2642013 25413 ALICE TB Status of LS1 activities ATauro 2 LS1 plan 2013 Weeks Remove plug mobile shielding open doors 89 Prepare for PHOS extraction remove RB24 beampipe and PMD 10 ID: 499627

trd p2tech week altead p2tech trd altead week dcal ls1 side tue phos tauro install meeting mon remove planning

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "LS1 planning meeting" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

LS1 planning meeting

26.4.2013Slide2

25/4/13 ALICE TB

Status of LS1 activities - A.Tauro

2

LS1 plan

2013

WeeksRemove plug, mobile shielding, open doors8-9Prepare for PHOS extraction, remove RB24 beampipe and PMD10Remove PHOS cradle and modules, transfer TOF crates on SF11-13Modify L3 services and install YP for TRD1714Modify L3 services, remove TRD17 and rework LV distr. TRD 7-8-10, DCal tests in SXL215-19Modify L3 services, open low-beta and swap Q5L8 magnet, DCal tests in SXL220-23Swap PHOS beams with DCal beams25-28 (tbc)DCal and PHOS services (1/2)31-33Contingency34-35 (August)Install DCal Cradle36-38DCal and PHOS services (2/2)39-40Open Days – 27-28-29/939-40Install 2 1/3 DCal modules41Install 3 DCal modules (C-side)42-43Rework LV distr. TRD11-15-16Two weeks between 44 and 51Xmas pause52-1

Done

Done

Done

Done

OngoingSlide3

25/4/13 ALICE TB

Status of LS1 activities - A.Tauro

3

LS1 plan

2013 – detailed plan weeks 18-30WeeksModify L3 services18Modify L3 services, TRD1019Preparation for low-beta opening, DCal tests in SXL2 (?), drill holes L3 (C-side)20Open low-beta start 21-521Swap Q5L8 magnet 29-30-31/5, Install UPSes22Close low-beta2324Swap PHOS beams with DCal beams, TRD and TPC tanks (1w)25Swap PHOS beams with DCal beams, CR1 racks (2d)26Swap PHOS beams with DCal beams27Swap PHOS beams with DCal beams282930Slide4

25/4/13 ALICE TB

Status of LS1 activities - A.Tauro

4

LS1 plan

2014

WeeksInstall 4 PHOS modules (incl.pre-commiss.)2-5Install 3 DCAL modules (A-side)6-7Install top/bottom counterweights8Remove comp. magnet and Suspend Miniframe9-11Install TRD12-13-14 with yellow platform (bottom)12-14‘Un-suspend’ Miniframe15-16Reinstall TRD1717Concrete walls & TRD installation frame18-19Install TRD4-5 (top) & counterweights20-21Remove TRD infrastructure22Reinstall PMD, ZEM and comp. magnet23Reinstall and bakeout RB24 beampipe24-25----Close plug, mobile shielding 26-29Slide5

Activities weeks 18, 19 & 20

26/4/13

LS1 planning meeting - A.Tauro

5Slide6

Access situation

No access restrictions foreseen

26/4/13

LS1 planning meeting - A.Tauro

6Slide7

Week

15 (8-14/4)

UX25:

TRD + P2tech: take out TRD17 (Mon) – L3 access from O-side only

P2tech + ALTEAD: move L3 staircase from O-side to I-side (Tue)

P2tech ALTEAD: install blocks + rails yellow platform on O-side (Tue)P2tech + ALTEAD: install yellow platform on O-side (Tue)TRD + ALTEAD: take out TRD7 (Wed)TRD: modify TRD7 in Low-Beta (Thu)TRD + ALTEAD: reinstall TRD7 (Fri)TRD + ALTEAD + P2tech: remove TRD8 (Sat)TRD: modify TRD8 in Low-Beta (Sun)Muon TRK: work on CH6L and CH5R (whole week)BE-ABP-SU: survey babyframe, TRD feet and A-side beampipe flange after each TRD removal (whole week)L3:TOF + PH-DT (gas): check C2H2F4 tightness (Mon)P2tech: L3 services modifications (whole week)TPC work on A-side (Tue ?)Surface:P2tech: load test DCal extension ribs (Mon)TRD + ALTEAD: move TRD17 to blue frame (Mon-Tue)P2tech + ALTEAD + Nantes: DCal insertion test in SXL2 (60 and 40deg ?) (Tue-Fri)Removal barracks 6120 (HLT), 6121 (MTR) and 6122 (MTG) (Mon-Tue)26/4/13LS1 planning meeting - A.Tauro7Slide8

