea Production System Reliability and Technical Risk Management - PPT Presentation

API 17N Subsea Production System Reliability and Technical Risk Management Don Wells Hess Corporation History Status Document released in 2009 Specificatio n contains Life Cycle Process LCP Define Plan Implement Feedback ID: 761788

cycle detail document amp detail cycle amp document plan management life change dpif level implement define lcp process dual

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "API 17N Subsea Production System Reliabi..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

API 17NSubsea Production System Reliability and Technical Risk Management Don Wells Hess Corporation

History / Status Document released in 2009 Specificatio n contains:Life Cycle Process (LCP)Define, Plan, Implement, Feedback (DPIF) Loop12 Key Practices (KP)Technology Qualification ProcessTechnology Readiness Level

Why Change? BSEE Wants: Prevent Prescriptive Standards Self-regulation by the IndustryIssues with 17N:Operational Goals & RequirementsUnbalanced Life Cycle ProcessesTechnology Readiness Level Use & Implementation

Plan / Path Forward Process Split into 5 subgroups Industry LeadersCommon TemplateIntroduce IM into the scope of 17N:Define IMExpand the Life Cycle ProcessesReassessment through remediationDefine TRL progression

Detail Expand the LCP Provides balance and depth to the document Communication of goals & requirements 5

Detail Change to a Dual- DPIF LoopDefine – Plan – Implement - FeedbackAdd Remediation cycle Facilitates Integrity Management

Detail

Detail

Detail Change to a Dual- DPIF loopAdd Remediation cycle Facilitates Integrity Management

Next Remaining challenges: Incorporating Human Factors Decommissioning (Well Abandonment)Document MatrixTechnology Qualification Appendix17N is currently in first edition draftingFinal Draft Review late-Q2 2013Peer & Industry Review Q3 2013Submittal Planned Q4 2013