DAM AND POND No 3 DAM REHABILITATION PROJECT Village of Tuxedo Park Meeting March 15 2017 Critical Dam Safety Criteria Wee Wah Lake Dam Is Spillway Capacity sufficient to pass SDF 50 of PMF ID: 598712

auxiliary spillway amp dam spillway auxiliary dam amp improvements contract permitted drawings wee service wah wall crest left discharge

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "WEE WAH LAKE" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

WEE WAH LAKE

DAM

AND POND No. 3 DAM REHABILITATION PROJECT

Village of Tuxedo Park

Meeting

:

March 15, 2017Slide2

Critical Dam Safety Criteria

Wee

Wah

Lake Dam

Is Spillway Capacity sufficient to pass SDF (50% of PMF)

Stability of the concrete gravity and earthen embankment

Can

outlet works effectively drawdown the pool level in event of dam emergency

Slide3

Wee

Wah

Lake Dam

Earthen Embankment

Wee

Wah

Lake

Service Spillway

Auxiliary Spillway

Wee

Wah

Road (Crest of Dam)

Stop Log Gate

Left Abutment

Right Abutment

Stilling BasinSlide4

Contract Drawings & Permitted Improvements

Clear Brush and Large

Trees and Flatten D/S Slope, Provide Drainage and MonitoringSlide5

Contract Drawings & Permitted Improvements

Construct Low Level Outlet w/in Service Spillway Slide6

Contract Drawings & Permitted ImprovementsSlide7

Service Spillway

Service Spillway Weir Currently at El. 492.5’, New El. 492’

Service Spillway (Crest El 496.9’)

Service Spillway & LLOSlide8

Repair and Improve

Stability of Auxiliary Spillway, M

itigate Seepage

Discharge

through Floor of Spillway Structure

Contract Drawings & Permitted ImprovementsSlide9

Auxiliary Spillway (Left Side)

Auxiliary Spillway Weir El. 493.0’ currently, new crest to El. 492.5’

Auxiliary Spillway Training WallSlide10

Auxiliary Spillway (Left Side)

Leakage Through Auxiliary Spillway

Auxiliary Spillway Weir El. 493.0’

Auxiliary Spillway Training WallSlide11

Auxiliary Spillway (Right Side)

Leakage Through Auxiliary Spillway

Service Spillway

Auxiliary Spillway Weir

El. 493.0’Slide12

Auxiliary Spillway (Lower Floor)

Seepage Discharge through Auxiliary Floor

Reinforced Concrete Slabs over Pore water Relief Wells

Auxiliary Spillway Stone/Masonry FloorSlide13

Contract Drawings & Permitted ImprovementsSlide14

Contract Drawings & Permitted Improvements

Construct

Parapet Wall along Crest of

DamSlide15

Parapet Wall

Left Abutment

Wall Alignment

Parapet Wall Along Right Side of RoadSlide16

Parapet Wall

Contract Drawings & Permitted Improvements

Wee

Wah

Road (Dam Crest) at approx. El. 498Slide17

Pond No. 3 Dam

Earthen Embankment

Third Pond

Primary Spillway

Low Level Outlet Channel Beneath Splash Pad

(Crest of Dam)

Left Abutment

Right Abutment

Discharge Channel to Wee

Wah

LakeSlide18

Critical Dam Safety Criteria

Pond No. 3 Dam

Is Spillway Capacity sufficient to pass SDF (the 100-yr Storm)

Structural Stability of the stone masonry and earthen embankment segments of the dam.

Can

outlet works effectively drawdown the pool level in event of dam emergency

Slide19

LLO Siphon System

Contract Drawings & Permitted Improvements

Flow Priming and Control Vault

Discharge

IntakeSlide20

LLO Siphon System

Contract Drawings & Permitted Improvements

Flow Priming and Control Vault

Discharge

IntakeSlide21

Contract Drawings & Permitted Improvements

Sound Mortar

Open Masonry Joints

Repointing Stone MasonrySlide22