/
VSC SMACC Status Report VSC SMACC Status Report

VSC SMACC Status Report - PowerPoint Presentation

phoebe-click
phoebe-click . @phoebe-click
Follow
432 views
Uploaded On 2016-08-08

VSC SMACC Status Report - PPT Presentation

Paul Cruikshank on behalf of TEVSC colleagues amp AL4030 Consortium S133 1 Paul Cruikshank TEVSC VSC SMACC Status Report LSC ID: 437830

status vsc leak smacc vsc status smacc leak leaks report paul cruikshank lsc 2014 test amp support qrl pumping

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "VSC SMACC Status Report" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

VSC SMACC Status Report

Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133)

1

Paul Cruikshank TE/VSC - VSC SMACC Status Report - LSC, 11/04/2014

W

bellows leaks

i

nternal

leaks

k

flexibles

leaks

i

nsulation

vacuum leaks

- LEAKS teamSlide2

VSC SMACC Status Report- ContentsSMACC DashboardsVSC Insulation Vacuum StatusM leak testW leak testVSC Cold Vacuum OverviewSIT & DFBAPumping pipesk flexibles

Known leaks & QRLLeak overviewSummary

2

Paul Cruikshank

TE/VSC - VSC SMACC Status Report -

LSC, 11/04/2014Slide3

LS1 arc splices dashboard - simplified Status table for Splice train3Paul Cruikshank TE/VSC - VSC SMACC Status Report - LSC, 11/04/2014Slide4

LHC Insulation Vacuum Status - 11/04/20144Paul Cruikshank TE/VSC - VSC SMACC Status Report - LSC, 11/04/2014Slide5

M Leak Test> 1400 M welds leak testedLeak testing rate follows M weld delivery rate13 leaks identified in 6.5 sectorsMME analysis of each case – reported LSC by Said

Several needs are often combined –

eg

QRL validations with SMACC works - Evacuation and backfilling of line C or line D headers for QRL repair validation,- Evacuation and backfilling of cold mass volumes in case of SMACC NC repairs (M line, diode,

etc),-

Evacuation and backfilling of cold mass volumes for M lines series tests- Evacuation

and backfilling for specific circuits related to special intervention repairs (eg line k, Q5L8, DFBAK, DFBAO, SSS replaced in S3-4, etc.).- Local actuation of service module valves if remote actuation is not possible.- (0.5 x design pressure) configuration following the pressure test.- Pressurization/evacuation of headers during post PT leak localization and repair.

Without this help leak testing would be slower – VSC acknowledges the support & flexibility of CRG team

5

Paul Cruikshank

TE/VSC - VSC SMACC Status Report -

LSC, 11/04/2014

Cryo

AssistanceSlide6

W Leak Test1001 W bellows leak tested.A few issues with W tightnessO-rings out of placeO-ring flatteningO-ring cleanliness

Excellent reactivity/pro-activity of W coordination to resolve problems.Many W reopenings required:

W leaks, internal leak search, diode repairs, magnet alignment,

Other ventings – DN200, vac inst

, BPM, flap valve, etc

So far, 74% of pumped volumes needed venting and re-pumping

6

Paul Cruikshank

TE/VSC - VSC SMACC Status Report -

LSC, 11/04/2014

Flattening of

o-ring

observed in a few interconnects,

make statistics and use spare

o-ringSlide7

LHC Cold Vacuum - Activities Overview Status table for overall activities7

Many VSC activities in parallel‘M leak tests’ & ‘W leak test’ progressing well.Strategy to treat some NC until after PTest

eg W leaks, internal leaks…..

Other VSC consolidation activities in shadow. Paul Cruikshank

TE/VSC - VSC SMACC Status Report - LSC, 11/04/2014

2 air leaks at foot cradles to solveSlide8

SIT Leak Test SupportSignificant leak test support effort, > 730 leak tests so farLarge flexibility to deal with planning – mainly NC follow-up nowVery good collaboration with MSC teams 8

Paul Cruikshank TE/VSC - VSC SMACC Status Report - LSC, 11/04/2014

Test type

QuantitySlide9

DFBA Leak Test SupportDFBA activities coming to an endMain activities to do : DFBAO, DFBAK….Helium leak to IV near to DFBAK in subsector A8L6 ?? 9