Week 16 (15-21/4)

UX25:

TRD + P2tech: reinstall TRD8 (Mon)

P2tech + ALTEAD: remove blocks and install rails yellow platform on O-side (Mon)TRD + ALTEAD: take out

TRD10 (Tue)TRD: modify TRD10 in Low-Beta (Wed)TRD + ALTEAD: reinstall TRD10 (

Thu)Muon TRK: work on CH6L and CH5 R (whole week)FMD + P2tech: modify 2 FMD1 cooling pipes (miniframe)P2tech: install survey plate RB26 sideP2tech + ALTEAD: remove ADC + BCM C-sideFire brigade test: ‘pompe relevage’ (Wed)L3:P2tech: L3 services modifications (whole week)cut and remove 20 inox pipes along the PHOS (I-side) beamSurface:ALTEAD + P2tech: modify DCal infrastructure SXL2 (whole week)P2tech: install ZDC fences in SXL2 (provided by ALTEAD)SDD: swap SuperCarlosRX boards in CR4 (whole week)26/4/13LS1 planning meeting - A.Tauro8Slide9

Week 17 (22-28/4)

UX25:

P2tech: move baby-frame (Wed)

ALTEAD + P2tech: modify TRD infrastructure (Wed-Thu)TRD + P2tech:

TRD10 extraction (Thu)Muon TRK: work on CH6L and CH5 R (whole week)DGS-RP: RAMSES maintenance

BE-ABP-SU: survey UX25<->RB26 (Tue-Thu)L3:P2tech + SPD: drill filter SR3P2tech: L3 services modifications (whole week):Remove 4 PHOS cooling pipesRemove false floor (O-side) and modify the supports for the cooling pipes (interference with the new beams)Install new cable tray for the cables which were liftedSurface:P2tech + ALTEAD + Nantes: DCal and PHOS insertion test in SXL2 (0deg) (Tue-Fri)LHC tunnel:ZDC: remove both detectors (Mon-Tue)26/4/13LS1 planning meeting - A.Tauro9Slide10

Week 18 (29/4-5/5)

UX25:

TRD: modify TRD10 in Low-Beta

(Fri-Sun)Muon TRK: work on

ST4 (whole week)BE-ABP-SU: survey UX25<->RB24 (Mon-Tue)

P2tech: remove/reinstall steel plates RB24 to allow for survey measurement (Mon-Tue)P2tech: help for extraction and reinstallation of TRD11 (Thu-Fri)ACO: exchange old PMTs and check the functionality (mechanics, alignment, optical coupling) of the complete 60 ACO module system (start on Wed – several weeks)P2tech: remove CO2 bottles from UX25 (C-side, level 0)L3:P2tech: install new L3 ladders (top part, access from scaffolding)Surface:ALTEAD: move ALICE stuff from SX2-SA2 to b.185 (tbc)26/4/13LS1 planning meeting - A.Tauro10Slide11

Week 19 (6-12/5)

UX25:

TRD + P2tech: reinstall TRD10

(Mon)ALTEAD + P2tech:

removal of all equipment from cavern: rotator + control rack + tookboxes, YP, test equipment (1 rack, 1 box) (Tue-Wed)P2tech: reinstall L3 staircase (O-side)

(Wed)Muon TRK: work on ST4 (whole week)L3:P2tech: install new gangway (I-side)P2tech + SPD: drill SPD filter (tbc)26/4/13LS1 planning meeting - A.Tauro11Slide12

Week 20 (13-19/5)

UX25:

ALTEAD: open

low-beta and swap Q5L8 magnetMuon

TRK: work on ST4 (whole week)L3:

P2tech: P test TRD pipesP2tech: start LV consolidation (TRD-TPC-TOF) O-side (whole week)Ouvaroff: remove scaffolding inside L3 (Fri)Surface:DCal + ALTEAD + P2tech: test in SXL226/4/13LS1 planning meeting - A.Tauro12Slide13

Visits in the coming weeks

26/4/13

LS1 planning meeting - A.Tauro

13Slide14