Paul Cruikshank TE/VSC - VSC SMACC Status Report - LSC, 11/04/2014

DFBAO

SHM-HCM

c

lamshell

test Slide10

BV Pumping Pipe Damage10

Paul Cruikshank TE/VSC - VSC SMACC Status Report - LSC, 11/04/2014

5-6

6-7

7-8

8-1

1-2

2-3

3-4

4-5

Damage

0

0

4

3

6

2

9

0

Consolidated or changed

-

-

4

3

4

2

5

-

Status of non-conformities, courtesy

C.Garion

Typical damages on pumping hoses

Consolidation with a reinforcement sleeve Slide11

k Flexible IssuesRecall:Braid damage – > use-as-is, proceed to W closure and perform global leak test at 1 bar heliumShocks, compression, – > exchange preventatively before W closureWhere are we:k & M2N flexibles

procured52 NC opened before W closure – of which 29 exchanged – of which 2 leaking (18 of 29 tested)Additionally, 7 have been found leaking after W closure – not part of 52 NC (on 4.5 sectors)

ICIT support – detailed inspection and NC opening

EN/MME support - analysis by Alexandre Gerardin.

11

Paul Cruikshank

TE/VSC - VSC SMACC Status Report -

LSC, 11/04/2014Slide12

Insulation Vacuum Leaks pre-SMACC12Paul Cruikshank TE/VSC - VSC SMACC Status Report - LSC, 11/04/2014

‘Known’ and ‘LS1 start’ helium leaks eliminated, except…..

Triplet 5L – use-as-is

23R8.M – 2 leaks already eliminated in subsector – signal still present – on-goingDFBAK – awaiting re-closure to measure.

Hugh work by VSC, MSC, CRG, MME, MEF teams.Slide13

Helium leak elimination & status13Paul Cruikshank TE/VSC - VSC SMACC Status Report - LSC, 11/04/2014

1 E-7 mbarl/s

Cryosorption

pumpingContinuous turbo pumping

Additional turbo pumping

Cannot be pumped

1 E-5

mbarl

/s

1 E-2

mbarl

/s

1 E-4

mbarl

/s

Helium Leak

rate

i

n subsector

(Cold

,

RT)

5

QRL leaks

1

cryomagnet

leak( S34)

1

QRL leak

17

cryomagnet

leaks

Triplet

5L – use-as-is

DFBAK – to do

(DFBA CL

flexibles

in 2009)

A8R6.M

QRL

ssH

7-8

Several others pre-LS1

Created

in

thermal

transients

1

QRL

leak (S45)

A23R8.M

– on-goingSlide14

SummaryVSC SMACC progress is close to baseline planningSIT & DFBA vac support is coming to the endLS1 leaks have to be dealt with in parallel to series workCollateral damage to k flexibles still persists

Collateral damage to pumping pipes solvedW leaks are understoodReactivity to NC remains good

Known and QRL leaks (almost) eliminated

Risk of helium leaks after P.Test or cooldown

cannot be excludedExcellent support from all – MSC, CRG, EN/MME & MEF, BE-OP….

The work goes on…………

14

Paul Cruikshank

TE/VSC - VSC SMACC Status Report -

LSC, 11/04/2014Slide15

 Other issues - back-up slides15Paul Cruikshank TE/VSC - VSC SMACC Status Report - LSC, 11/04/2014Slide16

Phase 1 – Air to IV leaks0-ring16

MB vessel

a

t central foot

x 3

F

oot flange

o-ring

Connector

feedthrough

Jumper

weld/material

Q7L2

Q29R2

Q21L3

Q21R3

Q33R7

Status for LHC arcs

S5-6

S4-5

S6-7

S7-8

S1-2

S8-1

S3-4

S2-3

Air

leaks (identified to component)

4

5

4

4

8

5

3

6

Paul Cruikshank

TE/VSC - VSC SMACC Status Report -

LSC, 11/04/2014Slide17

LT Phase 1 – internal leak types 17

M weld or collar (x3)

M2N flexible (x3)

K collector (x4)

QBBI.8L7, QQBI.22L7, QBBI.B34L7, QBBI.B21R6

K flexible (x3)

QBBI.B26L3, QBQI.9R2, QBEI.11R3

QQS current leads (x1)

QBQI.9L2 (Q8)

QQBI.13L6 (M3)

QQBI.7R5 (M2)

QBBI.A29L4(M3)

QBQI.18R5

QBQI.26R7

QBQI.33R3

Paul Cruikshank

TE/VSC - VSC SMACC Status Report -

LSC, 11/04/2014